5331 N BOTHWELL ROAD 91356

Certificate Information: 5331 N BOTHWELL ROAD 91356

Application / Permit
17014-20000-05041
Plan Check / Job No.
B17VN15056
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16' X 15' ADDITION TO ADD NEW BEDROOM AND BATHROOM. 6'0" X 13'6" ADDITION TO ADD WALK IN CLOSET. 5' X 5' ADDITION TO EXPAND BATHROOM. 3'6" X 5'6" ADDITION TO EXPAND ENTRY. CONVERT LIVING ROOM TO BEDROOM AND 1/2 BATH. REMODEL KITCHEN AND BATHROOMS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/8/2018
Issuing Office
Valley
Current Status
CofO Issued on 3/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2017 APPLICANT
Assigned to Plan Check Engineer 10/5/2017 JEFFREY TANGONAN
Corrections Issued 10/5/2017 JEFFREY TANGONAN
Plan Check Approved 3/8/2018 MICHAEL PEREZ
Issued 3/8/2018 LADBS
CofO in Progress 2/24/2025 JOHN KIDWELL
Permit Finaled 3/18/2025 JOHN JANSON
CofO Issued 3/18/2025 JOHN JANSON
Permit Finaled 3/18/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/4/2017 KENNETH PHAM
Grading Pre-Inspection Cleared 10/4/2017 JEFFREY TANGONAN
Roof/Waste drainage to street Cleared 10/4/2017 KENNETH PHAM
Sewer availability Cleared 10/4/2017 KENNETH PHAM
Public Works-Highway Ded. Cleared 10/4/2017 KENNETH PHAM
Public Works-Open Permits Cleared 10/4/2017 KENNETH PHAM
Public Works-Sewers Cleared 10/4/2017 KENNETH PHAM
Construction near power lines Cleared 1/4/2018 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Zarate, Eduardo P; Lic. No.: C71359 1272 MILLIGAN DR      CAMARILLO, CA 93010

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/2/2019 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 7/24/2019 Corrections Issued JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 8/5/2019 Approved SEAN WIRCH
PLUMBING-Rough 9/23/2019 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 10/21/2019 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Corrections Issued DAVID SANDOVAL
Rough-Elec/Plmb/HVAC 4/7/2020 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/9/2021 Partial Approval DAVID SANDOVAL
HVAC-Rough 8/9/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 8/9/2021 Not Ready for Inspection DAVID SANDOVAL
Drywall Nailing 5/4/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 6/22/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 11/26/2024 Approved JOHN COLEMAN
Final 11/26/2024 Not Ready for Inspection JOHN COLEMAN
Footing/Foundation/Slab 11/26/2024 Approved JOHN COLEMAN
Green Building Final 11/26/2024 Not Ready for Inspection JOHN COLEMAN
Green Building Rough 11/26/2024 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Approved JOHN COLEMAN
Smoke Detectors 11/26/2024 Approved JOHN COLEMAN
Final 1/7/2025 Corrections Issued JOHN COLEMAN
Green Building Final 1/7/2025 Approved JOHN COLEMAN
Special/Order Compliance 1/22/2025 Partial Approval JOHN COLEMAN
Final 2/24/2025 OK to Issue CofO JOHN KIDWELL