12373 W PIERCE ST 91331

Certificate Information: 12373 W PIERCE ST 91331

Application / Permit
17014-20000-02925
Plan Check / Job No.
B17VN08952
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
CONVERT (E) 18'-3" x 18'-6" GARAGE TO RECREATION ROOM AND ADDITION OF 15'-0" x 16'-9" TO NEW RECREATION ROOM. ALL WORK PER ENGINEERING. SEE COMMENTS.
Permit Issued
Issued on 8/25/2017
Issuing Office
Valley
Current Status
CofO Issued on 4/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2017 APPLICANT
Assigned to Plan Check Engineer 6/20/2017 MENA WASSEF
Corrections Issued 6/20/2017 MENA WASSEF
Plan Check Approved 8/25/2017 ALDOUS CHIC
Issued 8/25/2017 LADBS
CofO in Progress 4/8/2026 MICHEL ABAJAN
Permit Finaled 4/22/2026 RUBEN SALAS
CofO Issued 4/22/2026 RUBEN SALAS
Permit Finaled 4/22/2026 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 7/13/2017 JESSE RAMOS
ZA Case Cleared 7/13/2017 JESSE RAMOS
ZA Case Cleared 7/13/2017 JESSE RAMOS
ZA Case Cleared 7/13/2017 JESSE RAMOS
ZA Case Cleared 7/13/2017 JESSE RAMOS
ZA Case Cleared 7/13/2017 JESSE RAMOS
ZA Case Cleared 7/13/2017 JESSE RAMOS
Low Impact Development Cleared 8/24/2017 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 8/25/2017 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 8/25/2017 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada, Mynor Anibal; Lic. No.: C48666 22634 SYLVAN ST      WOODLAND HILLS, CA 91367

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/5/2017 Corrections Issued JEFFREY PARD
Deputy Drilled-In Anchors 9/7/2017 Approved JEFFREY PARD
BUILDING-Rough-Frame 9/19/2017 Corrections Issued JEFFREY PARD
Green Building Rough 9/19/2017 Not Ready for Inspection JEFFREY PARD
Insulation 9/27/2017 Approved JEFFREY PARD
Interior/Exterior Lathing 9/27/2017 Approved JEFFREY PARD
Drywall Nailing 10/3/2017 Approved JEFFREY PARD
Green Building Rough 10/3/2017 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/17/2025 Partial Approval JACK KARGODORIAN
Final 12/17/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 12/17/2025 Partial Approval JACK KARGODORIAN
Green Building Final 12/17/2025 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 12/17/2025 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 1/6/2026 Approved MICHEL ABAJAN
Final 1/6/2026 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 1/6/2026 Approved MICHEL ABAJAN
Green Building Final 1/6/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/6/2026 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/6/2026 Approved MICHEL ABAJAN
Final 4/7/2026 OK to Issue CofO MICHEL ABAJAN