10880 W WILSHIRE BLVD 90024

Certificate Information: 10880 W WILSHIRE BLVD 90024

Application / Permit
17014-10000-04521
Plan Check / Job No.
B17LA16236
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
RENOVATION OF LOBBY IN (E) HIGH RISE TOWER W/8150 SF NEW FLOOR INFILL, AND OFFSET W/8150 SF (E) COMMERCIAL SPACE REASSIGNED AS STORAGE AT BASEMENT LEVEL; EXTERIOR IMPROVEMENT INCLUDE (N) FRAMELESS GLAZING, (N) OPERABLE GLASS WALLS
Permit Issued
Issued on 2/9/2018
Issuing Office
Metro
Current Status
Issued on 2/9/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/8/2017 APPLICANT
Assigned to Plan Check Engineer 9/14/2017 LARRY LEE
Corrections Issued 9/26/2017 LARRY LEE
Green Plans Picked Up 9/26/2017 APPLICANT
Disabled Access Plans Picked Up 10/2/2017 APPLICANT
Quality Review Completed 10/5/2017 SIAVOSH POURSABAHIAN
Building Plans Picked Up 10/5/2017 APPLICANT
Applicant returned to address corrections 11/8/2017 LARRY LEE
Applicant returned to address corrections 12/7/2017 LARRY LEE
Plan Check Approved 12/19/2017 LARRY LEE
Issued 2/9/2018 LADBS

Permit Application Clearance Information

"Q" conditions Cleared 10/12/2017 DANALYNN DOMINGUEZ
Eng Process Fee Ord 176,300 Cleared 10/12/2017 ALFREDO JARA
Hydrant and Access approval Cleared 10/12/2017 JOHN CONNEALLY
Low Impact Development Cleared 10/12/2017 ORVAL HERNANDEZ-MARCI
Miscellaneous Cleared 10/12/2017 DANALYNN DOMINGUEZ
Sewer availability Cleared 10/12/2017 ALFREDO JARA
ZA Case Cleared 10/12/2017 DANALYNN DOMINGUEZ
ZA Case Cleared 10/12/2017 DANALYNN DOMINGUEZ
ZA Case Cleared 10/12/2017 DANALYNN DOMINGUEZ
Highway dedication Cleared 10/13/2017 OSCAR GUTIERREZ
Specific Plan Cleared 12/8/2017 CLIVE GRAWE
Metro Rail approval Cleared 12/13/2017 LARRY LEE
Metro Rail approval Cleared 12/13/2017 LARRY LEE
Fire Marshall Fire Life Safety Cleared 12/18/2017 DOMINIQUE MEDINA
Green Code Cleared 12/18/2017 WILLIAM ROSE
DAS Clearance Cleared 12/19/2017 LARRY LEE

Contact Information

Architect Herst, Hans Robert; Lic. No.: C12001 4628 NOB HILL DRIVE      LOS ANGELES, CA 90065
Architect Woollett, Architecture; Lic. No.: BUS92 58 PLAZA SQUARE SUITE A      ORANGE, CA 92866
Contractor Swinerton Builders; Lic. No.: 92-B 260 TOWNSEND STREET   5TH FLOOR    SAN FRANCISCO, CA 94107
Engineer Islam, Mohammed Saiful; Lic. No.: S4083 155 N LAKE AVE SUITE 600      PASADENA, CA 91101

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2018 Approved SORIN CIRSTOIU
Pre-Inspection 8/2/2018 Approved SORIN CIRSTOIU
Pre-Inspection 10/9/2018 Approved SORIN CIRSTOIU
Pre-Inspection 10/24/2018 Partial Approval SORIN CIRSTOIU
Pre-Inspection 11/8/2018 Not Ready for Inspection SORIN CIRSTOIU
Pre-Inspection 11/14/2018 Approved DERRICK SPENCER
Deputy Steel/Welding 11/27/2018 Approved DERRICK SPENCER
Deputy Steel/Welding 11/28/2018 Approved DERRICK SPENCER
Deputy Steel/Welding 11/29/2018 Approved DERRICK SPENCER
Deputy Steel/Welding 11/30/2018 Approved DERRICK SPENCER
Structural Steel Frame 1/10/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 1/14/2019 Partial Approval SORIN CIRSTOIU
Green Building Rough 1/23/2019 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 1/23/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 1/29/2019 Partial Approval JOHN DODGE
Reinforced Masonry Frame 1/31/2019 Not Ready for Inspection SORIN CIRSTOIU
Special/Order Compliance 2/1/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 2/7/2019 Approved SORIN CIRSTOIU
Special/Order Compliance 2/7/2019 Partial Inspection SORIN CIRSTOIU
Green Building Rough 2/8/2019 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 2/8/2019 Not Ready for Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 2/11/2019 Partial Approval SORIN CIRSTOIU
Deputy Fireproofing 2/13/2019 Approved SORIN CIRSTOIU
Drywall Nailing 2/13/2019 Partial Approval SORIN CIRSTOIU
Green Building Rough 2/13/2019 Not Ready for Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 2/13/2019 Partial Approval SORIN CIRSTOIU
Deputy Fireproofing 2/14/2019 Approved DERRICK SPENCER
Deputy Fireproofing 2/15/2019 Conditional Approval SORIN CIRSTOIU
Deputy Fireproofing 2/19/2019 Approved SORIN CIRSTOIU
Reinforced Masonry Frame 2/19/2019 Approved SORIN CIRSTOIU
Deputy Fireproofing 2/20/2019 Conditional Approval SORIN CIRSTOIU
Deputy Fireproofing 2/21/2019 Approved DERRICK SPENCER
Deputy Fireproofing 2/22/2019 Approved SORIN CIRSTOIU
Drywall Nailing 2/22/2019 Partial Approval SORIN CIRSTOIU
Special/Order Compliance 2/22/2019 Approved SORIN CIRSTOIU
Deputy Fireproofing 2/25/2019 Conditional Approval SORIN CIRSTOIU
Special/Order Compliance 2/27/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/5/2019 Conditional Approval SORIN CIRSTOIU
Masonry Wall/Backfill 3/8/2019 Partial Approval SORIN CIRSTOIU
Reinforced Masonry Frame 3/8/2019 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 3/14/2019 Partial Approval SORIN CIRSTOIU
Masonry Wall/Backfill 3/14/2019 Approved SORIN CIRSTOIU
Reinforced Masonry Frame 3/14/2019 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 3/20/2019 Partial Approval SORIN CIRSTOIU
Special/Order Compliance 3/20/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/21/2019 Approved SORIN CIRSTOIU
Drywall Nailing 3/27/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 3/27/2019 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 4/2/2019 Partial Inspection SORIN CIRSTOIU
Green Building Rough 4/2/2019 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 4/2/2019 Corrections Issued SORIN CIRSTOIU
Structural Steel Frame 4/2/2019 Partial Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 4/4/2019 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 4/8/2019 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 4/8/2019 Partial Approval SORIN CIRSTOIU
Green Building Rough 4/8/2019 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 4/8/2019 Partial Approval SORIN CIRSTOIU
Drywall Nailing 4/30/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 4/30/2019 Not Ready for Inspection SORIN CIRSTOIU
Green Building Rough 4/30/2019 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 4/30/2019 Not Ready for Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 5/1/2019 Partial Approval DERRICK SPENCER
Green Building Rough 5/8/2019 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 5/8/2019 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 5/9/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 5/9/2019 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 5/16/2019 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 5/16/2019 Partial Inspection SORIN CIRSTOIU
Green Building Rough 5/16/2019 Partial Inspection SORIN CIRSTOIU
Light Gage Steel Frame 5/16/2019 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 5/16/2019 Partial Inspection SORIN CIRSTOIU
Structural Steel Frame 5/16/2019 Partial Inspection SORIN CIRSTOIU
Deputy Drilled-In Anchors 5/17/2019 Conditional Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 5/20/2019 Partial Approval SORIN CIRSTOIU
Drywall Nailing 5/22/2019 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 5/22/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 5/22/2019 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 5/22/2019 Partial Approval SORIN CIRSTOIU
Drywall Nailing 5/28/2019 Partial Approval SORIN CIRSTOIU
Drywall Nailing 5/31/2019 Not Ready for Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 5/31/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 5/31/2019 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 5/31/2019 Not Ready for Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 6/6/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 6/6/2019 Partial Approval SORIN CIRSTOIU
Reinforced Masonry Frame 6/17/2019 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 6/18/2019 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 6/20/2019 Not Ready for Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 6/20/2019 Not Ready for Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 6/24/2019 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 6/24/2019 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 6/28/2019 Partial Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 7/1/2019 Not Ready for Inspection SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 7/19/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 7/19/2019 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 7/26/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 7/26/2019 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 8/5/2019 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 8/5/2019 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 8/12/2019 Conditional Approval SORIN CIRSTOIU
Footing/Foundation/Slab 8/12/2019 Conditional Approval SORIN CIRSTOIU
Special/Order Compliance 8/12/2019 Partial Inspection TED RIES
Deputy Reinf. Masonry 8/15/2019 Approved DERRICK SPENCER
Deputy Reinf. Masonry 8/16/2019 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 8/19/2019 Approved SORIN CIRSTOIU
Reinforced Concrete Frame 8/19/2019 Partial Approval SORIN CIRSTOIU
Wall Anchors 8/19/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Masonry 8/20/2019 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 8/21/2019 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Masonry 8/22/2019 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Masonry 8/23/2019 Conditional Approval SORIN CIRSTOIU
Insulation 8/28/2019 Partial Approval SORIN CIRSTOIU
Pre-Inspection 9/5/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/10/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 10/10/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/11/2019 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Concrete 10/11/2019 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 10/15/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 10/15/2019 Approved SORIN CIRSTOIU
Pre-Inspection 10/15/2019 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/16/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 10/16/2019 Approved SORIN CIRSTOIU
Pre-Inspection 10/16/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/17/2019 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 10/17/2019 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/18/2019 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 10/18/2019 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/21/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/22/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/23/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/24/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/25/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/28/2019 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/29/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/30/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/31/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 11/1/2019 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 11/4/2019 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 11/5/2019 Partial Approval SORIN CIRSTOIU
Pre-Inspection 11/5/2019 Approved SORIN CIRSTOIU
Pre-Inspection 11/8/2019 Approved SORIN CIRSTOIU
Final 11/22/2019 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 11/22/2019 Partial Inspection SORIN CIRSTOIU
Green Building Final 11/22/2019 Partial Inspection SORIN CIRSTOIU
Green Building Rough 11/22/2019 Approved SORIN CIRSTOIU
Reinforced Concrete Frame 11/22/2019 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 11/22/2019 SGSOV Approved SORIN CIRSTOIU
Smoke Detectors 11/22/2019 Approved SORIN CIRSTOIU
Final 12/5/2019 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 12/5/2019 Partial Inspection SORIN CIRSTOIU
Green Building Final 12/5/2019 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 12/5/2019 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 10/1/2020 Partial Inspection PAUL DAVIDSON
Green Building Final 10/1/2020 Not Ready for Inspection PAUL DAVIDSON
Pre-Inspection 10/1/2020 Approved PAUL DAVIDSON
Reinforced Concrete Frame 10/1/2020 Partial Inspection PAUL DAVIDSON
Deputy Steel/Welding 8/1/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/2/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/3/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/4/2023 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 8/9/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/9/2023 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 8/10/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/10/2023 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 8/14/2023 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Concrete 8/14/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/14/2023 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 8/15/2023 Approved GRANT WOODS
Deputy Steel/Welding 8/15/2023 Approved GRANT WOODS
Reinforced Concrete Frame 8/15/2023 Not Ready for Inspection GRANT WOODS
Deputy Reinf. Concrete 8/16/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/16/2023 Conditional Approval PAUL DAVIDSON
Deputy Fireproofing 8/22/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/22/2023 Conditional Approval PAUL DAVIDSON
Deputy Fireproofing 8/23/2023 Conditional Approval MICHAEL PETRUSKO
Deputy Steel/Welding 8/23/2023 Conditional Approval MICHAEL PETRUSKO
Deputy Fireproofing 8/24/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/24/2023 Conditional Approval PAUL DAVIDSON
Deputy Fireproofing 8/25/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/25/2023 Conditional Approval PAUL DAVIDSON
Special/Order Compliance 8/25/2023 Partial Inspection PAUL DAVIDSON
Light Gage Steel Frame 8/28/2023 Partial Approval PAUL DAVIDSON
Structural Steel Frame 8/28/2023 Partial Approval PAUL DAVIDSON
Structural Steel Frame 9/14/2023 Not Ready for Inspection GRANT WOODS
Deputy Fireproofing 9/15/2023 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 9/15/2023 Conditional Approval PAUL DAVIDSON
Light Gage Steel Frame 9/28/2023 Partial Approval PAUL DAVIDSON
Deputy Reinf. Concrete 9/29/2023 Conditional Approval FARHAD DADBIN
Deputy Steel/Welding 9/29/2023 Conditional Approval FARHAD DADBIN
Light Gage Steel Frame 10/6/2023 Approved MICHAEL PETRUSKO
Deputy Reinf. Concrete 10/10/2023 Conditional Approval PAUL DAVIDSON
Pre-Inspection 11/13/2023 Partial Inspection PAUL DAVIDSON
Final 11/20/2023 Partial Inspection AMANUEL BERHE
Final 11/30/2023 Not Ready for Inspection PAUL DAVIDSON
Footing/Foundation/Slab 11/30/2023 Approved PAUL DAVIDSON
Green Building Final 11/30/2023 Not Ready for Inspection PAUL DAVIDSON
Reinforced Concrete Frame 11/30/2023 Approved PAUL DAVIDSON
Final 12/5/2023 Conditional Approval MICHAEL PETRUSKO
Green Building Final 12/5/2023 Approved MICHAEL PETRUSKO