1129 E VAN BUREN AVE 90291

Certificate Information: 1129 E VAN BUREN AVE 90291

Application / Permit
17014-20000-05294
Plan Check / Job No.
B17VN15820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'-9" X 30' ADDITION ON THE FIRST FLOOR OF NEW FAMILY ROOM, LAUNDRY ROOM BEDROOM AND FULL BATHROOM; 22'-9" X 30' SECOND STORY ADDITION OF 1 BEDROOM, 1 BATHROOM; CONVERT 13'-4" X 11'-10" PORTION OF DWELLING TO NEW GARAGE AND ADD 13'-4" X 8'; 23'-6" x 16'-6" ROOF DECK
Permit Issued
Issued on 8/13/2018
Issuing Office
Valley
Current Status
CofO Issued on 7/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2017 APPLICANT
Green Plans Picked Up 10/24/2017 APPLICANT
Assigned to Plan Check Engineer 10/26/2017 SELLA BENYAMIN
Corrections Issued 10/30/2017 SELLA BENYAMIN
Quality Review Completed 10/30/2017 GUANG MIN TUNG
Building Plans Picked Up 11/2/2017 APPLICANT
Plan Check Approved 5/10/2018 SELLA BENYAMIN
Issued 8/13/2018 LADBS
CofO in Progress 6/29/2021 ENRIQUE MIRELES
CofO Issued 7/12/2021 VINCENT COTTON
Permit Finaled 7/12/2021 VINCENT COTTON

Permit Application Clearance Information

Green Code Cleared 12/4/2017 DAVID MATSON
Eng Process Fee Ord 176,300 Cleared 3/30/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 3/30/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/30/2018 ADRIAN SANCHEZ
Sewer availability Cleared 3/30/2018 ADRIAN SANCHEZ
Specific Plan Cleared 3/30/2018 JEFF KHAU
Coastal Zone Cleared 5/3/2018 SEAN VEAL
Coastal Zone Cleared 5/3/2018 SEAN VEAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/27/2018 Corrections Issued BOB DUNN
Footing/Foundation/Slab 10/16/2018 No Access for Inspection CRAIG DAVIS
Footing/Foundation/Slab 10/26/2018 Corrections Issued RONALD WEBER
Deputy Drilled-In Anchors 10/31/2018 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 10/31/2018 Corrections Issued CRAIG DAVIS
Deputy Drilled-In Anchors 11/2/2018 No Access for Inspection CRAIG DAVIS
Special/Order Compliance 1/18/2019 No Access for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 1/28/2019 Corrections Issued RONALD WEBER
Footing/Foundation/Slab 1/28/2019 Corrections Issued RONALD WEBER
Footing/Foundation/Slab 2/25/2019 Partial Approval DAVID HEINE
Pre-Inspection 6/10/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 8/7/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/11/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 8/20/2020 Partial Approval DAVID HEINE
Deputy Wood Construction 11/18/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 12/15/2020 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/15/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 12/18/2020 Approved ENRIQUE MIRELES
Green Building Rough 12/18/2020 Approved ENRIQUE MIRELES
HVAC-Rough 12/18/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/18/2020 Approved ENRIQUE MIRELES
HVAC-Rough 12/29/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/12/2021 Corrections Issued ENRIQUE MIRELES
Shower Pan 1/12/2021 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 1/14/2021 Approved ENRIQUE MIRELES
Insulation 1/14/2021 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 1/14/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/19/2021 Approved ENRIQUE MIRELES
Drywall Nailing 1/21/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/26/2021 Approved ENRIQUE MIRELES
Service/Power Release 4/27/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 5/6/2021 Approved ENRIQUE MIRELES
Final 5/6/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 5/6/2021 Approved ENRIQUE MIRELES
Green Building Final 5/6/2021 Approved ENRIQUE MIRELES
HVAC-Final 5/6/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 5/6/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/6/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 5/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 5/6/2021 Approved ENRIQUE MIRELES
Final 6/29/2021 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 6/29/2021 Approved ENRIQUE MIRELES