1325 N WETHERLY DR 90069
Certificate Information: 1325 N WETHERLY DR 90069
- Application / Permit
- 17014-20000-02554
- Plan Check / Job No.
- B17VN07904
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 28'2" X 14'4" (IRREGULAR) ADDITION FOR NEW ENTERTAINMENT ROOM AND 52'8" X 24'2" ADDITION FOR NEW SECOND FLOOR DECK. INTERIOR REMODEL, INCLUDING NEW BEDROOM.
- Permit Issued
- Issued on 1/23/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2017 | STANLEY RAAP |
| Corrections Issued | 6/13/2017 | STANLEY RAAP |
| Quality Review Completed | 6/15/2017 | CHON CHIO KUO |
| Building Plans Picked Up | 6/16/2017 | APPLICANT |
| Green Plans Picked Up | 6/16/2017 | APPLICANT |
| Plan Check Approved | 1/23/2018 | STANLEY RAAP |
| Issued | 1/23/2018 | LADBS |
| CofO in Progress | 10/29/2021 | BRAD BESCOS |
| Permit Finaled | 11/6/2021 | DEROLD HAUFF |
| CofO Issued | 11/6/2021 | DEROLD HAUFF |
| Permit Finaled | 11/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/9/2017 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 8/9/2017 | ROCHELLE DUNGCA |
| BHO/Hillside ordinance | Cleared | 8/11/2017 | ROCHELLE DUNGCA |
| BHO/Hillside ordinance | Cleared | 8/11/2017 | ROCHELLE DUNGCA |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2017 | ALFREDO JARA |
| Green Code | Cleared | 8/17/2017 | MICKEY YAMASHITA |
| Sewer availability | Cleared | 8/17/2017 | ALFREDO JARA |
| BHO/Hillside ordinance | Cleared | 8/29/2017 | ROCHELLE DUNGCA |
| GPI Written Notices | Cleared | 1/23/2018 | STANLEY RAAP |
| Grading Pre-Inspection | Cleared | 1/23/2018 | STANLEY RAAP |
Contact Information
| Contractor | Pomer Construction Inc; Lic. No.: 908354-B | 8391 BEVERLY BLVD #294 LOS ANGELES, CA 90048 |
| Engineer | Gaprelian, Armen; Lic. No.: GE2668 | 1445 VALLEY VIEW ROAD #10 GLENDALE, CA 91202 |
| Engineer | Rhee, Kyle; Lic. No.: C78215 | 3855 W 7TH ST #304 LOS ANGELES, CA 90005 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/13/2018 | No Access for Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 7/2/2018 | Corrections Issued | DANNY TOLENTINO |
| Footing/Foundation/Slab | 7/5/2018 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 7/12/2018 | Partial Approval | DANIEL GONZALEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2018 | Partial Approval | DANIEL GONZALEZ |
| Green Building Rough | 7/17/2018 | Not Ready for Inspection | DANIEL GONZALEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2018 | Corrections Issued | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 11/14/2018 | Approved | DANIEL GONZALEZ |
| Green Building Rough | 11/14/2018 | Approved | DANIEL GONZALEZ |
| Rough-Elec/Plmb/HVAC | 11/14/2018 | Approved | DANIEL GONZALEZ |
| Insulation | 1/2/2019 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/2/2019 | Approved | RAUL BARAJAS |
| Shower Pan | 1/2/2019 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/15/2019 | Approved | DANNY TOLENTINO |
| Interior/Exterior Lathing | 1/15/2019 | Partial Approval | DANNY TOLENTINO |
| ELECTRICAL-Final | 7/24/2019 | Corrections Issued | RICHARD STEINBACH |
| Final | 7/24/2019 | Corrections Issued | RICHARD STEINBACH |
| Footing/Foundation/Slab | 7/24/2019 | Approved | RICHARD STEINBACH |
| Green Building Final | 7/24/2019 | Approved | RICHARD STEINBACH |
| HVAC-Final | 7/24/2019 | Corrections Issued | RICHARD STEINBACH |
| PLUMBING-Final | 7/24/2019 | Corrections Issued | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 7/24/2019 | SGSOV Not Ready | RICHARD STEINBACH |
| Smoke Detectors | 7/24/2019 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Final | 9/16/2019 | Approved | RICHARD STEINBACH |
| Final | 9/16/2019 | Not Ready for Inspection | RICHARD STEINBACH |
| HVAC-Final | 9/16/2019 | Approved | RICHARD STEINBACH |
| PLUMBING-Final | 9/16/2019 | Approved | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 9/16/2019 | SGSOV Approved | RICHARD STEINBACH |
| Smoke Detectors | 9/16/2019 | Approved | RICHARD STEINBACH |
| Final | 2/24/2020 | Not Ready for Inspection | RICHARD STEINBACH |
| Final | 12/18/2020 | Corrections Issued | RAUL BARAJAS |
| Final | 1/7/2021 | Corrections Issued | RAUL BARAJAS |
| Final | 10/29/2021 | OK to Issue CofO | BRAD BESCOS |