113 N RIDGEWOOD PL 90004

Certificate Information: 113 N RIDGEWOOD PL 90004

Application / Permit
17014-10000-05815
Plan Check / Job No.
B17LA20864
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) GARAGE CONVERSION TO (N) ADU AB 2299 AND SB 1069
Permit Issued
Issued on 8/13/2018
Issuing Office
Valley
Current Status
Issued on 8/13/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/14/2017 APPLICANT
Assigned to Plan Check Engineer 12/7/2017 AUNG SOE
Corrections Issued 12/14/2017 AUNG SOE
Green Plans Picked Up 12/22/2017 APPLICANT
Quality Review Completed 12/27/2017 WING SUEN
Building Plans Picked Up 1/3/2018 APPLICANT
Applicant returned to address corrections 4/11/2018 AUNG SOE
Applicant returned to address corrections 7/9/2018 AUNG SOE
Plan Check Approved 7/18/2018 AUNG SOE
Issued 8/13/2018 LADBS

Permit Application Clearance Information

Green Code Cleared 3/30/2018 PARISA ZAHABI
Hydrant and Access approval Cleared 4/9/2018 GEORGE SUCHAND
Address approval Cleared 4/11/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 4/11/2018 MICHAEL CASTILLO
Low Impact Development Cleared 4/11/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 4/11/2018 STEVE MELGAR
Sewer availability Cleared 4/11/2018 MICHAEL CASTILLO

Contact Information

Engineer Melchor, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/12/2018 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 9/26/2018 Conditional Approval JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 11/8/2018 Corrections Issued JOSEPH MCGARRY
Sewer 11/8/2018 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 11/26/2018 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 11/26/2018 Corrections Issued JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 11/26/2018 Approved JOSEPH MCGARRY
Green Building Rough 11/26/2018 Approved JOSEPH MCGARRY
HVAC-Rough 11/26/2018 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 11/26/2018 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 12/5/2018 Approved DANNY TOLENTINO
HVAC-Rough 12/5/2018 Partial Inspection DANNY TOLENTINO
BUILDING-Rough-Frame 12/6/2018 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 12/6/2018 Approved JOSEPH MCGARRY
HVAC-Rough 12/6/2018 Approved JOSEPH MCGARRY
Insulation 12/28/2018 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 12/28/2018 Partial Approval JOSEPH MCGARRY
Drywall Nailing 1/10/2019 Approved JOSEPH MCGARRY
Gas Test 1/10/2019 Not Ready for Inspection JOSEPH MCGARRY
Underground Mechanical 1/10/2019 Partial Approval JOSEPH MCGARRY
Gas Test 3/27/2019 Corrections Issued LUIS BARRALES
Interior/Exterior Lathing 3/27/2019 Not Ready for Inspection LUIS BARRALES
Shower Pan 3/27/2019 Corrections Issued LUIS BARRALES
Gas Test 4/1/2019 Approved LUIS BARRALES
Interior/Exterior Lathing 4/1/2019 Partial Approval LUIS BARRALES
Shower Pan 4/1/2019 Approved LUIS BARRALES