24239 W GILMORE ST 91307
Certificate Information: 24239 W GILMORE ST 91307
- Application / Permit
- 17014-20000-01693
- Plan Check / Job No.
- B17VN05284
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 42'-10" x 31'-3" 2ND STORY ADDITION TO (E) ONE STORY SFD
- Permit Issued
- Issued on 6/9/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2017 | ARTIN ZARUKIAN |
| Green Plans Picked Up | 5/5/2017 | APPLICANT |
| Corrections Issued | 5/6/2017 | ARTIN ZARUKIAN |
| Quality Review Completed | 5/9/2017 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 5/19/2017 | APPLICANT |
| Plan Check Approved | 6/2/2017 | ARTIN ZARUKIAN |
| Issued | 6/9/2017 | LADBS |
| CofO in Progress | 7/30/2018 | PETER FOLLING |
| CofO Issued | 11/17/2020 | JOHN JANSON |
| Permit Finaled | 11/17/2020 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2017 | IRENE CHIA |
| Green Code | Cleared | 5/25/2017 | MICHAEL AYERS |
| Sewer availability | Cleared | 5/25/2017 | IRENE CHIA |
| Low Impact Development | Cleared | 6/1/2017 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 6/1/2017 | ARMENIA AGUILAR |
Contact Information
| Contractor | Zigner Ami General Contractor; Lic. No.: 493578-B | PO BOX 6461 WOODLAND HILLS, CA 91365 |
| Engineer | Helou, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/3/2017 | Approved | FRED HANNUM |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2017 | Partial Approval | FRED HANNUM |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2018 | Partial Approval | FRED HANNUM |
| Green Building Rough | 2/5/2018 | Not Ready for Inspection | FRED HANNUM |
| BUILDING-Rough-Frame | 2/21/2018 | Approved | FRED HANNUM |
| ELECTRICAL-Rough | 2/21/2018 | Approved | FRED HANNUM |
| Gas Test | 2/21/2018 | Approved | FRED HANNUM |
| Green Building Rough | 2/21/2018 | Approved | FRED HANNUM |
| HVAC-Rough | 2/21/2018 | Approved | FRED HANNUM |
| PLUMBING-Rough | 2/21/2018 | Approved | FRED HANNUM |
| Insulation | 3/22/2018 | Approved | FRED HANNUM |
| Interior/Exterior Lathing | 3/22/2018 | Approved | FRED HANNUM |
| Shower Pan | 3/22/2018 | Approved | FRED HANNUM |
| Drywall Nailing | 4/2/2018 | Approved | FRED HANNUM |
| Interior/Exterior Lathing | 4/2/2018 | Approved | FRED HANNUM |
| ELECTRICAL-Final | 7/16/2018 | Not Ready for Inspection | DONALD SUNSERI |
| Final | 7/16/2018 | Not Ready for Inspection | DONALD SUNSERI |
| Green Building Final | 7/16/2018 | Not Ready for Inspection | DONALD SUNSERI |
| HVAC-Final | 7/16/2018 | Not Ready for Inspection | DONALD SUNSERI |
| PLUMBING-Final | 7/16/2018 | Not Ready for Inspection | DONALD SUNSERI |
| SGSOV-Seismic Gas S/O Valve | 7/16/2018 | SGSOV Not Ready | DONALD SUNSERI |
| Smoke Detectors | 7/16/2018 | Approved | DONALD SUNSERI |
| ELECTRICAL-Final | 7/26/2018 | Approved | PETER FOLLING |
| Final | 7/26/2018 | OK to Issue CofO | PETER FOLLING |
| Green Building Final | 7/26/2018 | Approved | PETER FOLLING |
| HVAC-Final | 7/26/2018 | Approved | PETER FOLLING |
| PLUMBING-Final | 7/26/2018 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 7/26/2018 | SGSOV Approved | PETER FOLLING |
| Service/Power Release | 7/26/2018 | Not Ready for Inspection | PETER FOLLING |