4016 N OAKFIELD DR 91423

Certificate Information: 4016 N OAKFIELD DR 91423

Application / Permit
17014-20000-04077
Plan Check / Job No.
B17VN12152
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ENTIRE BUILDING EXCEPT 15'-0" WALLS AT NORTH SIDE AND SOUTH SIDE AND BUILD 42'-10" x 56'-10" IRRG. TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED FOUR CAR BASEMENT GARAGE. FIRE SPRINKLER NFPA13D. ALL WORK PER ENGINEERING. SEE COMMENTS.
Permit Issued
Issued on 10/24/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2017 APPLICANT
Assigned to Plan Check Engineer 8/24/2017 MENA WASSEF
Green Plans Picked Up 8/31/2017 APPLICANT
Corrections Issued 9/12/2017 MENA WASSEF
Quality Review Completed 9/13/2017 DOUGLAS NAKATANI
Building Plans Picked Up 9/13/2017 APPLICANT
Applicant returned to address corrections 10/12/2017 MENA WASSEF
Plan Check Approved 6/19/2018 MENA WASSEF
Issued 10/24/2019 LADBS
CofO in Progress 11/5/2025 MISAEL ESPARZA
Permit Finaled 11/19/2025 RUBEN SALAS
CofO Issued 11/19/2025 RUBEN SALAS
Permit Finaled 11/19/2025 RUBEN SALAS

Permit Application Clearance Information

Green Code Cleared 9/7/2017 MICKEY YAMASHITA
Eng Process Fee Ord 176,300 Cleared 9/28/2017 MARKOS PEREZ-BRAN
Sewer availability Cleared 9/28/2017 MARKOS PEREZ-BRAN
Certificate of Compliance Cleared 9/29/2017 JESSE RAMOS
Address approval Cleared 10/12/2017 EDUARDO PEDROZA
BHO/Hillside ordinance Cleared 11/20/2017 KAYLA PEJI
BHO/Hillside ordinance Cleared 11/20/2017 KAYLA PEJI
Miscellaneous Cleared 11/20/2017 DAISY BENICIA
Miscellaneous Cleared 11/20/2017 DAISY BENICIA
Permit Cleared 11/20/2017 KAYLA PEJI
Low Impact Development Cleared 12/11/2017 MITESH PATEL
BHO/Hillside ordinance Cleared 12/14/2017 JACOB BIGLER
Roof/Waste drainage to street Cleared 12/14/2017 JACOB BIGLER
Distance to fire station Cleared 12/15/2017 JOHN DALLAS
GPI Written Notices Cleared 12/15/2017 MENA WASSEF
Grading Pre-Inspection Cleared 12/15/2017 MENA WASSEF
Hydrant and Access approval Cleared 12/15/2017 JOHN DALLAS

Contact Information

Contractor Owner-Builder       ,
Engineer Jitechian, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504
Engineer Nazari, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327
Geologist Miller, Steven Burl; Lic. No.: EG1303 23890 COPPERHILL DRIVE #111      VALENCIA, CA 91354

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/20/2020 Partial Approval CHARLES POWELL
Piling/Pier/Caisson 3/20/2020 Partial Approval CHARLES POWELL
Piling/Pier/Caisson 3/25/2020 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 3/26/2020 Partial Approval CHARLES POWELL
Masonry Wall/Backfill 4/27/2020 Approved TROY SANDERS
Reinforced Masonry Frame 5/8/2020 Corrections Issued THOMAS FINNILA
Piling/Pier/Caisson 5/14/2020 Partial Approval CHARLES POWELL
Special/Order Compliance 5/14/2020 Partial Inspection DANIEL ORRANTE
Masonry Wall/Backfill 6/10/2020 Not Ready for Inspection CHARLES POWELL
Reinforced Concrete Frame 6/10/2020 Partial Approval CHARLES POWELL
Deputy Shotcrete 6/25/2020 Partial Approval CHARLES POWELL
Piling/Pier/Caisson 7/22/2020 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 7/23/2020 Approved CHARLES POWELL
Deputy Reinf. Concrete 7/24/2020 Approved CHARLES POWELL
Footing/Foundation/Slab 10/5/2020 Not Ready for Inspection ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 10/13/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 11/17/2020 Corrections Issued CHARLES POWELL
Reinforced Concrete Frame 11/17/2020 Not Ready for Inspection CHARLES POWELL
Excavation/Setback/Form/Re-Bar 11/18/2020 Partial Approval CHARLES POWELL
Reinforced Concrete Frame 11/18/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 4/7/2021 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 5/17/2021 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 6/4/2021 Partial Approval ARAM AVEDISIAN
Masonry Wall/Backfill 6/24/2021 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 10/21/2021 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 11/12/2021 Corrections Issued MISAEL ESPARZA
Deputy Steel/Welding 11/15/2021 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 11/22/2021 Partial Approval MISAEL ESPARZA
Wood Frame 12/20/2021 Approved MATT KELLERMAN
Deputy Wood Construction 1/27/2022 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Partial Approval JACK KARGODORIAN
Wood Frame 3/3/2022 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 3/4/2022 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 No Access for Inspection MISAEL ESPARZA
HVAC-Rough 6/9/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 6/9/2022 Approved MISAEL ESPARZA
Wood Frame 8/18/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 9/2/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 9/2/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 9/14/2022 Not Ready for Inspection MISAEL ESPARZA
Deputy Steel/Welding 9/20/2022 Conditional Approval MISAEL ESPARZA
Deputy Steel/Welding 9/21/2022 Conditional Approval MISAEL ESPARZA
Deputy Steel/Welding 9/22/2022 Conditional Approval CALEB MEISTER
HVAC-Rough 9/22/2022 Approved DEANDRE HOFFMAN
Wood Frame 9/27/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 10/14/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 10/14/2022 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 10/14/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 10/21/2022 Approved MISAEL ESPARZA
Wood Frame 10/21/2022 Corrections Issued MISAEL ESPARZA
Pre-Inspection 10/26/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/4/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 11/4/2022 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 11/4/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/14/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 11/14/2022 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 11/14/2022 Corrections Issued MISAEL ESPARZA
Special/Order Compliance 1/5/2023 No Access for Inspection ROBERT GOLD
Pre-Inspection 5/2/2023 Approved MISAEL ESPARZA
Special/Order Compliance 5/2/2023 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 6/5/2023 Partial Approval JUAN VALENZUELA
Insulation 6/26/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 7/17/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 7/17/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/14/2023 Partial Approval MISAEL ESPARZA
Drywall Nailing 4/19/2024 Partial Approval MISAEL ESPARZA
Shower Pan 4/25/2024 Partial Inspection LEONARD ROSS II
Shower Pan 4/26/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/3/2024 Partial Approval MISAEL ESPARZA
Special/Order Compliance 5/3/2024 Corrections Issued MISAEL ESPARZA
Drywall Nailing 7/15/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 12/23/2024 Corrections Issued MISAEL ESPARZA
Service/Power Release 1/29/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 10/24/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/24/2025 Corrections Issued MISAEL ESPARZA
Final 10/24/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/24/2025 Approved MISAEL ESPARZA
Green Building Final 10/24/2025 Approved MISAEL ESPARZA
Green Building Rough 10/24/2025 Approved MISAEL ESPARZA
HVAC-Final 10/24/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 10/24/2025 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 10/24/2025 Approved MISAEL ESPARZA
Final 11/4/2025 OK to Issue CofO MISAEL ESPARZA