3711 S VETERAN AVE 90034

Certificate Information: 3711 S VETERAN AVE 90034

Application / Permit
17014-10000-04462
Plan Check / Job No.
B17LA15998
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Demo Existing ALQ down to a single wall (East wall) and construct new detached 2-story, 35'x23', Type VB, R3-Occ Accessory Dwelling Unit per AB 2299 AND SB 1069
Permit Issued
Issued on 11/13/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2017 APPLICANT
Assigned to Plan Check Engineer 9/21/2017 DEVIN GORDON
Corrections Issued 9/28/2017 DEVIN GORDON
Green Plans Picked Up 10/11/2017 APPLICANT
Quality Review Completed 10/12/2017 ARMEN JIVALAGIAN
Building Plans Picked Up 10/13/2017 APPLICANT
Applicant returned to address corrections 11/7/2017 DEVIN GORDON
Plan Check Approved 5/14/2018 DEVIN GORDON
Plan Check Approved 5/14/2018 ARSALAN SHABESTARI
Issued 11/13/2019 LADBS
CofO in Progress 10/29/2021 KENNETH NAGLE
Permit Finaled 10/29/2021 KENNETH NAGLE
CofO Issued 10/29/2021 KENNETH NAGLE
Permit Finaled 10/29/2021 KENNETH NAGLE

Permit Application Clearance Information

Green Code Cleared 10/30/2017 KATHRYN BUTTERWORTH
Address approval Cleared 11/1/2017 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 11/1/2017 RAVIL MANAPOV
Hydrant and Access approval Cleared 11/1/2017 ROBERT DUFF
Sewer availability Cleared 11/1/2017 RAVIL MANAPOV
Low Impact Development Cleared 11/7/2017 MITESH PATEL
Roof/Waste drainage to street Cleared 11/7/2017 STEVE MELGAR
Construction near power lines Cleared 2/22/2018 RIDWAN HARDY
GPI Written Notices Cleared 4/24/2018 DEVIN GORDON
Grading Pre-Inspection Cleared 4/24/2018 DEVIN GORDON

Contact Information

Architect Song, Michael; Lic. No.: C32566 5608 E PEABODY STREET      LONG BEACH, CA 90808
Contractor All Star Prime Construction Services Inc; Lic. No.: 1034984-B 123 S MESA ST      SAN PEDRO, CA 90731

Inspector Information

BOBBY KEY, (310) 914-3907 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/5/2020 Not Ready for Inspection KEVIN BEAULIEU
Footing/Foundation/Slab 2/5/2020 Not Ready for Inspection KEVIN BEAULIEU
Excavation/Setback/Form/Re-Bar 2/13/2020 Conditional Approval KEVIN BEAULIEU
Footing/Foundation/Slab 2/13/2020 Not Ready for Inspection KEVIN BEAULIEU
PLUMBING-Rough 2/13/2020 Partial Approval KEVIN BEAULIEU
Footing/Foundation/Slab 3/11/2020 Not Ready for Inspection KEVIN BEAULIEU
Footing/Foundation/Slab 3/24/2020 Corrections Issued KENNETH NAGLE
Footing/Foundation/Slab 3/31/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/2/2020 Approved KENNETH NAGLE
PLUMBING-Rough 4/2/2020 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval KENNETH NAGLE
PLUMBING-Rough 8/6/2020 Corrections Issued KENNETH NAGLE
Wood Frame 8/6/2020 Corrections Issued KENNETH NAGLE
PLUMBING-Rough 8/7/2020 Conditional Approval KENNETH NAGLE
BUILDING-Rough-Frame 9/24/2020 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Rough 9/24/2020 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 9/24/2020 Not Ready for Inspection KENNETH NAGLE
HVAC-Rough 9/24/2020 Not Ready for Inspection KENNETH NAGLE
PLUMBING-Rough 9/24/2020 Not Ready for Inspection KENNETH NAGLE
ELECTRICAL-Rough 11/4/2020 Not Ready for Inspection KENNETH NAGLE
HVAC-Rough 11/4/2020 Not Ready for Inspection KENNETH NAGLE
PLUMBING-Rough 11/4/2020 Not Ready for Inspection KENNETH NAGLE
Wood Frame 11/4/2020 Partial Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 11/5/2020 Conditional Approval KENNETH NAGLE
BUILDING-Rough-Frame 12/3/2020 Partial Approval KENNETH NAGLE
ELECTRICAL-Rough 12/3/2020 Approved KENNETH NAGLE
HVAC-Rough 12/3/2020 Corrections Issued KENNETH NAGLE
PLUMBING-Rough 12/3/2020 Approved KENNETH NAGLE
BUILDING-Rough-Frame 12/29/2020 Corrections Issued KENNETH NAGLE
HVAC-Rough 12/29/2020 Corrections Issued KENNETH NAGLE
Insulation 12/29/2020 Not Ready for Inspection KENNETH NAGLE
Interior/Exterior Lathing 12/29/2020 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 1/6/2021 Approved KENNETH NAGLE
Footing/Foundation/Slab 1/6/2021 Approved KENNETH NAGLE
Green Building Rough 1/6/2021 Approved KENNETH NAGLE
HVAC-Rough 1/6/2021 Approved KENNETH NAGLE
Insulation 1/6/2021 Approved KENNETH NAGLE
Drywall Nailing 1/20/2021 Approved KENNETH NAGLE
Interior/Exterior Lathing 1/26/2021 Approved KENNETH NAGLE
Final 5/25/2021 Corrections Issued EVAN COOPER
Green Building Final 5/25/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/25/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 5/25/2021 Approved EVAN COOPER
Final 5/26/2021 Corrections Issued KENNETH NAGLE
Final 10/25/2021 Conditional Approval KENNETH NAGLE