1372 N GOUCHER ST 90272
Certificate Information: 1372 N GOUCHER ST 90272
- Application / Permit
- 17014-20000-02900
- Plan Check / Job No.
- B17VN08863
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 46'8"X12'11" IRREGULAR 2ND FLOOR ADDITION AND 2ND FLOOR REMODEL. ROOF REMODELING. FULL 1ST FLOOR INTERIOR REMODELING. NFPA-13D FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 3/7/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2017 | MARVEL DELACRUZ |
| Green Plans Picked Up | 6/29/2017 | APPLICANT |
| Corrections Issued | 7/1/2017 | MARVEL DELACRUZ |
| Quality Review Completed | 7/6/2017 | CHON CHIO KUO |
| Building Plans Picked Up | 7/10/2017 | APPLICANT |
| Applicant returned to address corrections | 10/10/2017 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 10/19/2017 | MARVEL DELACRUZ |
| Plan Check Approved | 11/17/2017 | MARVEL DELACRUZ |
| Issued | 3/7/2018 | LADBS |
| CofO in Progress | 8/30/2022 | KEVIN SARGSYAN |
| No Progress | 2/8/2023 | KENNETH NAGLE |
| CofO in Progress | 6/23/2023 | KENNETH NAGLE |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
| CofO Issued | 7/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/26/2017 | KENNETH PHAM |
| BHO/Hillside ordinance | Cleared | 7/26/2017 | KENNETH PHAM |
| BHO/Hillside ordinance | Cleared | 7/26/2017 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2017 | KENNETH PHAM |
| Sewer availability | Cleared | 7/26/2017 | KENNETH PHAM |
| Hydrant and Access approval | Cleared | 8/11/2017 | JOHN DALLAS |
| Construction near power lines | Cleared | 9/25/2017 | OSCAR CASTRO |
| Construction within easement | Cleared | 9/25/2017 | OSCAR CASTRO |
| Low Impact Development | Cleared | 10/19/2017 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 10/19/2017 | STEVE MELGAR |
| Green Code | Cleared | 11/1/2017 | MICKEY YAMASHITA |
| GPI Written Notices | Cleared | 11/17/2017 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 11/17/2017 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/30/2018 | Partial Inspection | RICHARD STEINBACH |
| Footing/Foundation/Slab | 5/11/2018 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 5/17/2018 | Corrections Issued | VINCENT SCIPIONI |
| Footing/Foundation/Slab | 5/22/2018 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 5/30/2018 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2018 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Rough | 9/6/2018 | Corrections Issued | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2018 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 9/6/2018 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 9/6/2018 | Corrections Issued | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 1/2/2019 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 1/2/2019 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2019 | Corrections Issued | ANDREW NAVE |
| Green Building Rough | 1/2/2019 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 1/2/2019 | Corrections Issued | ANDREW NAVE |
| Verify Sprinkler Sign Off | 1/2/2019 | Not Ready for Inspection | ANDREW NAVE |
| Deputy Wood Construction | 1/3/2019 | Partial Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 1/3/2019 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 1/3/2019 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 1/3/2019 | Approved | RICHARD STEINBACH |
| Wood Frame | 1/3/2019 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2019 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 2/27/2019 | Approved | RICHARD STEINBACH |
| Green Building Rough | 2/27/2019 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 2/27/2019 | Partial Approval | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 2/27/2019 | Approved | RICHARD STEINBACH |
| Insulation | 3/21/2019 | Approved | RICHARD STEINBACH |
| Drywall Nailing | 4/23/2019 | Approved | RICHARD STEINBACH |
| Shower Pan | 4/23/2019 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 5/9/2019 | Approved | TIM CHRISTENSEN |
| ELECTRICAL-Final | 7/29/2019 | Corrections Issued | DANNY TOLENTINO |
| PLUMBING-Final | 9/19/2019 | Corrections Issued | DANNY TOLENTINO |
| PLUMBING-Final | 11/14/2019 | Corrections Issued | DANNY TOLENTINO |
| Final | 6/17/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 6/17/2020 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/17/2020 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 6/17/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 7/25/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Smoke Detectors | 7/25/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 8/17/2022 | Corrections Issued | KEVIN SARGSYAN |
| Smoke Detectors | 8/17/2022 | Approved | KEVIN SARGSYAN |
| Final | 8/29/2022 | OK to Issue CofO | KEVIN SARGSYAN |