6013 N LAURELGROVE AVE 91606
Certificate Information: 6013 N LAURELGROVE AVE 91606
- Application / Permit
- 17014-20000-02921
- Plan Check / Job No.
- B17VN08936
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 25'-0" X 25'-0" ADDITION TO AND CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069. ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/22/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2017 | JEROME MAGAT PALMA |
| Corrections Issued | 6/26/2017 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 6/28/2017 | APPLICANT |
| Plan Check Approved | 8/17/2017 | JEROME MAGAT PALMA |
| Issued | 8/22/2017 | LADBS |
| CofO in Progress | 9/11/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 9/23/2025 | RUBEN SALAS |
| CofO Issued | 9/23/2025 | RUBEN SALAS |
| Permit Finaled | 9/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2017 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2017 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 8/17/2017 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 8/17/2017 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/7/2017 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 9/19/2017 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2017 | Partial Inspection | WILLIAM KUEHN |
| Sewer | 12/5/2017 | Approved | WILLIAM KUEHN |
| Shower Pan | 12/5/2017 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/18/2017 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 12/18/2017 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 12/18/2017 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 12/18/2017 | Not Ready for Inspection | COREY HUPP |
| Shower Pan | 12/18/2017 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 1/26/2018 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 1/26/2018 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 2/6/2018 | Partial Approval | COREY HUPP |
| Green Building Rough | 2/6/2018 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 2/20/2018 | Approved | KEVIN BEAULIEU |
| ELECTRICAL-Rough | 2/20/2018 | Approved | KEVIN BEAULIEU |
| Green Building Rough | 2/20/2018 | Approved | KEVIN BEAULIEU |
| Interior/Exterior Lathing | 2/20/2018 | Approved | KEVIN BEAULIEU |
| PLUMBING-Rough | 2/20/2018 | Approved | KEVIN BEAULIEU |
| Shower Pan | 2/20/2018 | Approved | KEVIN BEAULIEU |
| Insulation | 2/23/2018 | Approved | JOHN KIDWELL |
| Drywall Nailing | 3/9/2018 | Approved | COREY HUPP |
| Special/Order Compliance | 7/3/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 7/25/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 7/25/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/25/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 9/3/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 9/3/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/3/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/4/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 9/4/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |