5134 N CEDROS AVE 91403
Certificate Information: 5134 N CEDROS AVE 91403
- Application / Permit
- 17014-20000-02202
- Plan Check / Job No.
- B17VN06877
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 40' x 31'-8" Irregular Shape Basement , 21'-9" x 12'-10" Irr. (N) Covered Porch & Entry on 1st Floor, 40' x 40' Irr. (3) Bedrooms and (1) 3/4 Bath and (1) Full Bath (N) 2nd Story & Major remodel maintaing 81'-8" linear foot of (E) wall walls, remodel kitchen, Convert (E) Bedroom to Family Room.
- Permit Issued
- Issued on 11/14/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2017 | OMID HEDAYAT |
| Corrections Issued | 6/12/2017 | OMID HEDAYAT |
| Quality Review Completed | 6/13/2017 | CHON CHIO KUO |
| Building Plans Picked Up | 6/14/2017 | APPLICANT |
| Green Plans Picked Up | 7/5/2017 | APPLICANT |
| Applicant returned to address corrections | 4/23/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/14/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/31/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/2/2018 | OMID HEDAYAT |
| Plan Check Approved | 7/2/2018 | OMID HEDAYAT |
| Plan Check Approved | 11/14/2018 | OMID HEDAYAT |
| Issued | 11/14/2018 | LADBS |
| CofO in Progress | 10/3/2022 | JACK KARGODORIAN |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
| CofO Issued | 10/14/2022 | DEROLD HAUFF |
| Permit Finaled | 10/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2018 | EDUARDO PEDROZA |
| Green Code | Cleared | 5/23/2018 | ROLLIN GETTLE III |
| Miscellaneous | Cleared | 5/23/2018 | ANNA VIDAL |
| Miscellaneous | Cleared | 5/23/2018 | ANNA VIDAL |
| Miscellaneous | Cleared | 5/23/2018 | ANNA VIDAL |
| Miscellaneous | Cleared | 5/23/2018 | ANNA VIDAL |
| Sewer availability | Cleared | 5/23/2018 | EDUARDO PEDROZA |
| ZA Case | Cleared | 5/23/2018 | ANNA VIDAL |
| ZA Case | Cleared | 5/23/2018 | ANNA VIDAL |
| ZI | Cleared | 5/23/2018 | ANNA VIDAL |
| Miscellaneous | Cleared | 5/31/2018 | OMID HEDAYAT |
| Low Impact Development | Cleared | 6/1/2018 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 6/1/2018 | STEVE MELGAR |
| ZA Case | Cleared | 6/14/2018 | TOM HENRY |
| Excavation more than 5-ft deep | Cleared | 7/20/2018 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cai, Luo B; Lic. No.: C80352 | 5244 HUCKLEBERRY OAK STREET SIMI VALLEY, CA 93063 |
| Engineer | Gorgy, Moheb Shohdy; Lic. No.: C53260 | 1545 VICTORY BLVD STE 102 GLENDALE, CA 91201 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/30/2019 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 10/29/2019 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 10/30/2019 | Approved | DANIEL ORRANTE |
| Footing/Foundation/Slab | 11/4/2019 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 7/23/2020 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 7/23/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/27/2020 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 7/27/2020 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/16/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/16/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/16/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/22/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 2/22/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 2/22/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 3/1/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 3/1/2021 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 3/1/2021 | Corrections Issued | BRENDAN LOONEY |
| Deputy Wood Construction | 3/24/2021 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 3/25/2021 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Rough | 3/25/2021 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 3/26/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 5/27/2021 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 5/27/2021 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 9/15/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/15/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 9/15/2021 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 9/20/2021 | No Access for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/27/2021 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/2/2021 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 3/7/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 3/7/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/7/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/11/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 3/11/2022 | Approved | JACK KARGODORIAN |
| Insulation | 5/4/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/28/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/1/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/4/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 8/4/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/9/2022 | Approved | JACK KARGODORIAN |
| HVAC-Final | 8/9/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 8/9/2022 | Corrections Issued | JACK KARGODORIAN |
| Drywall Nailing | 8/29/2022 | Not Ready for Inspection | DAVID MATSON |
| Final | 8/29/2022 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 8/29/2022 | Not Ready for Inspection | DAVID MATSON |
| Reinforced Masonry Frame | 8/29/2022 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 8/29/2022 | Not Ready for Inspection | DAVID MATSON |
| Structural Steel Frame | 8/29/2022 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 9/2/2022 | Corrections Issued | JACK KARGODORIAN |
| Grading Pre-Inspection | 9/2/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Service/Power Release | 9/2/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 9/13/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/13/2022 | Approved | JACK KARGODORIAN |
| Final | 9/13/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 9/13/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 9/13/2022 | Approved | JACK KARGODORIAN |
| Reinforced Masonry Frame | 9/13/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 9/13/2022 | Approved | JACK KARGODORIAN |
| Structural Steel Frame | 9/13/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/15/2022 | Approved | JACK KARGODORIAN |
| Final | 9/15/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/19/2022 | Approved | JACK KARGODORIAN |
| Final | 10/3/2022 | OK to Issue CofO | JACK KARGODORIAN |