627 S SAN JULIAN ST 90014

Certificate Information: 627 S SAN JULIAN ST 90014

Application / Permit
17014-10000-03951
Plan Check / Job No.
B17LA14272
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(11) Dormitory
Work Description
TENANT IMPROVEMENT AND GROUND FLOOR GUARD KIOSK ADDITION TO EXISTING 2-STORY DORMITORY BUILDING WITH PROPOSED OFF-SITE PARKING.
Permit Issued
Issued on 6/21/2019
Issuing Office
Metro
Current Status
CofO Issued on 5/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2017 APPLICANT
Assigned to Plan Check Engineer 8/17/2017 LAWRENCE QUIRANTE
Corrections Issued 8/21/2017 LAWRENCE QUIRANTE
Quality Review Completed 8/21/2017 JAMESON LEE
Building Plans Picked Up 8/23/2017 APPLICANT
Green Plans Picked Up 8/23/2017 APPLICANT
Disabled Access Plans Picked Up 8/25/2017 APPLICANT
Applicant returned to address corrections 11/30/2017 LAWRENCE QUIRANTE
Plan Check Approved 11/29/2018 RICARDO SUPAN
No Progress 5/6/2019 EUGENE BARBEAU
Plan Check Approved 6/19/2019 EUGENE BARBEAU
Issued 6/21/2019 LADBS
CofO in Progress 5/28/2020 DANIEL COLLINS
CofO Issued 5/29/2020 DAVID TSAU
Permit Finaled 5/29/2020 DAVID TSAU

Permit Application Clearance Information

"D" conditions Cleared 9/14/2017 DANALYNN DOMINGUEZ
Highway dedication Cleared 11/6/2017 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 2/7/2018 MICHAEL CASTILLO
Sewer availability Cleared 2/20/2018 STEVE MELGAR
ZA Case Cleared 4/10/2018 EDBER MACEDO
DAS Clearance Cleared 6/7/2019 LAWRENCE QUIRANTE
Project located in CRA area Cleared 6/13/2019 JIM URQUHART
"Q" conditions Cleared 6/14/2019 ANNA VAN
Green Code Cleared 6/14/2019 RICHARD DOCKUS

Contact Information

Architect Arnold, John Howard; Lic. No.: C30834 2166 W 30TH STREET      LOS ANGELES, CA 90018
Engineer Toranzo-Dianderas,, Luis Alberto; Lic. No.: S6014 7235 N MAPLE ROAD      VAN NUYS, CA 91405

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/16/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 8/14/2019 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 8/14/2019 Not Ready for Inspection MARK FERRARI
Deputy Reinf. Concrete 8/15/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 8/15/2019 Partial Inspection MARK FERRARI
Deputy Reinf. Concrete 8/16/2019 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 8/16/2019 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 8/20/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 8/29/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 9/3/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 9/5/2019 Conditional Approval DANIEL COLLINS
Green Building Rough 9/5/2019 Approved DANIEL COLLINS
Reinforced Concrete Frame 9/5/2019 Not Ready for Inspection DANIEL COLLINS
Deputy Drilled-In Anchors 9/6/2019 Conditional Approval DANIEL COLLINS
Reinforced Masonry Frame 9/6/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 9/9/2019 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 9/11/2019 Not Ready for Inspection DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 9/16/2019 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 9/17/2019 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 9/25/2019 Not Ready for Inspection DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 9/27/2019 Not Ready for Inspection DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 10/1/2019 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/2/2019 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 10/3/2019 Partial Approval DANIEL COLLINS
Wood Frame 10/3/2019 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 11/12/2019 Corrections Issued DANIEL COLLINS
Light Gage Steel Frame 11/13/2019 Partial Inspection DANIEL COLLINS
Drywall Nailing 12/2/2019 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/2/2019 Partial Inspection DANIEL COLLINS
Wood Frame 12/2/2019 Partial Inspection DANIEL COLLINS
Drywall Nailing 12/10/2019 Approved DANIEL COLLINS
Insulation 12/10/2019 Approved DANIEL COLLINS
Interior/Exterior Lathing 12/10/2019 Partial Approval DANIEL COLLINS
Drywall Nailing 12/17/2019 Approved DANIEL COLLINS
Deputy Reinf. Concrete 12/18/2019 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 12/18/2019 Approved DANIEL COLLINS
Deputy Reinf. Concrete 12/19/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 1/7/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 1/8/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 2/3/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 2/6/2020 Conditional Approval DANIEL COLLINS
Grading Pre-Inspection 2/6/2020 Partial Approval DANIEL COLLINS
Final 2/13/2020 Not Ready for Inspection DANIEL COLLINS
Footing/Foundation/Slab 2/13/2020 Approved DANIEL COLLINS
Green Building Final 2/13/2020 Not Ready for Inspection DANIEL COLLINS
Reinforced Masonry Frame 2/13/2020 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 2/13/2020 SGSOV Approved DANIEL COLLINS
Smoke Detectors 2/13/2020 Approved DANIEL COLLINS
Deputy Reinf. Concrete 2/18/2020 Conditional Approval DANIEL COLLINS
Final 5/8/2020 Corrections Issued JONATHAN QUACH
Green Building Final 5/8/2020 Not Ready for Inspection JONATHAN QUACH
Final 5/20/2020 Not Ready for Inspection DANIEL COLLINS
Green Building Final 5/20/2020 Not Ready for Inspection DANIEL COLLINS
Final 5/22/2020 OK to Issue CofO DANIEL COLLINS
Green Building Final 5/22/2020 Approved DANIEL COLLINS