5883 W 77TH PL 90045
Certificate Information: 5883 W 77TH PL 90045
- Application / Permit
- 17014-10000-06086
- Plan Check / Job No.
- B17LA21802
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SECOND STORY ADDITION, GARAGE EXPANSION AND INTERIOR REMODEL TO AN EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 1/25/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2017 | SINA KHOSRAVI |
| Corrections Issued | 1/8/2018 | SINA KHOSRAVI |
| Quality Review Completed | 1/10/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 1/11/2018 | APPLICANT |
| Green Plans Picked Up | 1/11/2018 | APPLICANT |
| Plan Check Approved | 1/24/2018 | SINA KHOSRAVI |
| Issued | 1/25/2018 | LADBS |
| CofO in Progress | 8/27/2020 | JUAN VALENZUELA |
| CofO Issued | 9/8/2020 | VINCENT COTTON |
| Permit Finaled | 9/8/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/29/2017 | BARTON HOLMES |
| CPC | Cleared | 1/11/2018 | JESSE RAMOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2018 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 1/11/2018 | STEVE MELGAR |
| GPI Written Notices | Cleared | 1/24/2018 | RONALD ALLEN |
| Green Code | Cleared | 1/24/2018 | NEGAR NEJAD |
Contact Information
| Contractor | L A Design Group - W L A; Lic. No.: 989810-B | 8640 GULANA AVE J3007 PLAYA DEL REY, CA 90293 |
| Engineer | Loghmani, Mohsen; Lic. No.: C62741 | 8212 LAUREL CANYON BLVD NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/31/2018 | Partial Approval | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 2/5/2018 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2018 | Partial Approval | MICKEY YAMASHITA |
| Green Building Rough | 4/19/2018 | Approved | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2018 | Partial Approval | RONALD WEBER |
| Interior/Exterior Lathing | 6/7/2018 | Corrections Issued | MICKEY YAMASHITA |
| Interior/Exterior Lathing | 6/20/2018 | Partial Approval | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 11/2/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| HVAC-Rough | 11/2/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| PLUMBING-Rough | 11/2/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 11/2/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| Shower Pan | 11/2/2018 | Corrections Issued | TIM CHRISTENSEN |
| Wood Frame | 11/2/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 11/8/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| HVAC-Rough | 11/8/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| PLUMBING-Rough | 11/8/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 11/8/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| Wood Frame | 11/8/2018 | Not Ready for Inspection | TIM CHRISTENSEN |
| HVAC-Rough | 11/13/2018 | Approved | RONALD WEBER |
| PLUMBING-Rough | 11/13/2018 | Approved | RONALD WEBER |
| Shower Pan | 11/13/2018 | Not Ready for Inspection | RONALD WEBER |
| Insulation | 11/21/2018 | Approved | TIM CHRISTENSEN |
| Shower Pan | 11/21/2018 | Approved | TIM CHRISTENSEN |
| Drywall Nailing | 1/11/2019 | Not Ready for Inspection | TIM CHRISTENSEN |
| Drywall Nailing | 1/16/2019 | Approved | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 1/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 1/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 1/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Gas Test | 1/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Final | 1/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 1/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 1/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 1/23/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Service/Power Release | 1/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 1/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Gas Test | 2/6/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/28/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 2/28/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 2/28/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 2/28/2020 | Approved | JUAN VALENZUELA |
| HVAC-Final | 2/28/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 2/28/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 2/28/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 2/28/2020 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 3/13/2020 | Approved | JUAN VALENZUELA |
| Final | 3/13/2020 | Conditional Approval | JUAN VALENZUELA |
| HVAC-Final | 3/13/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 3/13/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 3/13/2020 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 3/13/2020 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 3/13/2020 | Approved | JUAN VALENZUELA |