2117 S PARNELL AVE 90025
Certificate Information: 2117 S PARNELL AVE 90025
- Application / Permit
- 17014-10005-02669
- Plan Check / Job No.
- B24WL06656
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Supplemental permit to # 17014-30000-02669 to change the engineer of record and architectural and structural design, propose interior layout and exterior changes with no change to the floor area
- Permit Issued
- Issued on 10/16/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/24/2025
Permit Application Status History
| Submitted | 8/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | REZA HAGHIGHAT |
| Corrections Issued | 9/8/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 9/9/2024 | CHIHARU SUZUKI |
| Plan Check Approved | 10/14/2024 | REZA HAGHIGHAT |
| Issued | 10/16/2024 | APPLICANT |
| Permit Finaled | 6/24/2025 | DANIEL VERA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Copper Construction Llc; Lic. No.: 1060557-B | , |
| Engineer | Zhang,, Lei; Lic. No.: C89369 | 530 TECHNOLOGY DR IRVINE, CA 92618 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/31/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 1/31/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 1/31/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/31/2025 | Approved | EVAN COOPER |
| Shower Pan | 2/7/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/21/2025 | Approved | STEPHANIE SWANSON |
| Wood Frame | 3/12/2025 | Corrections Issued | DANIEL VERA |
| Interior/Exterior Lathing | 3/19/2025 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 3/21/2025 | Partial Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/21/2025 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 3/26/2025 | Partial Approval | DANIEL VERA |
| Green Building Rough | 3/26/2025 | Partial Approval | DANIEL VERA |
| Insulation | 3/26/2025 | Partial Approval | DANIEL VERA |
| Drywall Nailing | 4/1/2025 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 4/4/2025 | Partial Approval | DANIEL VERA |
| Drywall Nailing | 4/4/2025 | Approved | DANIEL VERA |
| Green Building Rough | 4/4/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 6/10/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 6/10/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 6/10/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 6/10/2025 | Approved | DANIEL VERA |
| Smoke Detectors | 6/10/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 6/13/2025 | Approved | DANIEL VERA |
| HVAC-Final | 6/13/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 6/13/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 6/24/2025 | Approved | DANIEL VERA |
| Final | 6/24/2025 | Permit Finaled | DANIEL VERA |
| Smoke Detectors | 6/24/2025 | Approved | DANIEL VERA |