7942-7944 N WILKINSON AVE 91605

Certificate Information: 7942-7944 N WILKINSON AVE 91605

Application / Permit
17014-20000-03188
Plan Check / Job No.
B17VN09661
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
27'4" x 18'3" ADDITION TO REAR OF (E) DWELLING FOR ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069. ALL WORK PER WFPP.
Permit Issued
Issued on 4/22/2020
Issuing Office
Current Status
CofO Issued on 2/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2017 APPLICANT
Assigned to Plan Check Engineer 7/6/2017 JEFFREY TANGONAN
Corrections Issued 7/13/2017 JEFFREY TANGONAN
Building Plans Picked Up 7/14/2017 APPLICANT
Plan Check Approved 9/19/2017 JEFFREY TANGONAN
Issued 4/22/2020 APPLICANT
CofO in Progress 10/2/2020 JOHN HAYES
Permit Finaled 2/23/2021 MICHAEL SMITH
CofO Issued 2/23/2021 MICHAEL SMITH
Permit Finaled 2/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/25/2017 JOHN LIN
Low Impact Development Cleared 9/14/2017 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 9/19/2017 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 9/19/2017 MARKOS PEREZ-BRAN
Sewer availability Cleared 9/19/2017 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/29/2020 No Access for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/30/2020 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 5/5/2020 Not Ready for Inspection PIERRE VEGA
Footing/Foundation/Slab 5/7/2020 Approved JOHN HAYES
BUILDING-Rough-Frame 5/13/2020 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Partial Approval BEAU COLLINS
PLUMBING-Rough 5/15/2020 Corrections Issued BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Partial Approval JOHN HAYES
Insulation 5/18/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/19/2020 Corrections Issued JOHN HAYES
Green Building Rough 6/19/2020 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 6/19/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/23/2020 Partial Approval JOHN HAYES
ELECTRICAL-Rough 6/23/2020 Approved JOHN HAYES
Green Building Rough 6/23/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 6/23/2020 Partial Approval JOHN HAYES
PLUMBING-Rough 6/23/2020 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 6/26/2020 Partial Approval JOHN HAYES
Interior/Exterior Lathing 6/26/2020 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 6/26/2020 Partial Approval JOHN HAYES
Shower Pan 6/26/2020 Approved JOHN HAYES
Insulation 6/30/2020 Approved PIERRE VEGA
Drywall Nailing 7/6/2020 Approved JOHN HAYES
Green Building Rough 7/6/2020 Approved JOHN HAYES
BUILDING-Rough-Frame 7/24/2020 Not Ready for Inspection JOHN HAYES
Final 7/24/2020 Not Ready for Inspection JOHN HAYES
Green Building Final 7/24/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/24/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 7/24/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/27/2020 Not Ready for Inspection JOHN HAYES
Final 7/27/2020 Not Ready for Inspection JOHN HAYES
Green Building Final 7/27/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/27/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 7/27/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/1/2020 Approved JOHN HAYES
Final 10/1/2020 OK to Issue CofO JOHN HAYES
Green Building Final 10/1/2020 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/1/2020 SGSOV Approved JOHN HAYES
Smoke Detectors 10/1/2020 Approved JOHN HAYES