100 WORLD WAY 90045

Certificate Information: 100 WORLD WAY 90045

Application / Permit
17014-10008-06579
Plan Check / Job No.
B19LA14647
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(3) Airport Building
Work Description
SUPPLEMENTAL TO PERMIT # 17014-10000-06579 FOR DEFERRED DESIGN ITEM FOR SEISMIC BRACING OF OVERHEAD HYDRONIC PIPING, DUCTWORK , AND MECHANICAL EQUIPMENT ANCHORAGE.
Permit Issued
Issued on 10/9/2019
Issuing Office
Metro
Current Status
Permit Finaled on 11/4/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2019 APPLICANT
Assigned to Plan Check Engineer 7/22/2019 EDUARDO RODRIGUEZ
Corrections Issued 7/22/2019 EDUARDO RODRIGUEZ
Quality Review Completed 8/1/2019 LIPING TENG
Applicant returned to address corrections 10/3/2019 EDUARDO RODRIGUEZ
Plan Check Approved 10/9/2019 EDUARDO RODRIGUEZ
Issued 10/9/2019 LADBS
Permit Finaled 11/4/2020 JONATHAN ALLEN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Pan-Pacific Mechanical Llc; Lic. No.: 1006709-A 18250 EUCLID STREET      FOUNTAIN VALLEY, CA 92708
Engineer Hoang,, Soi Quang; Lic. No.: C61625 8323 JOSARD ROAD      SAN GABRIEL, CA 91775

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 2/7/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 2/10/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 2/12/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 2/13/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 2/20/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 2/21/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 2/24/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 2/25/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 2/26/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 3/3/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 3/10/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 3/11/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 3/16/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 3/17/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 3/24/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 3/27/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 4/1/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 4/3/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 4/6/2020 Approved JONATHAN ALLEN
Special/Order Compliance 4/9/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 4/14/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 4/16/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 4/22/2020 Partial Approval ALBERT COMISARI
Light Gage Steel Frame 4/23/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 4/24/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 4/28/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 4/29/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 4/30/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 5/4/2020 Approved JONATHAN ALLEN
Special/Order Compliance 5/5/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 5/6/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 5/7/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 5/8/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 5/12/2020 Approved JONATHAN ALLEN
Special/Order Compliance 5/13/2020 Approved JONATHAN ALLEN
Special/Order Compliance 5/14/2020 Approved JONATHAN ALLEN
Special/Order Compliance 5/19/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 5/20/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 5/21/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 5/22/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 5/26/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 5/27/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 6/11/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 6/12/2020 Approved JONATHAN ALLEN
Special/Order Compliance 6/15/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 6/18/2020 Partial Approval JONATHAN ALLEN
Special/Order Compliance 6/19/2020 Partial Approval JONATHAN ALLEN
Special/Order Compliance 6/23/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 6/24/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 7/14/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 7/15/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 7/16/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 7/20/2020 Partial Approval JONATHAN ALLEN
Special/Order Compliance 7/21/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 7/24/2020 Partial Approval ALBERT COMISARI
Special/Order Compliance 7/28/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 7/30/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 7/31/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 8/3/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 8/5/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 8/6/2020 Approved JONATHAN ALLEN
Special/Order Compliance 8/7/2020 Approved JONATHAN ALLEN
Light Gage Steel Frame 8/10/2020 Not Ready for Inspection ALBERT COMISARI
Special/Order Compliance 8/11/2020 Conditional Approval ALBERT COMISARI
Light Gage Steel Frame 8/17/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 8/18/2020 Conditional Approval ALBERT COMISARI
Special/Order Compliance 8/19/2020 Approved JONATHAN ALLEN
Special/Order Compliance 10/8/2020 Not Ready for Inspection ALBERT COMISARI
Final 10/28/2020 Conditional Approval ALBERT COMISARI