1483 W 28TH ST 90007

Certificate Information: 1483 W 28TH ST 90007

Application / Permit
17014-10000-05197
Plan Check / Job No.
B17LA18650
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE (14' X 18') AND ADDITION OF 17'X18' TO ADU AS PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER WFPP
Permit Issued
Issued on 11/30/2020
Issuing Office
Current Status
CofO Issued on 12/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2017 APPLICANT
Assigned to Plan Check Engineer 10/23/2017 SAM CHANG
Corrections Issued 10/23/2017 SAM CHANG
Applicant returned to address corrections 6/5/2020 AUNG SOE
Applicant returned to address corrections 7/2/2020 LUKE GONZALES
Applicant returned to address corrections 7/23/2020 AMIR DANAI
Building Plans Picked Up 7/24/2020 APPLICANT
Plan Check Approved 11/16/2020 ADAM HEGAZI
Issued 11/30/2020 APPLICANT
CofO in Progress 10/15/2021 HORACE FULTZ
Permit Finaled 12/4/2021 DEROLD HAUFF
CofO Issued 12/4/2021 DEROLD HAUFF
Permit Finaled 12/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/20/2017 FATIMA GUERRA
Roof/Waste drainage to street Cleared 12/20/2017 FATIMA GUERRA
Eng Process Fee Ord 176,300 Cleared 7/17/2018 NAZILA NOORIFAR
Hydrant and Access approval Cleared 7/17/2018 GILBERT URREA
Sewer availability Cleared 7/17/2018 NAZILA NOORIFAR
HPOZ Cleared 7/24/2020 LYDIA CHAPMAN
ZI Cleared 7/24/2020 LYDIA CHAPMAN
ZI Cleared 8/20/2020 LAUREN PADICK

Contact Information

Contractor Residential Remodeling & Development Co; Lic. No.: 926862-B 10972 POPE AVE      LYNWOOD, CA 90262

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/18/2020 Approved KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 12/23/2020 No Access for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/23/2020 No Access for Inspection KATHRYN BUTTERWORTH
METHANE-Barrier 12/23/2020 No Access for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 12/23/2020 No Access for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 12/30/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 12/30/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 2/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Barrier 2/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 2/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 2/12/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/12/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 3/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 3/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 3/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Rough-Elec/Plmb/HVAC 3/11/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/16/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 3/16/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/31/2021 No Access for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/31/2021 No Access for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 No Access for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 3/31/2021 No Access for Inspection KATHRYN BUTTERWORTH
METHANE-Rough 3/31/2021 No Access for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 3/31/2021 No Access for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/9/2021 Partial Approval KATHRYN BUTTERWORTH
HVAC-Rough 4/9/2021 Approved KATHRYN BUTTERWORTH
Insulation 4/19/2021 Not Ready for Inspection RUBEN SALAS
Wood Frame 4/19/2021 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 4/21/2021 Approved STUART CHAPMAN
METHANE-Rough 4/21/2021 Approved STUART CHAPMAN
Drywall Nailing 5/4/2021 Approved KATHRYN BUTTERWORTH
Underground Mechanical 5/5/2021 Corrections Issued KATHRYN BUTTERWORTH
Underground Mechanical 6/1/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Sewer 6/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Shower Pan 6/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 6/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/22/2021 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 6/22/2021 Approved KATHRYN BUTTERWORTH
Underground Mechanical 6/22/2021 Approved KATHRYN BUTTERWORTH
Final 8/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 8/5/2021 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 8/5/2021 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 8/5/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/5/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 8/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 8/17/2021 Corrections Issued KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/17/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 8/17/2021 Approved KATHRYN BUTTERWORTH
Final 9/2/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Approved KATHRYN BUTTERWORTH
Final 9/21/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 10/8/2021 Partial Approval HORACE FULTZ
Final 10/15/2021 OK to Issue CofO HORACE FULTZ
Service/Power Release 10/15/2021 Approved HORACE FULTZ
Rough-Elec/Plmb/HVAC 10/20/2021 Not Ready for Inspection FREDDIE RIVERA