2300 N APOLLO DR 90046

Certificate Information: 2300 N APOLLO DR 90046

Application / Permit
17014-10000-05067
Plan Check / Job No.
B17LA18172
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ALTERATION AND SECOND FLOOR ADDITION TO EXISTING 2 STORY SINGLE FAMILY RESIDENCE
Permit Issued
Issued on 8/17/2018
Issuing Office
Metro
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2017 APPLICANT
Assigned to Plan Check Engineer 10/12/2017 PAUL PIERRE
Corrections Issued 10/17/2017 PAUL PIERRE
Green Plans Picked Up 10/18/2017 APPLICANT
Quality Review Completed 10/26/2017 ARMEN JIVALAGIAN
Building Plans Picked Up 10/31/2017 APPLICANT
Plan Check Approved 2/13/2018 PAUL PIERRE
Issued 8/17/2018 LADBS
CofO in Progress 1/27/2023 STUART CHAPMAN
Permit Finaled 2/15/2023 DEROLD HAUFF
CofO Issued 2/15/2023 DEROLD HAUFF
Permit Finaled 2/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/31/2018 PATRICK MISCHLICH
BHO/Hillside ordinance Cleared 2/1/2018 CARLA VALLADARES
BHO/Hillside ordinance Cleared 2/1/2018 CARLA VALLADARES
BHO/Hillside ordinance Cleared 2/1/2018 CARLA VALLADARES
Distance to fire station Cleared 2/1/2018 ROBERT DUFF
Hydrant and Access approval Cleared 2/1/2018 ROBERT DUFF
Sewer availability Cleared 2/1/2018 CARLA VALLADARES
Eng Process Fee Ord 176,300 Cleared 2/13/2018 KAREN LE
Green Code Cleared 2/13/2018 RICHARD DOCKUS
Low Impact Development Cleared 2/13/2018 SAM NAVID
Roof/Waste drainage to street Cleared 2/13/2018 KAREN LE

Contact Information

Contractor Owner-Builder       ,
Engineer Choi, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/29/2019 No Access for Inspection RAUL BARAJAS
Pre-Inspection 4/9/2019 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 5/21/2019 Conditional Approval RAUL BARAJAS
Pre-Inspection 5/21/2019 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/3/2019 Approved RAUL BARAJAS
Footing/Foundation/Slab 6/3/2019 Approved RAUL BARAJAS
BUILDING-Rough-Frame 6/20/2019 Partial Approval RAUL BARAJAS
Green Building Rough 6/20/2019 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 6/20/2019 Partial Approval RAUL BARAJAS
Verify Sprinkler Sign Off 6/20/2019 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/2/2019 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/22/2019 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/25/2019 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/15/2019 Conditional Approval RAUL BARAJAS
Special/Order Compliance 12/19/2019 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Partial Approval RAUL BARAJAS
Special/Order Compliance 4/28/2020 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 6/16/2020 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 9/21/2020 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 10/1/2020 Not Ready for Inspection RAUL BARAJAS
Insulation 11/23/2020 Approved RAUL BARAJAS
BUILDING-Rough-Frame 12/3/2020 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 12/3/2020 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 12/3/2020 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 12/3/2020 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 12/4/2020 Approved RAUL BARAJAS
Interior/Exterior Lathing 12/4/2020 Partial Approval RAUL BARAJAS
Rough-Elec/Plmb/HVAC 12/4/2020 Approved RAUL BARAJAS
Insulation 12/10/2020 Corrections Issued RAUL BARAJAS
Drywall Nailing 1/11/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 1/11/2021 Approved RAUL BARAJAS
Shower Pan 1/11/2021 Approved RAUL BARAJAS
Gas Test 1/14/2021 Approved RAUL BARAJAS
Insulation 1/14/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 1/14/2021 Approved RAUL BARAJAS
PLUMBING-Rough 1/14/2021 Conditional Approval RAUL BARAJAS
HVAC-Final 10/19/2021 Conditional Approval RAUL BARAJAS
HVAC-Final 10/28/2021 Approved RAUL BARAJAS
PLUMBING-Final 10/28/2021 Not Ready for Inspection RAUL BARAJAS
Sewer 10/28/2021 Corrections Issued RAUL BARAJAS
PLUMBING-Final 11/8/2021 Approved RAUL BARAJAS
Sewer 11/8/2021 Approved RAUL BARAJAS
ELECTRICAL-Final 1/5/2022 Approved RAUL BARAJAS
Footing/Foundation/Slab 1/7/2022 Approved BRIAN SULLIVAN
Grading Pre-Inspection 3/29/2022 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 12/16/2022 Approved STUART CHAPMAN
Final 12/16/2022 OK for TCO STUART CHAPMAN
Green Building Final 12/16/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 12/16/2022 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 12/16/2022 Approved STUART CHAPMAN
Final 1/12/2023 Corrections Issued DONALD CRICHLOW
Deck 1/24/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 1/24/2023 Approved STUART CHAPMAN
ELECTRICAL-Rough 1/24/2023 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 1/24/2023 Approved STUART CHAPMAN
Final 1/24/2023 Not Ready for Inspection STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Approved STUART CHAPMAN
Gas Test 1/24/2023 Approved STUART CHAPMAN
Grading Pre-Inspection 1/24/2023 Approved STUART CHAPMAN
Grounding or Bonding 1/24/2023 Approved STUART CHAPMAN
HVAC-Final 1/24/2023 Approved STUART CHAPMAN
HVAC-Rough 1/24/2023 Approved STUART CHAPMAN
Insulation 1/24/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 1/24/2023 Approved STUART CHAPMAN
Light Gage Steel Frame 1/24/2023 Approved STUART CHAPMAN
Masonry Wall/Backfill 1/24/2023 Approved STUART CHAPMAN
PLUMBING-Final 1/24/2023 Approved STUART CHAPMAN
PLUMBING-Rough 1/24/2023 Approved STUART CHAPMAN
Piling/Pier/Caisson 1/24/2023 Approved STUART CHAPMAN
Pool Piping 1/24/2023 Approved STUART CHAPMAN
Posting Pre-Inspection 1/24/2023 Approved STUART CHAPMAN
Pre-Inspection 1/24/2023 Approved STUART CHAPMAN
Reinforced Concrete Frame 1/24/2023 Approved STUART CHAPMAN
Reinforced Masonry Frame 1/24/2023 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 1/24/2023 Approved STUART CHAPMAN
Service/Power Release 1/24/2023 Not Required STUART CHAPMAN
Sewer 1/24/2023 Approved STUART CHAPMAN
Shower Pan 1/24/2023 Approved STUART CHAPMAN
Special/Order Compliance 1/24/2023 Approved STUART CHAPMAN
Structural Steel Frame 1/24/2023 Approved STUART CHAPMAN
Underground Mechanical 1/24/2023 Approved STUART CHAPMAN
Verify Rec and Parks Fee Memo 1/24/2023 Approved STUART CHAPMAN
Wood Frame 1/24/2023 Approved STUART CHAPMAN
Final 1/27/2023 OK to Issue CofO STUART CHAPMAN