270 S WINDSOR BLVD 90004
Certificate Information: 270 S WINDSOR BLVD 90004
- Application / Permit
- 17014-10000-03975
- Plan Check / Job No.
- B17LA14350
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO-STORY 15'X39' ADDITION TO AN EXISTING 69'X56' SFD, TYPE V-B, R-3 OCC., NFDA13D SPRINKLER SYSTEM.
- Permit Issued
- Issued on 3/6/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2017 | ARSEN ADZHEMYAN |
| Corrections Issued | 8/17/2017 | ARSEN ADZHEMYAN |
| Quality Review Completed | 9/5/2017 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 9/7/2017 | APPLICANT |
| Green Plans Picked Up | 9/7/2017 | APPLICANT |
| Applicant returned to address corrections | 11/6/2017 | DEVIN GORDON |
| Plan Check Approved | 11/7/2017 | DEVIN GORDON |
| Issued | 3/6/2018 | LADBS |
| CofO in Progress | 10/2/2024 | JEFFREY MEAD |
| Permit Finaled | 12/3/2024 | DEROLD HAUFF |
| CofO Issued | 12/3/2024 | DEROLD HAUFF |
| Permit Finaled | 12/3/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2017 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 10/3/2017 | ADRIAN SANCHEZ |
| Green Code | Cleared | 10/12/2017 | WILLIAM ROSE |
| Roof/Waste drainage to street | Cleared | 10/20/2017 | JAMES KHO |
| CPC | Cleared | 10/23/2017 | KIMBERLY HENRY |
| CPC | Cleared | 10/23/2017 | KIMBERLY HENRY |
| HPOZ | Cleared | 10/23/2017 | KIMBERLY HENRY |
| Low Impact Development | Cleared | 11/6/2017 | SAM NAVID |
Contact Information
| Architect | Soler, Jeffrey Robert; Lic. No.: C30180 | 619 N KILKEA DRIVE LOS ANGELES, CA 90048 |
| Contractor | Designing Edge Builders; Lic. No.: 947772-B | 17611 DELANO ST ENCINO, CA 91316 |
| Engineer | Reith, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Barrier | 4/18/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Subgrade | 4/18/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/20/2018 | Partial Approval | JOSEPH MCGARRY |
| METHANE-Barrier | 4/20/2018 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 4/20/2018 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/27/2018 | Partial Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/8/2018 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 5/8/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Rough | 5/8/2018 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 5/23/2018 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2018 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/5/2018 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2018 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 7/5/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 7/12/2019 | Approved | LUIS BARRALES |
| Pre-Inspection | 11/15/2019 | Approved | LUIS BARRALES |
| BUILDING-Rough-Frame | 3/13/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 3/13/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 2/2/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/19/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/19/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/19/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/26/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/26/2021 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 4/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 5/26/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Wood Construction | 5/26/2021 | No Access for Inspection | ELMER BLAND |
| Interior/Exterior Lathing | 5/27/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/28/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 5/28/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/28/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 6/4/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 6/18/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/16/2021 | Approved | CHARLES BOGHOSKHAN |
| Service/Power Release | 1/13/2022 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 5/10/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Special/Order Compliance | 7/18/2022 | Corrections Issued | JOSEPH MCGARRY |
| Special/Order Compliance | 8/19/2022 | No Access for Inspection | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 8/30/2022 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Final | 12/13/2022 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Final | 2/1/2023 | Corrections Issued | JEFFREY MEAD |
| Final | 2/1/2023 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 2/1/2023 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 2/1/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/9/2023 | Approved | JEFFREY MEAD |
| Final | 2/9/2023 | Partial Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/9/2023 | Approved | JEFFREY MEAD |
| Green Building Final | 2/9/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 2/9/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 2/9/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/10/2023 | Approved | JEFFREY MEAD |
| Final | 2/10/2023 | Partial Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/10/2023 | Approved | JEFFREY MEAD |
| Green Building Final | 2/10/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 2/10/2023 | Approved | JEFFREY MEAD |
| Final | 10/2/2024 | OK to Issue CofO | JEFFREY MEAD |