17336 W COLLINS ST 91316

Certificate Information: 17336 W COLLINS ST 91316

Application / Permit
17014-20000-06657
Plan Check / Job No.
B17VN19854
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
36'-10" x 45' IRREGULAR SHAPED ADDITION TO REAR OF SINGLE FAMILY DWELLING; 19'-9" X 10'-11" ADDITION TO FRONT OF SINGLE FAMILY DWELLING TO ENLARGE GARAGE AND ADD FOYER; REMOVE 10' X 40'-6" OF FAMILY ROOM; INTERIOR REMODEL; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS
Permit Issued
Issued on 2/15/2018
Issuing Office
Valley
Current Status
CofO Issued on 4/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2017 APPLICANT
Assigned to Plan Check Engineer 1/4/2018 SELLA BENYAMIN
Corrections Issued 1/10/2018 SELLA BENYAMIN
Quality Review Completed 1/11/2018 STEVEN KIM
Green Plans Picked Up 1/11/2018 APPLICANT
Building Plans Picked Up 1/12/2018 APPLICANT
Plan Check Approved 2/15/2018 SELLA BENYAMIN
Issued 2/15/2018 LADBS
CofO in Progress 4/15/2021 STEVEN BACK
CofO Issued 4/28/2021 JOHN JANSON
Permit Finaled 4/28/2021 JOHN JANSON

Permit Application Clearance Information

Low Impact Development Cleared 1/29/2018 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 1/30/2018 EDUARDO PEDROZA
Roof/Waste drainage to street Cleared 1/30/2018 EDUARDO PEDROZA
Sewer availability Cleared 1/30/2018 EDUARDO PEDROZA
Green Code Cleared 2/14/2018 MICKEY YAMASHITA

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C21234 22129 BRYANT ST      CANOGA PARK, CA

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/22/2018 Not Ready for Inspection BRYAN MEYER
Footing/Foundation/Slab 9/7/2018 Partial Approval BRYAN MEYER
Excavation/Setback/Form/Re-Bar 10/1/2018 Partial Inspection BRYAN MEYER
Footing/Foundation/Slab 10/2/2018 Approved BRYAN MEYER
BUILDING-Rough-Frame 10/5/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 10/5/2020 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/7/2020 Not Ready for Inspection STEVEN BACK
Insulation 10/7/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval RONALD COWAN
PLUMBING-Rough 11/9/2020 Not Ready for Inspection RONALD COWAN
BUILDING-Rough-Frame 11/19/2020 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 11/19/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Corrections Issued STEVEN BACK
Green Building Rough 11/19/2020 Not Ready for Inspection STEVEN BACK
HVAC-Rough 11/19/2020 Approved STEVEN BACK
MERV13>=Rough 11/19/2020 Approved STEVEN BACK
PLUMBING-Rough 11/19/2020 Approved STEVEN BACK
Verify Sprinkler Sign Off 11/19/2020 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/30/2020 Approved STEVEN BACK
Interior/Exterior Lathing 11/30/2020 Partial Approval STEVEN BACK
Shower Pan 11/30/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 12/7/2020 Approved STEVEN BACK
Green Building Rough 12/7/2020 Not Ready for Inspection STEVEN BACK
Verify Sprinkler Sign Off 12/7/2020 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 12/8/2020 Not Ready for Inspection STEVEN BACK
Green Building Rough 12/8/2020 Approved STEVEN BACK
Insulation 12/8/2020 Approved STEVEN BACK
Drywall Nailing 12/11/2020 Approved STEVEN BACK
Interior/Exterior Lathing 12/11/2020 Approved STEVEN BACK
ELECTRICAL-Final 1/12/2021 Not Ready for Inspection VINCENT HANLEY
Service/Power Release 1/15/2021 Approved VINCENT HANLEY
Final 2/25/2021 Corrections Issued STEVEN BACK
Green Building Final 2/25/2021 Not Ready for Inspection STEVEN BACK
MERV13>=Final 2/25/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/25/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 2/25/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 3/11/2021 Approved STEVEN BACK
Final 3/11/2021 Corrections Issued STEVEN BACK
Green Building Final 3/11/2021 Approved STEVEN BACK
Verify Sprinkler Sign Off 3/11/2021 Approved STEVEN BACK
Final 4/6/2021 Corrections Issued STEVEN BACK
Final 4/15/2021 OK to Issue CofO STEVEN BACK