3180 N LINDO ST 90068

Certificate Information: 3180 N LINDO ST 90068

Application / Permit
17014-20000-01356
Plan Check / Job No.
B17VN04306
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 31'0" X 24' 1ST FLOOR ADDITION TO CREATE (1) BEDROOM AND (1) BATHROOM , NEW 31'0"X 40'4" IRREGULAR SHAPE ADDITION TO 2ND FLOOR TO RELOCATE THE (E) KITCHEN AND CREATE (1) LAUNDRY , (1) POWDER ROOM ,NEW 20'6" X 21'6" ATTACHED GARAGE, NEW 31'0" X 40'4" IRREGULAR SHAPE 3RD FLOOR ADDITION TO CREATE A MASTER BEDROOM , MASTER BATHROOM, (2) W.I.C., (1) NEW BATHROOM ., NEW 31' X 5' REAR ATTACHED PATIO COVER AT 1ST FLOOR ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/4/2018
Issuing Office
Valley
Current Status
Issued on 5/4/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/30/2017 APPLICANT
Assigned to Plan Check Engineer 4/27/2017 RARES BODEA
Corrections Issued 5/3/2017 RARES BODEA
Green Plans Picked Up 5/8/2017 APPLICANT
Quality Review Completed 6/5/2017 TIEN JEN WANG
Building Plans Picked Up 6/5/2017 APPLICANT
Plan Check Approved 5/2/2018 RARES BODEA
Issued 5/4/2018 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 9/11/2017 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 9/11/2017 MARKOS PEREZ-BRAN
Drainage to Storm Drain Cleared 9/11/2017 MARKOS PEREZ-BRAN
Permit Cleared 9/11/2017 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 10/6/2017 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 10/6/2017 JOHN DALLAS
Construction near power lines Cleared 10/30/2017 RIDWAN HARDY
Construction within easement Cleared 10/30/2017 RIDWAN HARDY
GPI Written Notices Cleared 12/18/2017 RARES BODEA
Grading Pre-Inspection Cleared 12/18/2017 RARES BODEA
Low Impact Development Cleared 1/18/2018 RYAN HUDSON
Green Code Cleared 1/29/2018 ROLLIN GETTLE III
Roof/Waste drainage to street Cleared 5/3/2018 KAYLA PEJI

Contact Information

Architect Motamen, Azita; Lic. No.: C28112 16614 OAKVIEW COURT      ENCINO, CA 91436
Contractor Owner-Builder       ,
Engineer Kamkar, Albert; Lic. No.: C38311 12340 SANTA MONICA BLVD 236      SANTA MONICA, CA 90025
Geologist Schick, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/1/2018 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 8/15/2018 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 8/17/2018 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 8/23/2018 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 9/4/2018 Partial Approval BRIAN SULLIVAN
Deputy Steel/Welding 9/7/2018 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 9/27/2018 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 10/3/2018 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/31/2018 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 11/1/2018 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2018 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 11/14/2018 Partial Approval BRIAN SULLIVAN
Special/Order Compliance 11/28/2018 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/29/2018 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 3/15/2019 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2019 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 3/18/2019 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/3/2019 Partial Approval BRIAN SULLIVAN
Green Building Rough 6/3/2019 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 6/3/2019 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 6/13/2019 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 6/17/2019 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 6/17/2019 Partial Approval BRIAN SULLIVAN
Green Building Rough 6/17/2019 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 6/17/2019 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 7/26/2019 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 7/26/2019 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 7/26/2019 Corrections Issued BRIAN SULLIVAN
Verify Sprinkler Sign Off 7/26/2019 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 9/25/2019 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 9/25/2019 Partial Approval BRIAN SULLIVAN
Green Building Rough 9/25/2019 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 9/25/2019 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 9/25/2019 Partial Approval BRIAN SULLIVAN
Verify Sprinkler Sign Off 9/25/2019 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 11/26/2019 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 11/26/2019 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 11/26/2019 Corrections Issued BRIAN SULLIVAN
Verify Sprinkler Sign Off 11/26/2019 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 1/9/2020 Corrections Issued BRIAN SULLIVAN
Green Building Rough 1/9/2020 Approved BRIAN SULLIVAN
HVAC-Rough 1/9/2020 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 1/9/2020 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 1/27/2020 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 1/27/2020 Conditional Approval BRIAN SULLIVAN
HVAC-Rough 1/27/2020 Approved BRIAN SULLIVAN
PLUMBING-Rough 1/27/2020 Approved BRIAN SULLIVAN
Insulation 2/21/2020 Approved BRIAN SULLIVAN
Drywall Nailing 4/16/2020 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 6/4/2020 Approved BRIAN SULLIVAN
Special/Order Compliance 8/17/2020 Approved DAVID MATSON
Final 4/27/2021 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 4/27/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 4/27/2021 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/27/2021 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 4/27/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 1/27/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Final 2/2/2022 Approved BRIAN SULLIVAN
Special/Order Compliance 8/13/2024 Corrections Issued BRIAN SULLIVAN
Special/Order Compliance 5/8/2026 Corrections Issued ROY SPAULDING