2422 S 7TH AVE 90018

Certificate Information: 2422 S 7TH AVE 90018

Application / Permit
17014-10000-04026
Plan Check / Job No.
B17LA14514
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION, MAJOR REMODEL, GROUND FLOOR ADDITION COMBINING DETACHED GARAGES, & SECOND STORY ADDITION TO (E) GARAGE & STORAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER REASONABLE ACCOMDATION REQUEST DIR-2017-4429-RAO
Permit Issued
Issued on 6/12/2019
Issuing Office
South Los Angeles
Current Status
CofO Issued on 2/28/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2017 APPLICANT
Assigned to Plan Check Engineer 8/24/2017 LAMAR DAVIS
Corrections Issued 8/26/2017 LAMAR DAVIS
Plans on Hold 9/7/2017 ALLEN MANALANSAN
Hold Released 10/3/2017 ALLEN MANALANSAN
Quality Review Completed 10/3/2017 ALLEN MANALANSAN
Building Plans Picked Up 10/6/2017 APPLICANT
Green Plans Picked Up 10/26/2017 APPLICANT
Applicant returned to address corrections 6/14/2018 LAMAR DAVIS
Applicant returned to address corrections 2/15/2019 LAMAR DAVIS
Plan Check Approved 4/2/2019 LAMAR DAVIS
Issued 6/12/2019 LADBS
CofO in Progress 2/28/2020 RONALD MYRICK
Permit Finaled 2/28/2020 RONALD MYRICK
CofO Issued 2/28/2020 RONALD MYRICK
Permit Finaled 2/28/2020 RONALD MYRICK

Permit Application Clearance Information

Hold Cleared 8/24/2017 TERESA MUI
Address approval Cleared 11/22/2017 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 11/22/2017 ADRIAN SANCHEZ
Sewer availability Cleared 11/22/2017 ADRIAN SANCHEZ
Miscellaneous Cleared 11/2/2018 YOVANA PEREZ
ZA Case Cleared 11/2/2018 YOVANA PEREZ
HPOZ Cleared 11/6/2018 LYDIA CHAPMAN
Miscellaneous Cleared 11/6/2018 LYDIA CHAPMAN
Miscellaneous Cleared 11/6/2018 LYDIA CHAPMAN
Green Code Cleared 2/6/2019 KATHRYN BUTTERWORTH
Low Impact Development Cleared 2/7/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 2/14/2019 KAREN LE
Construction near power lines Cleared 3/22/2019 RIDWAN HARDY

Contact Information

Contractor R P M Development; Lic. No.: 529637-B P O BOX 452802      LOS ANGELES, CA 90045
Engineer Li, Dacheng David; Lic. No.: C58075 23240 RIDGELINE DR      DIAMOND BAR, CA 91765

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/1/2019 Conditional Approval CHARLENE BUSTAMANTE
Footing/Foundation/Slab 7/1/2019 Conditional Approval CHARLENE BUSTAMANTE
METHANE-Barrier 7/1/2019 Approved CHARLENE BUSTAMANTE
METHANE-Subgrade 7/1/2019 Approved CHARLENE BUSTAMANTE
PLUMBING-Rough 7/19/2019 Partial Approval CHARLENE BUSTAMANTE
BUILDING-Rough-Frame 8/30/2019 Conditional Approval CHARLENE BUSTAMANTE
Floor/Roof Diaphrgm/Shear Wall 8/30/2019 Corrections Issued CHARLENE BUSTAMANTE
Green Building Rough 8/30/2019 Corrections Issued CHARLENE BUSTAMANTE
HVAC-Rough 8/30/2019 Not Ready for Inspection CHARLENE BUSTAMANTE
Deputy Wood Construction 9/11/2019 Conditional Approval CHARLENE BUSTAMANTE
ELECTRICAL-Rough 9/27/2019 Approved CHARLENE BUSTAMANTE
Floor/Roof Diaphrgm/Shear Wall 9/27/2019 Approved CHARLENE BUSTAMANTE
HVAC-Rough 9/27/2019 Approved CHARLENE BUSTAMANTE
PLUMBING-Rough 9/27/2019 Approved CHARLENE BUSTAMANTE
Insulation 10/1/2019 Approved ROBERT VORHIS
BUILDING-Rough-Frame 10/7/2019 Corrections Issued CHARLENE BUSTAMANTE
Drywall Nailing 10/7/2019 Approved CHARLENE BUSTAMANTE
Green Building Rough 10/7/2019 Approved CHARLENE BUSTAMANTE
Interior/Exterior Lathing 10/18/2019 Approved HENRY KIM
BUILDING-Rough-Frame 12/20/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/20/2019 Corrections Issued ALEJANDRO DE ARTOLA
Final 12/20/2019 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/20/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
Green Building Final 12/20/2019 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Final 12/20/2019 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 12/20/2019 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Rough 12/20/2019 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Final 12/20/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
METHANE-Rough 12/20/2019 Not Ready for Inspection ALEJANDRO DE ARTOLA
PLUMBING-Final 12/20/2019 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/20/2019 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 12/20/2019 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/27/2019 Approved SCOTT FINNILA
ELECTRICAL-Final 12/27/2019 Approved SCOTT FINNILA
Final 12/27/2019 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 12/27/2019 Approved SCOTT FINNILA
Green Building Final 12/27/2019 Approved SCOTT FINNILA
HVAC-Final 12/27/2019 Approved SCOTT FINNILA
MERV13>=Final 12/27/2019 Approved SCOTT FINNILA
MERV13>=Rough 12/27/2019 Approved SCOTT FINNILA
METHANE-Final 12/27/2019 Approved SCOTT FINNILA
METHANE-Rough 12/27/2019 Approved SCOTT FINNILA
PLUMBING-Final 12/27/2019 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 12/27/2019 SGSOV Approved SCOTT FINNILA
Verify Sprinkler Sign Off 12/27/2019 Approved SCOTT FINNILA
Final 1/7/2020 Partial Approval CHARLENE BUSTAMANTE