2105 W OAK GLEN PL 90039
Certificate Information: 2105 W OAK GLEN PL 90039
- Application / Permit
- 17014-10000-06553
- Plan Check / Job No.
- B17LA23339
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- ALTEREATION TO THE EXISTING 2-STORY GARAGE WITH STORAGE ROOM BELOW BUILDING TO CONVERT THE STORAGE ROOM TO RECREATION ROOM AND CREATE A NEW STORAGE ROOM IN THE LOWER LEVEL. "COMPLY WITH DEPARTMENT ORDER effective date 07/21/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2017 | APPLICANT |
| Green Plans Picked Up | 12/27/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2018 | AUNG SOE |
| Corrections Issued | 1/8/2018 | AUNG SOE |
| Quality Review Completed | 1/12/2018 | LARRY LEE |
| Building Plans Picked Up | 1/24/2018 | APPLICANT |
| Applicant returned to address corrections | 5/8/2018 | AUNG SOE |
| Applicant returned to address corrections | 1/15/2019 | AUNG SOE |
| Applicant returned to address corrections | 7/22/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 7/29/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 8/5/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 8/6/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 8/19/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 8/30/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 9/17/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 12/3/2019 | JOSE RODRIGUEZ |
| Plan Check Approved | 3/5/2020 | ZAW HAN |
| Issued | 3/12/2020 | LADBS |
| CofO in Progress | 6/13/2022 | ALFREDO BALANDRA |
| Permit Finaled | 7/20/2022 | DANIEL SANCHEZ |
| CofO Issued | 7/20/2022 | DANIEL SANCHEZ |
| Permit Finaled | 7/20/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Hold | Cleared | 1/8/2018 | TERESA MUI |
| Address approval | Cleared | 10/15/2018 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 10/15/2018 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 10/15/2018 | KAYLA PEJI |
| BHO/Hillside ordinance | Cleared | 10/15/2018 | KAYLA PEJI |
| Sewer availability | Cleared | 10/15/2018 | KAYLA PEJI |
| ZI | Cleared | 10/15/2018 | STEVEN WECHSLER |
| Distance to fire station | Cleared | 10/30/2018 | JOHN DALLAS |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2018 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 10/30/2018 | JOHN DALLAS |
| GPI Written Notices | Cleared | 7/22/2019 | AUNG SOE |
| Grading Pre-Inspection | Cleared | 7/22/2019 | AUNG SOE |
| Roof/Waste drainage to street | Cleared | 8/6/2019 | JEANIE LAM |
Contact Information
| Contractor | S D R - B Inc; Lic. No.: 876317-B | 1108 SOUTH HARVARD BOULEVARD LOS ANGELES, CA 90006 |
| Engineer | Babayan, Raffi Samuel; Lic. No.: C72168 | 1140 N COLUMBUS AVE 112 GLENDALE, CA 91202 |
| Engineer | Zhang, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
| Geologist | Cugno, Giuseppe; Lic. No.: EG1804 | J. BYER GROUP, THE 1461 E CHEVY CHASE DR, #200 GLENDALE, CA 91206 |
Inspector Information
| RUBEN PEREZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT NILES, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK BEVELAQUA, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL SANCHEZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| COREY HUPP, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL OPFFER, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/18/2021 | Partial Approval | TIMOTHY MCCURDY |
| Piling/Pier/Caisson | 5/18/2021 | Partial Approval | TIMOTHY MCCURDY |
| Special/Order Compliance | 5/18/2021 | Approved | ROBERT MINASSIANS |
| Piling/Pier/Caisson | 5/19/2021 | Partial Approval | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 5/26/2021 | Approved | TIMOTHY MCCURDY |
| Excavation/Setback/Form/Re-Bar | 6/7/2021 | Partial Approval | TIMOTHY MCCURDY |
| Green Building Rough | 6/24/2021 | Approved | TIMOTHY MCCURDY |
| MERV13>=Rough | 6/24/2021 | Approved | TIMOTHY MCCURDY |
| Reinforced Concrete Frame | 6/24/2021 | Approved | TIMOTHY MCCURDY |
| BUILDING-Rough-Frame | 7/29/2021 | Approved | TIMOTHY MCCURDY |
| ELECTRICAL-Rough | 7/29/2021 | Corrections Issued | TIMOTHY MCCURDY |
| HVAC-Rough | 7/29/2021 | Corrections Issued | TIMOTHY MCCURDY |
| Insulation | 7/29/2021 | Approved | TIMOTHY MCCURDY |
| Drywall Nailing | 8/4/2021 | Approved | TIMOTHY MCCURDY |
| ELECTRICAL-Rough | 8/4/2021 | Approved | TIMOTHY MCCURDY |
| HVAC-Rough | 8/4/2021 | Approved | TIMOTHY MCCURDY |
| Insulation | 8/4/2021 | Approved | TIMOTHY MCCURDY |
| Final | 10/5/2021 | Partial Approval | TIMOTHY MCCURDY |
| Green Building Final | 10/5/2021 | Approved | TIMOTHY MCCURDY |
| MERV13>=Final | 10/5/2021 | Approved | TIMOTHY MCCURDY |
| SGSOV-Seismic Gas S/O Valve | 10/5/2021 | SGSOV Approved | TIMOTHY MCCURDY |
| Smoke Detectors | 10/5/2021 | Approved | TIMOTHY MCCURDY |
| Special/Order Compliance | 10/5/2021 | Partial Inspection | PIERRE VEGA |
| ELECTRICAL-Final | 6/7/2022 | Approved | ALFREDO BALANDRA |
| Final | 6/7/2022 | OK to Issue CofO | ALFREDO BALANDRA |
| HVAC-Final | 6/7/2022 | Approved | ALFREDO BALANDRA |
| PLUMBING-Final | 6/7/2022 | Approved | ALFREDO BALANDRA |