5145 N HIGHLAND VIEW AVE 90041

Certificate Information: 5145 N HIGHLAND VIEW AVE 90041

Application / Permit
17014-20000-05230
Plan Check / Job No.
B17VN15609
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO (E) SFD, & ADD IRR. 14'-3" X 4'-2" @ FRONT, 29'-6" X 26'-4" W/ 6'-0" X 22'-9" PATIO COVER @ REAR & ADD (N) IRR. 64'-6" X 37'-5" 2ND FLR W/ 6'-0" X 18'-0" TRELLIS @ REAR; TO BECOME A 2-STORY SFD. (COMMENTS)
Permit Issued
Issued on 3/27/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2017 APPLICANT
Assigned to Plan Check Engineer 10/19/2017 ALEXANDER SBARDELLATI
Corrections Issued 10/23/2017 ALEXANDER SBARDELLATI
Quality Review Completed 10/24/2017 DOUGLAS NAKATANI
Building Plans Picked Up 10/26/2017 APPLICANT
Green Plans Picked Up 10/26/2017 APPLICANT
Applicant returned to address corrections 11/17/2017 ALEXANDER SBARDELLATI
Applicant returned to address corrections 2/26/2018 ALEXANDER SBARDELLATI
Applicant returned to address corrections 2/27/2018 ALEXANDER SBARDELLATI
Applicant returned to address corrections 3/7/2018 ALEXANDER SBARDELLATI
Plan Check Approved 3/16/2018 ALEXANDER SBARDELLATI
Issued 3/27/2018 LADBS
CofO in Progress 5/3/2023 CRAIG VAUGHAN
CofO Issued 5/6/2023 DEROLD HAUFF
Permit Finaled 5/6/2023 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 10/23/2017 ALEXANDER SBARDELLATI
Grading Pre-Inspection Cleared 10/23/2017 ALEXANDER SBARDELLATI
Eng Process Fee Ord 176,300 Cleared 1/29/2018 LEE GUILBEAUX
Hydrant and Access approval Cleared 1/29/2018 JOHN CONNEALLY
Sewer availability Cleared 1/29/2018 LEE GUILBEAUX
Green Code Cleared 3/5/2018 MICKEY YAMASHITA
CPC Cleared 3/9/2018 STEVEN WECHSLER
Low Impact Development Cleared 3/16/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 3/16/2018 KAREN LE
Hold Cleared 5/23/2018 TERESA MUI

Contact Information

Contractor Murillo Sergio; Lic. No.: 860668-B 8613 MILLERGROVE DRIVE      WHITTIER, CA 90606
Engineer Avila, Albert Guerrero; Lic. No.: C41726 10034 GLADE AVNENUE      CHATSWORTH, CA 91311

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2018 Corrections Issued LUIS BARRALES
Excavation/Setback/Form/Re-Bar 6/12/2018 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 6/14/2018 Approved RUBEN SALAS
PLUMBING-Rough 7/17/2018 Partial Inspection OSVALDO PARAMO
Wood Frame 7/18/2018 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/27/2018 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/28/2019 Corrections Issued RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 10/11/2019 No Access for Inspection PIERRE VEGA
Deputy Wood Construction 10/17/2019 No Access for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 10/18/2019 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/18/2019 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 10/18/2019 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 10/24/2019 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2019 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 10/24/2019 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 11/13/2019 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 11/13/2019 Partial Approval CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 11/13/2019 Partial Approval CRAIG VAUGHAN
Structural Steel Frame 11/25/2019 No Access for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/2/2019 Partial Approval CRAIG VAUGHAN
Green Building Rough 12/2/2019 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 2/5/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/5/2020 Approved CRAIG VAUGHAN
Shower Pan 2/5/2020 Approved CRAIG VAUGHAN
Wood Frame 2/5/2020 Approved CRAIG VAUGHAN
Insulation 2/12/2020 Approved BRIAN SULLIVAN
Drywall Nailing 3/5/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/18/2020 Partial Approval CHRISTOPHER DELLEFIELD
Service/Power Release 11/10/2021 Corrections Issued CRAIG VAUGHAN
Special/Order Compliance 11/10/2021 Partial Inspection LILIANA PORTILLO
Service/Power Release 11/16/2021 No Access for Inspection CRAIG VAUGHAN
Service/Power Release 12/7/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/14/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/14/2022 SGSOV Not Ready CRAIG VAUGHAN
ELECTRICAL-Final 4/25/2022 Corrections Issued CRAIG VAUGHAN
Final 4/25/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 4/25/2022 Approved CRAIG VAUGHAN
HVAC-Final 4/25/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 4/25/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 4/25/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 4/26/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 5/2/2022 Approved CRAIG VAUGHAN
Final 5/2/2022 Corrections Issued CRAIG VAUGHAN
Gas Test 5/2/2022 Approved CRAIG VAUGHAN
HVAC-Final 5/2/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 5/2/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 5/2/2022 Approved CRAIG VAUGHAN
Final 5/12/2022 Not Ready for Inspection CRAIG VAUGHAN
Final 11/8/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 11/8/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 5/2/2023 OK to Issue CofO CRAIG VAUGHAN
PLUMBING-Final 5/2/2023 Approved CRAIG VAUGHAN