5145 N HIGHLAND VIEW AVE 90041
Certificate Information: 5145 N HIGHLAND VIEW AVE 90041
- Application / Permit
- 17014-20000-05230
- Plan Check / Job No.
- B17VN15609
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO (E) SFD, & ADD IRR. 14'-3" X 4'-2" @ FRONT, 29'-6" X 26'-4" W/ 6'-0" X 22'-9" PATIO COVER @ REAR & ADD (N) IRR. 64'-6" X 37'-5" 2ND FLR W/ 6'-0" X 18'-0" TRELLIS @ REAR; TO BECOME A 2-STORY SFD. (COMMENTS)
- Permit Issued
- Issued on 3/27/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2017 | ALEXANDER SBARDELLATI |
| Corrections Issued | 10/23/2017 | ALEXANDER SBARDELLATI |
| Quality Review Completed | 10/24/2017 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 10/26/2017 | APPLICANT |
| Green Plans Picked Up | 10/26/2017 | APPLICANT |
| Applicant returned to address corrections | 11/17/2017 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 2/26/2018 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 2/27/2018 | ALEXANDER SBARDELLATI |
| Applicant returned to address corrections | 3/7/2018 | ALEXANDER SBARDELLATI |
| Plan Check Approved | 3/16/2018 | ALEXANDER SBARDELLATI |
| Issued | 3/27/2018 | LADBS |
| CofO in Progress | 5/3/2023 | CRAIG VAUGHAN |
| CofO Issued | 5/6/2023 | DEROLD HAUFF |
| Permit Finaled | 5/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/23/2017 | ALEXANDER SBARDELLATI |
| Grading Pre-Inspection | Cleared | 10/23/2017 | ALEXANDER SBARDELLATI |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2018 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 1/29/2018 | JOHN CONNEALLY |
| Sewer availability | Cleared | 1/29/2018 | LEE GUILBEAUX |
| Green Code | Cleared | 3/5/2018 | MICKEY YAMASHITA |
| CPC | Cleared | 3/9/2018 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 3/16/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/16/2018 | KAREN LE |
| Hold | Cleared | 5/23/2018 | TERESA MUI |
Contact Information
| Contractor | Murillo Sergio; Lic. No.: 860668-B | 8613 MILLERGROVE DRIVE WHITTIER, CA 90606 |
| Engineer | Avila, Albert Guerrero; Lic. No.: C41726 | 10034 GLADE AVNENUE CHATSWORTH, CA 91311 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2018 | Corrections Issued | LUIS BARRALES |
| Excavation/Setback/Form/Re-Bar | 6/12/2018 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 6/14/2018 | Approved | RUBEN SALAS |
| PLUMBING-Rough | 7/17/2018 | Partial Inspection | OSVALDO PARAMO |
| Wood Frame | 7/18/2018 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2018 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2019 | Corrections Issued | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2019 | No Access for Inspection | PIERRE VEGA |
| Deputy Wood Construction | 10/17/2019 | No Access for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/18/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 10/18/2019 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/24/2019 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 10/24/2019 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/13/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2019 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/13/2019 | Partial Approval | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 11/13/2019 | Partial Approval | CRAIG VAUGHAN |
| Structural Steel Frame | 11/25/2019 | No Access for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/2/2019 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 12/2/2019 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 2/5/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/5/2020 | Approved | CRAIG VAUGHAN |
| Shower Pan | 2/5/2020 | Approved | CRAIG VAUGHAN |
| Wood Frame | 2/5/2020 | Approved | CRAIG VAUGHAN |
| Insulation | 2/12/2020 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 3/5/2020 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 5/18/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 11/10/2021 | Corrections Issued | CRAIG VAUGHAN |
| Special/Order Compliance | 11/10/2021 | Partial Inspection | LILIANA PORTILLO |
| Service/Power Release | 11/16/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 12/7/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/14/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/25/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 4/25/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 4/25/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 4/25/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 4/25/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/25/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 4/26/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/2/2022 | Approved | CRAIG VAUGHAN |
| Final | 5/2/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 5/2/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 5/2/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 5/2/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 5/2/2022 | Approved | CRAIG VAUGHAN |
| Final | 5/12/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 11/8/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/8/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 5/2/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| PLUMBING-Final | 5/2/2023 | Approved | CRAIG VAUGHAN |