2709 1/2 E DARWIN AVE 90031
Certificate Information: 2709 1/2 E DARWIN AVE 90031
- Application / Permit
- 17014-10001-05812
- Plan Check / Job No.
- X17LA21895
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT # 17014-10000-05812 TO CHANGE FROM OWNER-BLDR TO CONTRACTOR "JASSOS CONSTRUCTION"
- Permit Issued
- Issued on 12/19/2017
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/29/2018
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Issued | 12/19/2017 | LADBS |
| Permit Finaled | 8/28/2018 | OSVALDO PARAMO |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| No Data Available. |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/3/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Reinforced Concrete Frame | 1/3/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 1/4/2018 | Conditional Approval | DOMINIC DANERI |
| Excavation/Setback/Form/Re-Bar | 1/4/2018 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/4/2018 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2018 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 4/17/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2018 | Partial Inspection | OSVALDO PARAMO |
| Wood Frame | 4/26/2018 | Corrections Issued | OSVALDO PARAMO |
| Wood Frame | 5/2/2018 | Approved | OSVALDO PARAMO |
| Insulation | 5/4/2018 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 5/14/2018 | Partial Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/14/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/21/2018 | Approved | OSVALDO PARAMO |
| Final | 7/3/2018 | No Access for Inspection | OSVALDO PARAMO |
| Final | 7/6/2018 | Not Ready for Inspection | OSVALDO PARAMO |
| Insulation | 7/9/2018 | No Access for Inspection | ENRIQUE MIRELES |
| Final | 7/17/2018 | Corrections Issued | OSVALDO PARAMO |
| Final | 8/13/2018 | Not Ready for Inspection | DOMINIC DANERI |
| Final | 8/16/2018 | Corrections Issued | OSVALDO PARAMO |
| Final | 8/28/2018 | Permit Finaled | OSVALDO PARAMO |