26322 S GOVERNOR AVE 90710

Certificate Information: 26322 S GOVERNOR AVE 90710

Application / Permit
17014-10000-04664
Plan Check / Job No.
B17LA16745
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE-STORY, GROUND FLOOR ADDITION TO (E) ONE STORY SFD TO CREATE BEDROOM, BATH, AND CLOSET
Permit Issued
Issued on 11/16/2017
Issuing Office
Metro
Current Status
CofO Issued on 2/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2017 APPLICANT
Assigned to Plan Check Engineer 9/15/2017 LAMAR DAVIS
Corrections Issued 9/15/2017 LAMAR DAVIS
Plan Check Approved 11/15/2017 CAROLYNN NEPOMUCENO
Issued 11/16/2017 LADBS
CofO in Progress 1/30/2021 JOHN KLARIN
Permit Finaled 2/27/2021 DEROLD HAUFF
CofO Issued 2/27/2021 DEROLD HAUFF
Permit Finaled 2/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/15/2017 STEVE MELGAR
Grading Pre-Inspection Cleared 11/15/2017 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 11/15/2017 STEVE MELGAR

Contact Information

Contractor Pirelli A W; Lic. No.: 463755-B 1142 DIAMOND BAR BLVD #413      DIAMOND BAR, CA 91765
Engineer Moreno, Hector M; Lic. No.: C66015 236 W. ORANGE SHOW ROAD STE 105      SAN BERNARDINO, CA 92408

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/6/2017 Not Ready for Inspection ANSON MAGLASANG
Footing/Foundation/Slab 1/4/2018 Approved MARK HATFIELD
BUILDING-Rough-Frame 1/19/2018 Partial Approval ANSON MAGLASANG
Green Building Rough 1/19/2018 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 1/19/2018 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 1/24/2018 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 5/2/2018 Approved ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 10/7/2019 Approved JOHN KLARIN
ELECTRICAL-Rough 11/8/2019 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 11/8/2019 Corrections Issued JOHN KLARIN
PLUMBING-Rough 11/8/2019 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 12/31/2020 Approved JOHN KLARIN
Drywall Nailing 12/31/2020 Approved JOHN KLARIN
Final 12/31/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 12/31/2020 Not Ready for Inspection JOHN KLARIN
Green Building Rough 12/31/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/31/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 12/31/2020 Approved JOHN KLARIN
Final 1/28/2021 OK to Issue CofO JOHN KLARIN
Green Building Final 1/28/2021 Approved JOHN KLARIN