23000 W BALTAR ST 91304
Certificate Information: 23000 W BALTAR ST 91304
- Application / Permit
- 17014-20000-00947
- Plan Check / Job No.
- B17VN03024
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 46'-0" X 23'-4" IRREG SHAPED ADDITION TO (E) DWELLING FOR NEW BEDROOM, HALF BATHROOM, 3/4 BATHROOM, LIVING ROOM, AND CLOSET. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 5/9/2017
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2017 | SIAVOSH POURSABAHIAN |
| Corrections Issued | 3/7/2017 | STANLEY RAAP |
| Plan Check Approved | 5/2/2017 | JEROME MAGAT PALMA |
| Issued | 5/9/2017 | LADBS |
| CofO in Progress | 5/25/2022 | CHRIS CHRISTENSEN |
| CofO Issued | 6/1/2022 | MICHAEL SMITH |
| Permit Finaled | 6/1/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2017 | KENNETH PHAM |
| Sewer availability | Cleared | 3/10/2017 | KENNETH PHAM |
| Low Impact Development | Cleared | 5/1/2017 | MATTHEW JIMENEZ |
| Roof/Waste drainage to street | Cleared | 5/1/2017 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moser, Bradley Charles; Lic. No.: C68803 | 4111 W 239TH ST 28 TORRANCE, CA 90505 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/5/2019 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 1/21/2020 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 2/28/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 2/28/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 4/3/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 4/3/2020 | Partial Approval | DAVID STEPANYAN |
| Insulation | 4/23/2020 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2020 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 9/14/2020 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 9/14/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 9/14/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/25/2020 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 12/24/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 12/24/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 12/24/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 1/4/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 1/4/2021 | Partial Approval | DAVID STEPANYAN |
| Insulation | 2/5/2021 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 4/16/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 4/16/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 11/15/2021 | Approved | DAVID STEPANYAN |
| Final | 11/15/2021 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 11/15/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Final | 11/15/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Not Ready | DAVID STEPANYAN |
| Smoke Detectors | 11/15/2021 | Approved | DAVID STEPANYAN |
| Final | 4/28/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 4/28/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Final | 5/24/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| HVAC-Final | 5/24/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Approved | CHRIS CHRISTENSEN |