2006 N PRESTON AVE 90026
Certificate Information: 2006 N PRESTON AVE 90026
- Application / Permit
- 17014-20000-02975
- Plan Check / Job No.
- B17VN09080
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 400.5SF PORTION OF (E)UNDER FLOOR AREA FOR (N) ADDITION [CONSIST OF RECREATION ROOM WITH MAX. HALF BATH & LAUNDRY ROOM WITH EXTERIOR ACCESS] TO (E) ONE STORY SFD WITH (E) 1 CAR GARAGE TO CREATE TWO STORY SFD.
- Permit Issued
- Issued on 6/20/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2017 | DAWN MC NULTY |
| Corrections Issued | 7/6/2017 | DAWN MC NULTY |
| Quality Review Completed | 7/7/2017 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 7/13/2017 | APPLICANT |
| Green Plans Picked Up | 7/13/2017 | APPLICANT |
| Applicant returned to address corrections | 9/13/2017 | DAWN MC NULTY |
| Applicant returned to address corrections | 9/27/2017 | DAWN MC NULTY |
| Applicant returned to address corrections | 5/17/2018 | DAWN MC NULTY |
| Plan Check Approved | 5/29/2018 | DAWN MC NULTY |
| Issued | 6/20/2018 | LADBS |
| CofO in Progress | 8/15/2020 | STUART CHAPMAN |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
| CofO Issued | 3/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/1/2017 | KENNETH PHAM |
| BHO/Hillside ordinance | Cleared | 9/1/2017 | KENNETH PHAM |
| BHO/Hillside ordinance | Cleared | 9/1/2017 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2017 | KENNETH PHAM |
| Sewer availability | Cleared | 9/1/2017 | KENNETH PHAM |
| Green Code | Cleared | 9/8/2017 | MICKEY YAMASHITA |
| GPI Written Notices | Cleared | 9/27/2017 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 9/27/2017 | DAWN MC NULTY |
| Green Code | Cleared | 4/26/2018 | MICKEY YAMASHITA |
| Grading Pre-Inspection | Cleared | 5/17/2018 | DAWN MC NULTY |
Contact Information
| Architect | , ; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/27/2018 | Corrections Issued | DAVID CHAN |
| Footing/Foundation/Slab | 11/30/2018 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 12/11/2018 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 12/11/2018 | Corrections Issued | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 12/19/2018 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 12/19/2018 | Corrections Issued | DAVID CHAN |
| Masonry Wall/Backfill | 12/19/2018 | Corrections Issued | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 12/21/2018 | No Access for Inspection | JENNIFER RABUCHIN |
| Masonry Wall/Backfill | 12/21/2018 | No Access for Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 12/26/2018 | Partial Approval | DAVID CHAN |
| Masonry Wall/Backfill | 12/26/2018 | Corrections Issued | DAVID CHAN |
| Pre-Inspection | 3/6/2019 | Partial Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 6/25/2019 | Partial Approval | DAVID CHAN |
| Wood Frame | 6/25/2019 | Not Ready for Inspection | DAVID CHAN |
| Insulation | 7/3/2019 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 7/30/2019 | Corrections Issued | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 8/2/2019 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 8/10/2020 | Approved | STUART CHAPMAN |
| Drywall Nailing | 8/10/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/10/2020 | Approved | STUART CHAPMAN |
| Final | 8/10/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/10/2020 | Approved | STUART CHAPMAN |
| Green Building Final | 8/10/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/10/2020 | Approved | STUART CHAPMAN |
| HVAC-Final | 8/10/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/10/2020 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2020 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 8/10/2020 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/14/2020 | Approved | STUART CHAPMAN |
| Final | 8/14/2020 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 8/14/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/14/2020 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2020 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 8/14/2020 | Approved | STUART CHAPMAN |