1919 1/2 N VAN NESS AVE 90068

Certificate Information: 1919 1/2 N VAN NESS AVE 90068

Application / Permit
17014-10000-05043
Plan Check / Job No.
B17LA18081
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
15'x29' ground floor addition to existing accessory building and change use to accessory dwelling unit per AB 2299 and SB 1069. See comments.
Permit Issued
Issued on 10/28/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2017 APPLICANT
Assigned to Plan Check Engineer 10/19/2017 TU HUA
Corrections Issued 10/26/2017 TU HUA
Quality Review Completed 10/27/2017 ALLEN MANALANSAN
Building Plans Picked Up 10/31/2017 APPLICANT
Applicant returned to address corrections 2/27/2018 TU HUA
Green Plans Picked Up 2/27/2018 APPLICANT
Plan Check Approved 3/27/2019 TU HUA
Issued 10/28/2019 LADBS
CofO in Progress 11/3/2021 JOSEPH MCGARRY
Permit Finaled 11/10/2021 DEROLD HAUFF
CofO Issued 11/10/2021 DEROLD HAUFF
Permit Finaled 11/10/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/27/2018 NAZILA NOORIFAR
Address approval Cleared 2/27/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 2/27/2018 NAZILA NOORIFAR
Sewer availability Cleared 2/27/2018 NAZILA NOORIFAR
Grading Pre-Inspection Cleared 3/26/2019 BARTON HOLMES
HPOZ Cleared 3/26/2019 AMANDA KAINER
Miscellaneous Cleared 3/26/2019 AMANDA KAINER
Green Code Cleared 3/27/2019 NEGAR NEJAD
Roof/Waste drainage to street Cleared 3/27/2019 ERIK BEASLEY

Contact Information

Contractor Salgado Design & Construction Inc; Lic. No.: 1011670-B 4230 CENTER STREET      BALDWIN PARK, CA 91706
Engineer , ; Lic. No.: C85450 12881 BROWNING AVE      SANTA ANA, CA 92705

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/3/2019 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 12/11/2019 Partial Approval ROBERT CORNELL
Underground Mechanical 12/11/2019 Approved ROBERT CORNELL
Footing/Foundation/Slab 1/3/2020 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 1/8/2020 Not Ready for Inspection ROBERT CORNELL
Footing/Foundation/Slab 2/18/2020 Approved ROBERT CORNELL
BUILDING-Rough-Frame 7/13/2020 Partial Approval BRIAN SULLIVAN
Green Building Rough 7/13/2020 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 8/18/2020 Approved BRIAN SULLIVAN
HVAC-Rough 9/3/2020 Approved BRIAN SULLIVAN
PLUMBING-Rough 9/3/2020 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 9/18/2020 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 9/18/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 9/18/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 10/6/2020 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 10/13/2020 Approved BRIAN SULLIVAN
Gas Test 10/13/2020 Approved BRIAN SULLIVAN
Green Building Final 10/13/2020 Not Ready for Inspection BRIAN SULLIVAN
Insulation 10/16/2020 Approved BRIAN SULLIVAN
Drywall Nailing 11/2/2020 Approved HAMIK HARTOUNIAN
Shower Pan 11/2/2020 Approved HAMIK HARTOUNIAN
Shower Pan 11/9/2020 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 11/23/2020 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 5/11/2021 Approved JOSEPH MCGARRY
Service/Power Release 6/22/2021 Corrections Issued BRIAN SULLIVAN
Final 10/29/2021 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 10/29/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 10/29/2021 Approved JOSEPH MCGARRY