627 S SAN JULIAN ST 90014
Certificate Information: 627 S SAN JULIAN ST 90014
- Application / Permit
- 17014-10000-03951
- Plan Check / Job No.
- B17LA14272
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (11) Dormitory
- Work Description
- TENANT IMPROVEMENT AND GROUND FLOOR GUARD KIOSK ADDITION TO EXISTING 2-STORY DORMITORY BUILDING WITH PROPOSED OFF-SITE PARKING.
- Permit Issued
- Issued on 6/21/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2017 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/21/2017 | LAWRENCE QUIRANTE |
| Quality Review Completed | 8/21/2017 | JAMESON LEE |
| Building Plans Picked Up | 8/23/2017 | APPLICANT |
| Green Plans Picked Up | 8/23/2017 | APPLICANT |
| Disabled Access Plans Picked Up | 8/25/2017 | APPLICANT |
| Applicant returned to address corrections | 11/30/2017 | LAWRENCE QUIRANTE |
| Plan Check Approved | 11/29/2018 | RICARDO SUPAN |
| No Progress | 5/6/2019 | EUGENE BARBEAU |
| Plan Check Approved | 6/19/2019 | EUGENE BARBEAU |
| Issued | 6/21/2019 | LADBS |
| CofO in Progress | 5/28/2020 | DANIEL COLLINS |
| CofO Issued | 5/29/2020 | DAVID TSAU |
| Permit Finaled | 5/29/2020 | DAVID TSAU |
Permit Application Clearance Information
| "D" conditions | Cleared | 9/14/2017 | DANALYNN DOMINGUEZ |
| Highway dedication | Cleared | 11/6/2017 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2018 | MICHAEL CASTILLO |
| Sewer availability | Cleared | 2/20/2018 | STEVE MELGAR |
| ZA Case | Cleared | 4/10/2018 | EDBER MACEDO |
| DAS Clearance | Cleared | 6/7/2019 | LAWRENCE QUIRANTE |
| Project located in CRA area | Cleared | 6/13/2019 | JIM URQUHART |
| "Q" conditions | Cleared | 6/14/2019 | ANNA VAN |
| Green Code | Cleared | 6/14/2019 | RICHARD DOCKUS |
Contact Information
| Architect | Arnold, John Howard; Lic. No.: C30834 | 2166 W 30TH STREET LOS ANGELES, CA 90018 |
| Engineer | Toranzo-Dianderas,, Luis Alberto; Lic. No.: S6014 | 7235 N MAPLE ROAD VAN NUYS, CA 91405 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/16/2019 | Conditional Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 8/14/2019 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 8/14/2019 | Not Ready for Inspection | MARK FERRARI |
| Deputy Reinf. Concrete | 8/15/2019 | Conditional Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 8/15/2019 | Partial Inspection | MARK FERRARI |
| Deputy Reinf. Concrete | 8/16/2019 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/16/2019 | Partial Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 8/20/2019 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 8/29/2019 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 9/3/2019 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 9/5/2019 | Conditional Approval | DANIEL COLLINS |
| Green Building Rough | 9/5/2019 | Approved | DANIEL COLLINS |
| Reinforced Concrete Frame | 9/5/2019 | Not Ready for Inspection | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 9/6/2019 | Conditional Approval | DANIEL COLLINS |
| Reinforced Masonry Frame | 9/6/2019 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 9/9/2019 | Conditional Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 9/11/2019 | Not Ready for Inspection | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 9/16/2019 | Approved | HAMID PISHEHVAR |
| Deputy Reinf. Concrete | 9/17/2019 | Conditional Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 9/25/2019 | Not Ready for Inspection | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 9/27/2019 | Not Ready for Inspection | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 10/1/2019 | Partial Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 10/2/2019 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 10/3/2019 | Partial Approval | DANIEL COLLINS |
| Wood Frame | 10/3/2019 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 11/12/2019 | Corrections Issued | DANIEL COLLINS |
| Light Gage Steel Frame | 11/13/2019 | Partial Inspection | DANIEL COLLINS |
| Drywall Nailing | 12/2/2019 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/2/2019 | Partial Inspection | DANIEL COLLINS |
| Wood Frame | 12/2/2019 | Partial Inspection | DANIEL COLLINS |
| Drywall Nailing | 12/10/2019 | Approved | DANIEL COLLINS |
| Insulation | 12/10/2019 | Approved | DANIEL COLLINS |
| Interior/Exterior Lathing | 12/10/2019 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 12/17/2019 | Approved | DANIEL COLLINS |
| Deputy Reinf. Concrete | 12/18/2019 | Conditional Approval | DANIEL COLLINS |
| Reinforced Concrete Frame | 12/18/2019 | Approved | DANIEL COLLINS |
| Deputy Reinf. Concrete | 12/19/2019 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 1/7/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 1/8/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 2/3/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 2/6/2020 | Conditional Approval | DANIEL COLLINS |
| Grading Pre-Inspection | 2/6/2020 | Partial Approval | DANIEL COLLINS |
| Final | 2/13/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Footing/Foundation/Slab | 2/13/2020 | Approved | DANIEL COLLINS |
| Green Building Final | 2/13/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Reinforced Masonry Frame | 2/13/2020 | Approved | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 2/13/2020 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 2/13/2020 | Approved | DANIEL COLLINS |
| Deputy Reinf. Concrete | 2/18/2020 | Conditional Approval | DANIEL COLLINS |
| Final | 5/8/2020 | Corrections Issued | JONATHAN QUACH |
| Green Building Final | 5/8/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 5/20/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Green Building Final | 5/20/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Final | 5/22/2020 | OK to Issue CofO | DANIEL COLLINS |
| Green Building Final | 5/22/2020 | Approved | DANIEL COLLINS |