1129 E VAN BUREN AVE 90291
Certificate Information: 1129 E VAN BUREN AVE 90291
- Application / Permit
- 17014-20000-05294
- Plan Check / Job No.
- B17VN15820
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 22'-9" X 30' ADDITION ON THE FIRST FLOOR OF NEW FAMILY ROOM, LAUNDRY ROOM BEDROOM AND FULL BATHROOM; 22'-9" X 30' SECOND STORY ADDITION OF 1 BEDROOM, 1 BATHROOM; CONVERT 13'-4" X 11'-10" PORTION OF DWELLING TO NEW GARAGE AND ADD 13'-4" X 8'; 23'-6" x 16'-6" ROOF DECK
- Permit Issued
- Issued on 8/13/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2017 | APPLICANT |
| Green Plans Picked Up | 10/24/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2017 | SELLA BENYAMIN |
| Corrections Issued | 10/30/2017 | SELLA BENYAMIN |
| Quality Review Completed | 10/30/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/2/2017 | APPLICANT |
| Plan Check Approved | 5/10/2018 | SELLA BENYAMIN |
| Issued | 8/13/2018 | LADBS |
| CofO in Progress | 6/29/2021 | ENRIQUE MIRELES |
| CofO Issued | 7/12/2021 | VINCENT COTTON |
| Permit Finaled | 7/12/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Green Code | Cleared | 12/4/2017 | DAVID MATSON |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 3/30/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/30/2018 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 3/30/2018 | ADRIAN SANCHEZ |
| Specific Plan | Cleared | 3/30/2018 | JEFF KHAU |
| Coastal Zone | Cleared | 5/3/2018 | SEAN VEAL |
| Coastal Zone | Cleared | 5/3/2018 | SEAN VEAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/27/2018 | Corrections Issued | BOB DUNN |
| Footing/Foundation/Slab | 10/16/2018 | No Access for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 10/26/2018 | Corrections Issued | RONALD WEBER |
| Deputy Drilled-In Anchors | 10/31/2018 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 10/31/2018 | Corrections Issued | CRAIG DAVIS |
| Deputy Drilled-In Anchors | 11/2/2018 | No Access for Inspection | CRAIG DAVIS |
| Special/Order Compliance | 1/18/2019 | No Access for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 1/28/2019 | Corrections Issued | RONALD WEBER |
| Footing/Foundation/Slab | 1/28/2019 | Corrections Issued | RONALD WEBER |
| Footing/Foundation/Slab | 2/25/2019 | Partial Approval | DAVID HEINE |
| Pre-Inspection | 6/10/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 8/7/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2020 | Partial Approval | DAVID HEINE |
| Deputy Wood Construction | 11/18/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2020 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/15/2020 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/18/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/18/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/18/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/18/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/29/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/12/2021 | Corrections Issued | ENRIQUE MIRELES |
| Shower Pan | 1/12/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/14/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 1/14/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 1/14/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/19/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/21/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/26/2021 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 4/27/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/6/2021 | Approved | ENRIQUE MIRELES |
| Final | 5/6/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/6/2021 | Approved | ENRIQUE MIRELES |
| Green Building Final | 5/6/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 5/6/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 5/6/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 5/6/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 5/6/2021 | Approved | ENRIQUE MIRELES |
| Final | 6/29/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 6/29/2021 | Approved | ENRIQUE MIRELES |