810 N KENMORE AVE 90029

Certificate Information: 810 N KENMORE AVE 90029

Application / Permit
17014-10001-01976
Plan Check / Job No.
B24LA23884
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO 17014-10000-01976 TO INCLUDE A ROOF DECK, INCREASE AREA OF ADDITION AT DETACHED ADU
Permit Issued
Issued on 2/7/2025
Issuing Office
Metro
Current Status
Permit Finaled on 3/9/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 PRANITA SHAH
Corrections Issued 10/9/2024 PRANITA SHAH
Quality Review Completed 11/13/2024 GARO TELMI
Building Plans Picked Up 11/14/2024 APPLICANT
Plan Check Approved 2/7/2025 PRANITA SHAH
Issued 2/7/2025 APPLICANT
Permit Finaled 3/2/2026 FREDDIE RIVERA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/17/2024 CELINA MORENO
Sewer availability Cleared 12/17/2024 CELINA MORENO
Low Impact Development Cleared 1/13/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 2/5/2025 CELINA MORENO

Contact Information

Contractor Mateos Construction & Remodeling Co; Lic. No.: 1034279-B 10378 MARKLEIN AVE      MISSION HILLS, CA 91345
Engineer Kim, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/27/2025 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 4/7/2025 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Partial Approval FREDDIE RIVERA
Green Building Rough 5/27/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 1/7/2026 Approved FREDDIE RIVERA
Gas Test 1/7/2026 Partial Inspection FREDDIE RIVERA
HVAC-Final 1/7/2026 Approved FREDDIE RIVERA
PLUMBING-Final 1/7/2026 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/20/2026 No Access for Inspection FREDDIE RIVERA
Final 2/20/2026 No Access for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 2/20/2026 No Access for Inspection FREDDIE RIVERA
Green Building Final 2/20/2026 Partial Inspection FREDDIE RIVERA
Green Building Rough 2/20/2026 No Access for Inspection FREDDIE RIVERA
Smoke Detectors 2/20/2026 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 3/2/2026 Approved FREDDIE RIVERA
ELECTRICAL-Final 3/2/2026 Approved FREDDIE RIVERA
Final 3/2/2026 Permit Finaled FREDDIE RIVERA
Footing/Foundation/Slab 3/2/2026 Approved FREDDIE RIVERA
Green Building Final 3/2/2026 Approved FREDDIE RIVERA
Green Building Rough 3/2/2026 Approved FREDDIE RIVERA
Smoke Detectors 3/2/2026 Approved FREDDIE RIVERA