4508 W FOUNTAIN AVE 90029

Certificate Information: 4508 W FOUNTAIN AVE 90029

Application / Permit
17014-10000-04701
Plan Check / Job No.
B17LA16848
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY, 16'X16', R3-OCC ACCESSORY DWELLING UNIT ADDITION PER AB 2299 & SB 1069 TO EXISTING 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 4/19/2018
Issuing Office
Metro
Current Status
CofO Issued on 6/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2017 APPLICANT
Assigned to Plan Check Engineer 10/5/2017 DEVIN GORDON
Corrections Issued 10/16/2017 DEVIN GORDON
Quality Review Completed 10/24/2017 ARMEN JIVALAGIAN
Green Plans Picked Up 10/24/2017 APPLICANT
Building Plans Picked Up 11/2/2017 APPLICANT
Applicant returned to address corrections 4/16/2018 DEVIN GORDON
Plan Check Approved 4/19/2018 DEVIN GORDON
Issued 4/19/2018 LADBS
Refund in Progress-Status Void 6/5/2018 CANDICE JUSAY
Re-Activate Permit 7/3/2018 CANDICE JUSAY
Refund Completed-Status Void 8/10/2018 CHRISTINA TABIRARA
Re-Activate Permit 8/30/2018 CHRISTINA TABIRARA
CofO in Progress 3/16/2022 RUBEN SALAS
Permit Finaled 6/18/2022 DEROLD HAUFF
CofO Issued 6/18/2022 DEROLD HAUFF
Permit Finaled 6/18/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 3/16/2018 NEGAR NEJAD
Address approval Cleared 3/21/2018 KAREN LE
Encroachment in public way Cleared 3/21/2018 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 3/21/2018 KAREN LE
Hydrant and Access approval Cleared 3/21/2018 ROBERT DUFF
Low Impact Development Cleared 3/21/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 3/21/2018 JAMES KHO
Sewer availability Cleared 3/21/2018 KAREN LE
"D" conditions Cleared 4/10/2018 BRIAN CARR
Specific Plan Cleared 4/10/2018 RICHARD REASER
ZA Case Cleared 4/10/2018 BRIAN CARR
ZA Case Cleared 4/10/2018 SOPHIE GABEL-SCHEINBAU
ZI Cleared 4/10/2018 SOPHIE GABEL-SCHEINBAU
Work Adjacent to Public Way Cleared 4/11/2018 HOK CHI CHIU
ZA Case Cleared 4/11/2018 BRIAN CARR
ZA Case Cleared 4/11/2018 BRIAN CARR
Highway dedication Cleared 4/16/2018 KAREN LE
Excavation more than 5-ft deep Cleared 4/19/2018 CALOSHA APPROVED
GPI Written Notices Cleared 4/19/2018 DEVIN GORDON
Grading Pre-Inspection Cleared 4/19/2018 DEVIN GORDON

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez, Luis Fernando; Lic. No.: C56232 1551 RANDALL ST      GLENDALE, CA 91201

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/9/2018 Approved ROBERT MCDOWELL
Underground Mechanical 5/9/2018 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 5/18/2018 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 5/22/2018 Approved ROBERT MCDOWELL
Green Building Rough 5/22/2018 Not Ready for Inspection ROBERT MCDOWELL
Deputy Steel/Welding 6/5/2018 Conditional Approval ROBERT MCDOWELL
Pre-Inspection 7/5/2018 Partial Inspection RONALD MYRICK
BUILDING-Rough-Frame 7/23/2018 Corrections Issued ROBERT MCDOWELL
Green Building Rough 7/23/2018 Not Ready for Inspection ROBERT MCDOWELL
ELECTRICAL-Rough 9/19/2018 Corrections Issued ANDEY CHAPARRO
PLUMBING-Rough 12/3/2018 Corrections Issued ANDEY CHAPARRO
BUILDING-Rough-Frame 1/8/2019 Approved ANDEY CHAPARRO
Green Building Rough 1/8/2019 Approved ANDEY CHAPARRO
PLUMBING-Rough 1/8/2019 Approved ANDEY CHAPARRO
PLUMBING-Rough 1/8/2019 Partial Approval ANDEY CHAPARRO
PLUMBING-Rough 2/27/2019 Corrections Issued ANDEY CHAPARRO
BUILDING-Rough-Frame 8/6/2019 Not Ready for Inspection ROBERT VORHIS
Drywall Nailing 8/6/2019 Not Ready for Inspection ROBERT VORHIS
Final 8/6/2019 Corrections Issued ROBERT VORHIS
Green Building Final 8/6/2019 Not Ready for Inspection ROBERT VORHIS
Green Building Rough 8/6/2019 Not Ready for Inspection ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 8/6/2019 SGSOV Not Ready ROBERT VORHIS
Smoke Detectors 8/6/2019 Not Ready for Inspection ROBERT VORHIS
BUILDING-Rough-Frame 8/12/2019 Partial Inspection ROBERT VORHIS
Drywall Nailing 8/12/2019 Approved ROBERT VORHIS
Green Building Final 8/12/2019 Partial Inspection ROBERT VORHIS
Green Building Rough 8/12/2019 Approved ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 8/12/2019 SGSOV Not Ready ROBERT VORHIS
Smoke Detectors 8/12/2019 Approved ROBERT VORHIS
ELECTRICAL-Rough 8/21/2019 Corrections Issued ROBERT VORHIS
PLUMBING-Final 9/12/2019 Not Ready for Inspection ROBERT VORHIS
Special/Order Compliance 9/12/2019 Approved ELMER BLAND
Special/Order Compliance 9/12/2019 Corrections Issued ROBERT VORHIS
Special/Order Compliance 1/8/2020 Partial Inspection ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 1/22/2020 SGSOV Not Ready ELMER BLAND
Special/Order Compliance 2/19/2020 Corrections Issued BRAD BESCOS
Special/Order Compliance 2/19/2020 Corrections Issued ELMER BLAND
Special/Order Compliance 3/25/2020 Order to Comply Issued ROBERT VORHIS
BUILDING-Rough-Frame 5/14/2020 Not Ready for Inspection CRAIG VAUGHAN
Final 5/14/2020 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 5/14/2020 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/14/2020 SGSOV Not Ready CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/19/2020 SGSOV Not Ready RUBEN SALAS
Special/Order Compliance 8/25/2020 Partial Inspection RUBEN SALAS
Gas Test 9/4/2020 Approved RUBEN SALAS
PLUMBING-Rough 9/4/2020 Approved RUBEN SALAS
BUILDING-Rough-Frame 1/19/2021 Partial Inspection RUBEN SALAS
Final 1/19/2021 Partial Inspection RUBEN SALAS
Green Building Final 1/19/2021 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 1/19/2021 SGSOV Approved RUBEN SALAS
BUILDING-Rough-Frame 12/6/2021 Corrections Issued RUBEN SALAS
Final 12/6/2021 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 3/16/2022 Approved RUBEN SALAS
Final 3/16/2022 OK to Issue CofO RUBEN SALAS
Special/Order Compliance 6/7/2022 Corrections Issued RUBEN SALAS