671 N SALTAIR AVE 90049
Certificate Information: 671 N SALTAIR AVE 90049
- Application / Permit
- 17014-10000-04803
- Plan Check / Job No.
- B17LA17254
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL OF (E) SFD WITH (N) 3260 SF ADDITION; ONLY (E) RETAINING WALL PER PLOT PLAN TO REMAIN
- Permit Issued
- Issued on 8/20/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 9/22/2017 | APPLICANT |
Assigned to Plan Check Engineer | 10/12/2017 | TEODORO DIAZ RODRIGUEZ |
Corrections Issued | 10/20/2017 | WEIWEI BREAKWELL |
Green Plans Picked Up | 10/30/2017 | APPLICANT |
Quality Review Completed | 11/2/2017 | KESETE HAREGOT |
Building Plans Picked Up | 11/3/2017 | APPLICANT |
Applicant returned to address corrections | 1/17/2018 | WEIWEI BREAKWELL |
Applicant returned to address corrections | 1/23/2018 | WEIWEI BREAKWELL |
Applicant returned to address corrections | 2/9/2018 | WEIWEI BREAKWELL |
Applicant returned to address corrections | 6/26/2018 | WEIWEI BREAKWELL |
Plan Check Approved | 3/14/2019 | TEODORO DIAZ RODRIGUEZ |
Issued | 8/20/2019 | LADBS |
CofO in Progress | 8/5/2022 | CARLOS MATAMOROS |
Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
CofO Issued | 8/30/2022 | DANIEL ORRANTE |
Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
Address approval | Cleared | 1/12/2018 | STEVE MELGAR |
Eng Process Fee Ord 176,300 | Cleared | 1/12/2018 | STEVE MELGAR |
Hydrant and Access approval | Cleared | 1/12/2018 | JOHN CONNEALLY |
Permit | Cleared | 1/12/2018 | STEVE MELGAR |
BHO/Hillside ordinance | Cleared | 1/19/2018 | HISASHI KOBAYAKAWA |
BHO/Hillside ordinance | Cleared | 1/19/2018 | HISASHI KOBAYAKAWA |
BHO/Hillside ordinance | Cleared | 1/19/2018 | HISASHI KOBAYAKAWA |
Green Code | Cleared | 1/22/2018 | JOHN KLARIN |
GPI Written Notices | Cleared | 1/23/2018 | WEIWEI BREAKWELL |
Grading Pre-Inspection | Cleared | 1/23/2018 | WEIWEI BREAKWELL |
Excavation more than 5-ft deep | Cleared | 2/9/2018 | CALOSHA APPROVED |
Low Impact Development | Cleared | 3/13/2019 | RYAN HUDSON |
Roof/Waste drainage to street | Cleared | 3/13/2019 | ADRIAN SANCHEZ |
Work Adjacent to Public Way | Cleared | 3/13/2019 | BOK GOH |
Contact Information
Contractor | Intension Construction; Lic. No.: 956850-B | 1951 MALCOLM AVE #108 LOS ANGELES, CA 90023 |
Engineer | Garcia, Lionel Jesus; Lic. No.: S4653 | 23890 HAWTHORNE BLVD TORRANCE, CA 90505 |
Engineer | Lombera, Raymundo A; Lic. No.: L7740 | 5015 EAGLE ROCK BLVD 210 LOS ANGELES, CA 90041 |
Engineer | Rybak, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
Geologist | Haenschke, Eirik Francis; Lic. No.: EG1597 | 9001 MONOGRAM AVENUE NORTH HILLS, CA 91343 |
Inspector Information
CARLOS MATAMOROS, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Piling/Pier/Caisson | 12/19/2019 | Partial Approval | ANTHONY MCDOWALL |
Piling/Pier/Caisson | 1/2/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
Footing/Foundation/Slab | 1/8/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
Piling/Pier/Caisson | 1/8/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
Deputy Reinf. Concrete | 1/9/2020 | Conditional Approval | CARLOS MATAMOROS |
Reinforced Concrete Frame | 1/17/2020 | Partial Approval | MICHAEL TEMPLE |
Deputy Shotcrete | 1/24/2020 | Conditional Approval | CARLOS MATAMOROS |
Piling/Pier/Caisson | 2/28/2020 | Partial Approval | CARLOS MATAMOROS |
Piling/Pier/Caisson | 3/9/2020 | Partial Approval | CARLOS MATAMOROS |
Excavation/Setback/Form/Re-Bar | 4/14/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
Excavation/Setback/Form/Re-Bar | 4/15/2020 | Corrections Issued | CARLOS MATAMOROS |
Excavation/Setback/Form/Re-Bar | 4/16/2020 | Partial Approval | CARLOS MATAMOROS |
PLUMBING-Rough | 4/27/2020 | Partial Approval | CARLOS MATAMOROS |
Underground Mechanical | 4/27/2020 | Approved | CARLOS MATAMOROS |
Footing/Foundation/Slab | 4/28/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
Underground Mechanical | 4/28/2020 | Approved | CARLOS MATAMOROS |
Deputy Reinf. Concrete | 4/29/2020 | Conditional Approval | CARLOS MATAMOROS |
Footing/Foundation/Slab | 5/1/2020 | Partial Approval | CARLOS MATAMOROS |
Wood Frame | 5/29/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
Excavation/Setback/Form/Re-Bar | 7/9/2020 | Partial Approval | CARLOS MATAMOROS |
Floor/Roof Diaphrgm/Shear Wall | 7/9/2020 | Approved | CARLOS MATAMOROS |
Wood Frame | 8/4/2020 | Partial Approval | CARLOS MATAMOROS |
Floor/Roof Diaphrgm/Shear Wall | 9/11/2020 | Approved | CARLOS MATAMOROS |
ELECTRICAL-Rough | 11/9/2020 | Corrections Issued | CARLOS MATAMOROS |
Gas Test | 11/9/2020 | Approved | CARLOS MATAMOROS |
PLUMBING-Rough | 11/9/2020 | Corrections Issued | CARLOS MATAMOROS |
Deputy Wood Construction | 11/13/2020 | Conditional Approval | CARLOS MATAMOROS |
ELECTRICAL-Rough | 11/19/2020 | Approved | CARLOS MATAMOROS |
Floor/Roof Diaphrgm/Shear Wall | 11/19/2020 | Partial Approval | CARLOS MATAMOROS |
HVAC-Rough | 11/19/2020 | Partial Approval | CARLOS MATAMOROS |
PLUMBING-Rough | 11/19/2020 | Approved | CARLOS MATAMOROS |
BUILDING-Rough-Frame | 11/20/2020 | Conditional Approval | CARLOS MATAMOROS |
Green Building Rough | 11/20/2020 | Approved | CARLOS MATAMOROS |
Structural Steel Frame | 11/20/2020 | Conditional Approval | CARLOS MATAMOROS |
BUILDING-Rough-Frame | 12/4/2020 | Approved | CARLOS MATAMOROS |
Green Building Rough | 12/4/2020 | Approved | CARLOS MATAMOROS |
HVAC-Rough | 12/4/2020 | Approved | CARLOS MATAMOROS |
Verify Sprinkler Sign Off | 12/4/2020 | Approved | CARLOS MATAMOROS |
Insulation | 12/8/2020 | Approved | CARLOS MATAMOROS |
Shower Pan | 12/8/2020 | Partial Approval | CARLOS MATAMOROS |
Interior/Exterior Lathing | 12/17/2020 | Partial Approval | CARLOS MATAMOROS |
Shower Pan | 12/17/2020 | Approved | CARLOS MATAMOROS |
Interior/Exterior Lathing | 12/23/2020 | Approved | CARLOS MATAMOROS |
Drywall Nailing | 1/15/2021 | Partial Approval | CARLOS MATAMOROS |
Drywall Nailing | 1/21/2021 | Approved | CARLOS MATAMOROS |
Interior/Exterior Lathing | 2/9/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
Interior/Exterior Lathing | 2/22/2021 | Approved | CARLOS MATAMOROS |
Deck | 2/23/2021 | Approved | CARLOS MATAMOROS |
Sewer | 7/15/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
PLUMBING-Rough | 7/19/2021 | Approved | CARLOS MATAMOROS |
Sewer | 7/19/2021 | Approved | CARLOS MATAMOROS |
ELECTRICAL-Rough | 7/26/2021 | Partial Approval | CHRISTOPHER WILSON |
Pre-Inspection | 9/9/2021 | Approved | CARLOS MATAMOROS |
Service/Power Release | 2/7/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
Pre-Inspection | 2/10/2022 | Approved | CARLOS MATAMOROS |
Gas Test | 2/22/2022 | Partial Approval | CARLOS MATAMOROS |
ELECTRICAL-Final | 2/25/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
ELECTRICAL-Final | 3/3/2022 | Partial Approval | CARLOS MATAMOROS |
ELECTRICAL-Final | 3/11/2022 | Approved | CARLOS MATAMOROS |
Service/Power Release | 3/11/2022 | Approved | CARLOS MATAMOROS |
PLUMBING-Final | 3/16/2022 | Corrections Issued | CARLOS MATAMOROS |
Underground Mechanical | 3/16/2022 | Approved | CARLOS MATAMOROS |
HVAC-Final | 3/31/2022 | Approved | CARLOS MATAMOROS |
PLUMBING-Final | 3/31/2022 | Approved | CARLOS MATAMOROS |
Light Gage Steel Frame | 5/9/2022 | Approved | CARLOS MATAMOROS |
Wood Frame | 5/9/2022 | Approved | CARLOS MATAMOROS |
Final | 6/28/2022 | Corrections Issued | CARLOS MATAMOROS |
Footing/Foundation/Slab | 6/28/2022 | Approved | CARLOS MATAMOROS |
Green Building Final | 6/28/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
Reinforced Concrete Frame | 6/28/2022 | Approved | CARLOS MATAMOROS |
SGSOV-Seismic Gas S/O Valve | 6/28/2022 | SGSOV Not Ready | CARLOS MATAMOROS |
Smoke Detectors | 6/28/2022 | Approved | CARLOS MATAMOROS |
Final | 7/18/2022 | Corrections Issued | CARLOS MATAMOROS |
Green Building Final | 7/18/2022 | Approved | CARLOS MATAMOROS |
SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | CARLOS MATAMOROS |
Final | 8/4/2022 | OK to Issue CofO | CARLOS MATAMOROS |