128-128 1/2 E 46TH ST 90011

Certificate Information: 128-128 1/2 E 46TH ST 90011

Application / Permit
17014-10000-06212
Plan Check / Job No.
B17LA22190
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ONE- STORY ADDITION TO (E) S.F.D. & CONVERT TO DUPLEX . **1 OF 2**
Permit Issued
Issued on 11/26/2018
Issuing Office
Metro
Current Status
CofO Issued on 10/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2017 APPLICANT
Green Plans Picked Up 12/19/2017 APPLICANT
Assigned to Plan Check Engineer 12/28/2017 GEORGE BANNING
Corrections Issued 1/3/2018 GEORGE BANNING
Quality Review Completed 1/22/2018 JOHN VASQUEZ
Plan Check Approved 10/22/2018 YAQUB MIRZA
Issued 11/26/2018 LADBS
CofO in Progress 9/8/2020 ROBERT MCDOWELL
Permit Finaled 10/21/2020 DEROLD HAUFF
CofO Issued 10/21/2020 DEROLD HAUFF
Permit Finaled 10/21/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/15/2018 CELINA MORENO
Green Code Cleared 6/15/2018 DONALD CRICHLOW
Eng Process Fee Ord 176,300 Cleared 8/20/2018 ADRIAN SANCHEZ
Sewer availability Cleared 8/20/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 8/29/2018 RYAN HUDSON
Project located in CRA area Cleared 8/29/2018 JIM URQUHART
Roof/Waste drainage to street Cleared 8/31/2018 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Park, Juntae; Lic. No.: C65104 1444 HI POINT ST      LOS ANGELES, CA 90035

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/16/2019 Not Ready for Inspection VICTOR PUKHALSKY
Footing/Foundation/Slab 4/26/2019 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/2/2019 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 5/8/2019 Corrections Issued VICTOR PUKHALSKY
Footing/Foundation/Slab 5/10/2019 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 5/14/2019 Approved VICTOR PUKHALSKY
Wood Frame 6/7/2019 Corrections Issued VICTOR PUKHALSKY
BUILDING-Rough-Frame 6/25/2019 Partial Approval FREDDIE RIVERA
Green Building Rough 6/25/2019 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 6/25/2019 Approved FREDDIE RIVERA
Deputy Wood Construction 7/16/2019 Partial Approval VICTOR PUKHALSKY
Deputy Wood Construction 7/24/2019 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 7/30/2019 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/30/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 7/30/2019 Corrections Issued JOAQUIN GREENOUGH
Wood Frame 7/30/2019 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/6/2019 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 8/6/2019 Corrections Issued JOAQUIN GREENOUGH
Service/Power Release 8/27/2019 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 9/19/2019 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/19/2019 Partial Approval JOAQUIN GREENOUGH
Green Building Rough 9/19/2019 Approved JOAQUIN GREENOUGH
Service/Power Release 10/4/2019 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 1/8/2020 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 1/23/2020 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 1/23/2020 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 2/13/2020 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/10/2020 Not Ready for Inspection JOSEPH MCGARRY
Drywall Nailing 7/10/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 7/10/2020 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 7/10/2020 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/10/2020 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 7/10/2020 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 7/23/2020 Approved ROBERT MCDOWELL
Drywall Nailing 7/23/2020 Approved ROBERT MCDOWELL
Final 7/23/2020 Corrections Issued ROBERT MCDOWELL
Green Building Final 7/23/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 7/23/2020 SGSOV Not Ready ROBERT MCDOWELL
Smoke Detectors 7/23/2020 Not Ready for Inspection ROBERT MCDOWELL
Service/Power Release 8/3/2020 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 8/7/2020 Not Ready for Inspection ROBERT MCDOWELL
Service/Power Release 8/7/2020 Approved ROBERT MCDOWELL
Final 9/8/2020 OK to Issue CofO ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 9/8/2020 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 9/8/2020 Approved ROBERT MCDOWELL