12241 W HATTERAS ST 91607

Certificate Information: 12241 W HATTERAS ST 91607

Application / Permit
17014-20000-05902
Plan Check / Job No.
B17VN17751
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRREGULAR SHAPED 27'-2" X 31'-3" ADDITION TO THE (E) DWELLING FOR NEW BEDROOM , BATHROOM, CLOSET, PANTRY, AND TO ENLARGE THE (E) FAMILY ROOM. ALL WORK PER ENGINEER.
Permit Issued
Issued on 12/6/2017
Issuing Office
Valley
Current Status
CofO Issued on 10/24/2018
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2017 APPLICANT
Assigned to Plan Check Engineer 11/17/2017 RARES BODEA
Corrections Issued 11/17/2017 RARES BODEA
Plan Check Approved 12/5/2017 JEROME MAGAT PALMA
Issued 12/6/2017 LADBS
CofO in Progress 10/24/2018 GREG ALLTON
CofO in Progress 10/24/2018 GREG ALLTON
Permit Finaled 10/24/2018 ANTHONY GIANNINI
CofO Issued 10/24/2018 ANTHONY GIANNINI
Permit Finaled 10/24/2018 ANTHONY GIANNINI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/29/2017 LEE GUILBEAUX
Sewer availability Cleared 11/29/2017 LEE GUILBEAUX
Low Impact Development Cleared 12/1/2017 RARES BODEA
Roof/Waste drainage to street Cleared 12/1/2017 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,
Engineer Adamian, Garen; Lic. No.: C74459 215 N KENWOOD ST #306      GLENDALE, CA 91206

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI
GAREN HAYRAPETYAN, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/20/2017 Approved JUSTIN CURTIS
Footing/Foundation/Slab 12/28/2017 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 1/2/2018 Approved TIP WHITING
PLUMBING-Rough 1/18/2018 Corrections Issued COREY HUPP
PLUMBING-Rough 1/22/2018 Partial Approval COREY HUPP
ELECTRICAL-Rough 2/22/2018 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 2/22/2018 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 2/22/2018 Not Ready for Inspection WILLIAM KUEHN
ELECTRICAL-Rough 3/2/2018 Not Ready for Inspection RAYMOND KEHOE
Green Building Rough 3/2/2018 Not Ready for Inspection RAYMOND KEHOE
Interior/Exterior Lathing 3/2/2018 Approved RAYMOND KEHOE
PLUMBING-Rough 3/2/2018 Not Ready for Inspection RAYMOND KEHOE
ELECTRICAL-Rough 3/6/2018 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 3/6/2018 Not Ready for Inspection COREY HUPP
Shower Pan 3/6/2018 Not Ready for Inspection COREY HUPP
Wood Frame 3/6/2018 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 3/12/2018 Partial Inspection LEE HELLINGER
ELECTRICAL-Final 3/12/2018 Not Ready for Inspection LEE HELLINGER
ELECTRICAL-Rough 3/12/2018 Approved LEE HELLINGER
Green Building Rough 3/12/2018 Approved LEE HELLINGER
PLUMBING-Rough 3/12/2018 Approved LEE HELLINGER
Shower Pan 3/12/2018 Approved LEE HELLINGER
ELECTRICAL-Rough 3/15/2018 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 3/15/2018 Approved RAYMOND KEHOE
Insulation 3/19/2018 Approved COREY HUPP
Shower Pan 3/19/2018 Approved COREY HUPP
Drywall Nailing 3/22/2018 Approved COREY HUPP
BUILDING-Rough-Frame 6/15/2018 Approved RAYMOND KEHOE
Final 6/15/2018 OK to Issue CofO RAYMOND KEHOE
Green Building Final 6/15/2018 Approved RAYMOND KEHOE
SGSOV-Seismic Gas S/O Valve 6/15/2018 SGSOV Approved RAYMOND KEHOE
Smoke Detectors 6/15/2018 Approved RAYMOND KEHOE