7749 N KLUMP AVE 91352

Certificate Information: 7749 N KLUMP AVE 91352

Application / Permit
17014-20000-03854
Plan Check / Job No.
B17VN11585
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069; AND ADD 20'5" x 25'3" ADDITION TO EXPAND ADU. ALL WORK PER WFPP.
Permit Issued
Issued on 1/30/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2017 APPLICANT
Assigned to Plan Check Engineer 8/10/2017 JEFFREY TANGONAN
Corrections Issued 8/11/2017 JEFFREY TANGONAN
Quality Review Completed 8/11/2017 GUANG MIN TUNG
Building Plans Picked Up 8/14/2017 APPLICANT
Plan Check Approved 1/3/2018 JEFFREY TANGONAN
Issued 1/30/2018 LADBS
CofO in Progress 3/29/2022 CHRISTOPHER DELLEFIELD
CofO in Progress 3/29/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 5/26/2022 MICHAEL SMITH
CofO Issued 5/26/2022 MICHAEL SMITH
Permit Finaled 5/26/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/14/2017 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 10/12/2017 JOHN LIN
Roof/Waste drainage to street Cleared 10/12/2017 JOHN LIN
Sewer availability Cleared 10/12/2017 JOHN LIN
Construction near power lines Cleared 12/8/2017 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/12/2020 Not Ready for Inspection JOHN HAYES
Final 3/12/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 3/12/2020 Not Ready for Inspection JOHN HAYES
Green Building Final 3/12/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 3/12/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/12/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 3/12/2020 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 4/20/2020 Not Ready for Inspection JOHN HAYES
Underground Mechanical 5/6/2020 Corrections Issued PIERRE VEGA
Underground Mechanical 5/26/2020 Partial Approval JOHN HAYES
Footing/Foundation/Slab 6/2/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 6/10/2020 Approved JOHN HAYES
Wood Frame 10/5/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 12/18/2020 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 12/18/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 12/18/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/18/2020 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 12/29/2020 Conditional Approval JOHN HAYES
BUILDING-Rough-Frame 12/31/2020 Approved JOHN HAYES
ELECTRICAL-Rough 12/31/2020 Approved JOHN HAYES
Green Building Rough 12/31/2020 Approved JOHN HAYES
HVAC-Rough 12/31/2020 Approved JOHN HAYES
PLUMBING-Rough 12/31/2020 Approved JOHN HAYES
Drywall Nailing 2/2/2021 Approved JOHN HAYES
Interior/Exterior Lathing 2/2/2021 Partial Approval JOHN HAYES
ELECTRICAL-Final 12/7/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 12/7/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 12/7/2021 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 12/7/2021 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 12/7/2021 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 12/7/2021 Approved CHRISTOPHER DELLEFIELD
Final 3/22/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 3/22/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 3/22/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Final 3/29/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD