- CONVERT (E) 19'-2" X 19'-11" ATTACHED GARAGE AND ADD 9'-3" X 11'-9" BEDROOM/CLOSET FOR A (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/17/2018
- Issuing Office
- Valley
- Current Status
- Issued on 1/17/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/15/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2017 | JENNIFER LEE |
| Corrections Issued | 12/27/2017 | JENNIFER LEE |
| Plan Check Approved | 1/17/2018 | ANGELICA MARTINEZ |
| Issued | 1/17/2018 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2018 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2018 | KENNETH PHAM |
| Roof/Waste drainage to street | Cleared | 1/17/2018 | KENNETH PHAM |
| Sewer availability | Cleared | 1/17/2018 | KENNETH PHAM |
| Public Works-Highway Ded. | Cleared | 1/17/2018 | KENNETH PHAM |
| Public Works-Open Permits | Cleared | 1/17/2018 | KENNETH PHAM |
| Public Works-Sewers | Cleared | 1/17/2018 | KENNETH PHAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2018 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/9/2018 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 3/9/2018 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/3/2018 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/3/2018 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/4/2018 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/4/2018 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/4/2018 | Approved | MICHEL ABAJAN |
| Insulation | 4/5/2018 | Not Ready for Inspection | MICHEL ABAJAN |
| Insulation | 4/9/2018 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/17/2018 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/14/2018 | Approved | MICHEL ABAJAN |
| Special/Order Compliance | 5/1/2020 | Corrections Issued | ARAM AVEDISIAN |
| Final | 6/18/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 6/18/2020 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2020 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 6/18/2020 | No Access for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 6/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 6/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 6/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 6/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 7/7/2025 | No Access for Inspection | JENNIFER RABUCHIN |
| Final | 9/12/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 9/12/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/12/2025 | Corrections Issued | JENNIFER RABUCHIN |