7749 N KLUMP AVE 91352
Certificate Information: 7749 N KLUMP AVE 91352
- Application / Permit
- 17014-20000-03854
- Plan Check / Job No.
- B17VN11585
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069; AND ADD 20'5" x 25'3" ADDITION TO EXPAND ADU. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/30/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2017 | JEFFREY TANGONAN |
| Corrections Issued | 8/11/2017 | JEFFREY TANGONAN |
| Quality Review Completed | 8/11/2017 | GUANG MIN TUNG |
| Building Plans Picked Up | 8/14/2017 | APPLICANT |
| Plan Check Approved | 1/3/2018 | JEFFREY TANGONAN |
| Issued | 1/30/2018 | LADBS |
| CofO in Progress | 3/29/2022 | CHRISTOPHER DELLEFIELD |
| CofO in Progress | 3/29/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 5/26/2022 | MICHAEL SMITH |
| CofO Issued | 5/26/2022 | MICHAEL SMITH |
| Permit Finaled | 5/26/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2017 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2017 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 10/12/2017 | JOHN LIN |
| Sewer availability | Cleared | 10/12/2017 | JOHN LIN |
| Construction near power lines | Cleared | 12/8/2017 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/12/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 3/12/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 3/12/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 3/12/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 3/12/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/12/2020 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 3/12/2020 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 4/20/2020 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 5/6/2020 | Corrections Issued | PIERRE VEGA |
| Underground Mechanical | 5/26/2020 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 6/2/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/10/2020 | Approved | JOHN HAYES |
| Wood Frame | 10/5/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 12/18/2020 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 12/18/2020 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 12/18/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 12/18/2020 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 12/29/2020 | Conditional Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 12/31/2020 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 12/31/2020 | Approved | JOHN HAYES |
| Green Building Rough | 12/31/2020 | Approved | JOHN HAYES |
| HVAC-Rough | 12/31/2020 | Approved | JOHN HAYES |
| PLUMBING-Rough | 12/31/2020 | Approved | JOHN HAYES |
| Drywall Nailing | 2/2/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/2/2021 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Final | 12/7/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 12/7/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 12/7/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 12/7/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 12/7/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 12/7/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 3/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 3/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 3/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Final | 3/29/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |