4609 N PETIT AVE 91436
Certificate Information: 4609 N PETIT AVE 91436
- Application / Permit
- 17014-20000-01167
- Plan Check / Job No.
- B17VN03723
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO PORTION OF LIVING ROOM & MASTER BDRM BAY WINDOW (53SF), EXPAND (E) GARAGE, ADD STORAGE, MECHANICAL ROOM & HALLWAY AT BASEMENT, IRREGULAR ADDITIONS TO (E) 1ST FLR & ADD 2ND FLR TO (E) 1-STORY SFD W/ ATTACHED GARAGE & BASEMENT; MAJOR REMODEL (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 9/16/2019
- Issuing Office
- Valley
- Current Status
- Issued on 9/16/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/17/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2017 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/10/2017 | NILOOFAR MEHRAIN |
| Green Plans Picked Up | 4/11/2017 | APPLICANT |
| Quality Review Completed | 4/14/2017 | TIEN JEN WANG |
| Building Plans Picked Up | 4/17/2017 | APPLICANT |
| Applicant returned to address corrections | 10/29/2018 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/27/2018 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/18/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/16/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/3/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/28/2019 | NILOOFAR MEHRAIN |
| Issued | 9/16/2019 | LADBS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/9/2018 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/9/2018 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 4/9/2018 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2018 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 4/9/2018 | JOHN DALLAS |
| Sewer availability | Cleared | 4/9/2018 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 10/18/2018 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/18/2018 | CHRISTINE REUSCH |
| GPI Written Notices | Cleared | 10/29/2018 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 10/29/2018 | NILOOFAR MEHRAIN |
| Green Code | Cleared | 11/27/2018 | ROLLIN GETTLE III |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Reith, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
| Engineer | Tsao,, Tze-Tzong; Lic. No.: C46886 | 9428 ETON AVE STE M CHATSWORTH, CA 91311 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/17/2020 | Partial Inspection | RONALD COWAN |
| Pre-Inspection | 4/13/2021 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Corrections Issued | THOMAS FINNILA |
| Grading Pre-Inspection | 9/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/9/2025 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/2/2025 | Approved | JOHN KIDWELL |
| Deputy Reinf. Concrete | 7/7/2025 | Approved | SEAN WIRCH |
| Deputy Reinf. Concrete | 9/12/2025 | Conditional Approval | THOMAS FINNILA |
| Reinforced Concrete Frame | 9/15/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 9/22/2025 | Conditional Approval | THOMAS FINNILA |
| Reinforced Concrete Frame | 9/22/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 9/23/2025 | Conditional Approval | HENRY KIM |
| Reinforced Concrete Frame | 9/24/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 9/25/2025 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 10/1/2025 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/10/2025 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Partial Approval | THOMAS FINNILA |
| Deputy Steel/Welding | 11/4/2025 | Conditional Approval | THOMAS FINNILA |
| Wood Frame | 11/7/2025 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2025 | Partial Approval | JUAN ALVARADO |
| Deputy Drilled-In Anchors | 12/5/2025 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/8/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Wood Construction | 12/11/2025 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Reinf. Concrete | 12/22/2025 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/16/2026 | Partial Approval | JOHN KIDWELL |
| Sewer | 4/16/2026 | Approved | JOHN KIDWELL |