328 1/2 E 83RD ST 90003

Certificate Information: 328 1/2 E 83RD ST 90003

Application / Permit
17014-20000-03701
Plan Check / Job No.
B17VN11155
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD LAUNDRY RM AND ENLARGE BEDRM AT EXIST REAR SFD UNIT..
Permit Issued
Issued on 1/9/2018
Issuing Office
Valley
Current Status
CofO Issued on 11/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2017 APPLICANT
Assigned to Plan Check Engineer 8/10/2017 DOUGLAS NAKATANI
Corrections Issued 8/15/2017 DOUGLAS NAKATANI
Quality Review Completed 8/17/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 8/17/2017 APPLICANT
Green Plans Picked Up 8/23/2017 APPLICANT
Applicant returned to address corrections 9/15/2017 DOUGLAS NAKATANI
Applicant returned to address corrections 10/13/2017 DOUGLAS NAKATANI
Applicant returned to address corrections 10/27/2017 DOUGLAS NAKATANI
Applicant returned to address corrections 11/21/2017 DOUGLAS NAKATANI
Applicant returned to address corrections 12/15/2017 DOUGLAS NAKATANI
Plan Check Approved 1/9/2018 DOUGLAS NAKATANI
Issued 1/9/2018 LADBS
CofO in Progress 10/23/2023 MICHAEL LEWIS
Permit Finaled 11/2/2023 DEROLD HAUFF
CofO Issued 11/2/2023 DEROLD HAUFF
Permit Finaled 11/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2017 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/22/2017 EDUARDO PEDROZA
Roof/Waste drainage to street Cleared 8/22/2017 LEE GUILBEAUX
Sewer availability Cleared 8/22/2017 LEE GUILBEAUX
Green Code Cleared 9/7/2017 ROLLIN GETTLE III

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/31/2018 Approved ANDEY CHAPARRO
Footing/Foundation/Slab 2/7/2018 Approved ANDEY CHAPARRO
BUILDING-Rough-Frame 2/21/2018 Partial Approval ANDEY CHAPARRO
Insulation 2/21/2018 Partial Approval ANDEY CHAPARRO
PLUMBING-Rough 2/21/2018 Partial Approval ANDEY CHAPARRO
BUILDING-Rough-Frame 2/26/2018 Partial Approval ANDEY CHAPARRO
Floor/Roof Diaphrgm/Shear Wall 2/26/2018 Partial Approval ANDEY CHAPARRO
Floor/Roof Diaphrgm/Shear Wall 2/28/2018 Partial Approval ANDEY CHAPARRO
ELECTRICAL-Rough 5/3/2018 Not Ready for Inspection ANDEY CHAPARRO
Interior/Exterior Lathing 5/3/2018 Not Ready for Inspection ANDEY CHAPARRO
PLUMBING-Rough 5/3/2018 Not Ready for Inspection ANDEY CHAPARRO
Underground Mechanical 5/3/2018 Not Ready for Inspection ANDEY CHAPARRO
ELECTRICAL-Rough 5/7/2018 Not Ready for Inspection ANDEY CHAPARRO
Floor/Roof Diaphrgm/Shear Wall 5/7/2018 Approved ANDEY CHAPARRO
Interior/Exterior Lathing 5/7/2018 Partial Approval ANDEY CHAPARRO
PLUMBING-Rough 5/7/2018 Approved ANDEY CHAPARRO
Underground Mechanical 5/7/2018 Not Ready for Inspection ANDEY CHAPARRO
BUILDING-Rough-Frame 5/18/2018 Conditional Approval ANDEY CHAPARRO
ELECTRICAL-Rough 5/18/2018 Not Ready for Inspection ANDEY CHAPARRO
Floor/Roof Diaphrgm/Shear Wall 5/18/2018 Approved ANDEY CHAPARRO
Green Building Rough 5/18/2018 Approved ANDEY CHAPARRO
PLUMBING-Rough 5/18/2018 Approved ANDEY CHAPARRO
Underground Mechanical 5/18/2018 Not Ready for Inspection ANDEY CHAPARRO
ELECTRICAL-Rough 5/22/2018 Not Ready for Inspection ANDEY CHAPARRO
ELECTRICAL-Rough 5/25/2018 No Access for Inspection FRANCISCO MORADO
HVAC-Rough 5/25/2018 No Access for Inspection FRANCISCO MORADO
Wood Frame 5/25/2018 No Access for Inspection FRANCISCO MORADO
ELECTRICAL-Rough 6/1/2018 Not Ready for Inspection FRANCISCO MORADO
HVAC-Rough 6/1/2018 Not Ready for Inspection FRANCISCO MORADO
PLUMBING-Rough 6/1/2018 Not Ready for Inspection FRANCISCO MORADO
Wood Frame 6/1/2018 Not Ready for Inspection FRANCISCO MORADO
Floor/Roof Diaphrgm/Shear Wall 6/5/2018 Not Ready for Inspection ANDEY CHAPARRO
Rough-Elec/Plmb/HVAC 6/5/2018 Not Ready for Inspection FRANCISCO MORADO
BUILDING-Rough-Frame 2/1/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 2/26/2021 Partial Approval DAVID FEILER
Footing/Foundation/Slab 2/26/2021 Approved DAVID FEILER
Interior/Exterior Lathing 2/26/2021 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 3/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/12/2021 Approved ALEJANDRO DE ARTOLA
Insulation 3/12/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/19/2023 Approved MICHAEL LEWIS
Final 10/19/2023 OK to Issue CofO MICHAEL LEWIS
Green Building Final 10/19/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/19/2023 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 10/19/2023 Approved MICHAEL LEWIS