4179 N FALLING LEAF DR 91316
Certificate Information: 4179 N FALLING LEAF DR 91316
- Application / Permit
- 17014-20000-06060
- Plan Check / Job No.
- B17VN18198
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Proposed (32'-6" x 39'-4") irr. shaped 2nd story addition (955 sq ft) to (e) 1-story sfd. Remodel 1st story of (e) sfd to enlarge living & dining room, convert (9'-10" x 51'-7") south and (16'-3" x 18'-4") at north portion of (e) sfd to trellis patio and (n) (16' x 35'-3") trellis patios. All work per engineering. "COMPLY WITH DEPARTMENT ORDER effective date 04/19/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 5/8/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2017 | APPLICANT |
| Green Plans Picked Up | 12/20/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2017 | RAPHAEL ROSAS |
| Corrections Issued | 12/28/2017 | RAPHAEL ROSAS |
| Quality Review Completed | 1/9/2018 | STEVEN KIM |
| Building Plans Picked Up | 1/11/2018 | APPLICANT |
| Applicant returned to address corrections | 2/28/2018 | RAPHAEL ROSAS |
| Plan Check Approved | 5/8/2018 | RAPHAEL ROSAS |
| Issued | 5/8/2018 | LADBS |
| CofO in Progress | 3/17/2021 | ARIS ALLAHVERDIAN |
| CofO Issued | 6/10/2021 | DANIEL SANCHEZ |
| Permit Finaled | 6/10/2021 | DANIEL SANCHEZ |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/21/2018 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 2/21/2018 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 2/21/2018 | KAYLA PEJI |
| Distance to fire station | Cleared | 2/21/2018 | JOHN CONNEALLY |
| Hydrant and Access approval | Cleared | 2/21/2018 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2018 | KENNETH PHAM |
| Grading Pre-Inspection | Cleared | 3/9/2018 | RAPHAEL ROSAS |
| Green Code | Cleared | 3/9/2018 | DAVID MATSON |
| Low Impact Development | Cleared | 3/9/2018 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 3/9/2018 | KENNETH PHAM |
| Sewer availability | Cleared | 3/9/2018 | KENNETH PHAM |
| Public Works-Highway Ded. | Cleared | 3/9/2018 | KENNETH PHAM |
| Public Works-Open Permits | Cleared | 3/9/2018 | KENNETH PHAM |
| Public Works-Sewers | Cleared | 3/9/2018 | KENNETH PHAM |
| ZA Case | Cleared | 4/25/2018 | HERMINIGILDO AGUSTIN |
| GPI Written Notices | Cleared | 4/27/2018 | RAPHAEL ROSAS |
Contact Information
| Contractor | C M Design & Construction Inc; Lic. No.: 795191-B | 43940 BROOKHAVEN COURT TEMECULA, CA 92592 |
| Engineer | Phan, Ben; Lic. No.: C57550 | 11541 ELIZABETH ST GARDEN GROVE, CA 92840 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/21/2018 | Partial Approval | HAGOP BADOSSIAN |
| Deputy Steel/Welding | 6/27/2018 | Conditional Approval | HAGOP BADOSSIAN |
| Deputy Reinf. Concrete | 6/28/2018 | Conditional Approval | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 7/5/2018 | Partial Approval | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 7/12/2018 | Corrections Issued | MARK VISOCKY |
| BUILDING-Rough-Frame | 8/15/2018 | Partial Inspection | MARK VISOCKY |
| Green Building Rough | 8/15/2018 | Not Ready for Inspection | MARK VISOCKY |
| Verify Sprinkler Sign Off | 8/15/2018 | Not Ready for Inspection | MARK VISOCKY |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2018 | Partial Approval | JOEL WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2019 | Approved | JOEL WILLIAMS |
| ELECTRICAL-Rough | 7/23/2019 | Corrections Issued | JOEL WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2019 | Not Ready for Inspection | JOEL WILLIAMS |
| Gas Test | 7/23/2019 | Approved | JOEL WILLIAMS |
| HVAC-Rough | 7/23/2019 | Corrections Issued | JOEL WILLIAMS |
| PLUMBING-Rough | 7/23/2019 | Corrections Issued | JOEL WILLIAMS |
| BUILDING-Rough-Frame | 7/30/2019 | Corrections Issued | JOEL WILLIAMS |
| ELECTRICAL-Rough | 7/30/2019 | Corrections Issued | JOEL WILLIAMS |
| Green Building Rough | 7/30/2019 | Corrections Issued | JOEL WILLIAMS |
| HVAC-Rough | 7/30/2019 | Approved | JOEL WILLIAMS |
| PLUMBING-Rough | 7/30/2019 | Approved | JOEL WILLIAMS |
| ELECTRICAL-Rough | 8/6/2019 | Partial Approval | JOEL WILLIAMS |
| Insulation | 8/12/2019 | Not Ready for Inspection | JOEL WILLIAMS |
| Insulation | 8/28/2019 | Approved | JOEL WILLIAMS |
| Interior/Exterior Lathing | 8/28/2019 | Partial Approval | JOEL WILLIAMS |
| Interior/Exterior Lathing | 9/27/2019 | Partial Approval | THOMAS LOGRASSO |
| Wood Frame | 9/27/2019 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/16/2020 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| Drywall Nailing | 3/16/2020 | Approved | ARIS ALLAHVERDIAN |
| Final | 3/16/2020 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| Footing/Foundation/Slab | 3/16/2020 | Approved | ARIS ALLAHVERDIAN |
| Green Building Final | 3/16/2020 | Approved | ARIS ALLAHVERDIAN |
| Green Building Rough | 3/16/2020 | Approved | ARIS ALLAHVERDIAN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2020 | SGSOV Approved | ARIS ALLAHVERDIAN |
| Smoke Detectors | 3/16/2020 | Approved | ARIS ALLAHVERDIAN |
| Verify Sprinkler Sign Off | 3/16/2020 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| BUILDING-Rough-Frame | 3/17/2020 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| Verify Sprinkler Sign Off | 3/17/2020 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| BUILDING-Rough-Frame | 3/16/2021 | Approved | ARIS ALLAHVERDIAN |
| Final | 3/16/2021 | OK to Issue CofO | ARIS ALLAHVERDIAN |
| Verify Sprinkler Sign Off | 3/16/2021 | Approved | ARIS ALLAHVERDIAN |