1811 E 109TH ST 90059

Certificate Information: 1811 E 109TH ST 90059

Application / Permit
17014-10000-03650
Plan Check / Job No.
B17LA13322
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 STORY ADDITION TO 1 STORY SFD
Permit Issued
Issued on 9/27/2018
Issuing Office
Metro
Current Status
CofO Issued on 4/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2017 APPLICANT
Assigned to Plan Check Engineer 7/26/2017 VLADIMIR ARUTYUNYAN
Corrections Issued 8/22/2017 VLADIMIR ARUTYUNYAN
Plan Check Approved 9/27/2018 HELEN NGUYEN
Issued 9/27/2018 LADBS
CofO in Progress 3/10/2021 EUGENE CASSIDY
Permit Finaled 4/10/2021 DEROLD HAUFF
CofO Issued 4/10/2021 DEROLD HAUFF
Permit Finaled 4/10/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/12/2017 RAVIL MANAPOV
Roof/Waste drainage to street Cleared 10/12/2017 RAVIL MANAPOV
Sewer availability Cleared 10/12/2017 RAVIL MANAPOV
Low Impact Development Cleared 9/27/2018 MATTHEW JIMENEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Zhong, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/15/2018 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 2/11/2019 Not Ready for Inspection DAVID FEILER
Pre-Inspection 2/5/2020 Corrections Issued WILLIAM ROSE
BUILDING-Rough-Frame 11/12/2020 Approved EUGENE CASSIDY
Final 11/12/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 11/12/2020 Approved EUGENE CASSIDY
Green Building Final 11/12/2020 Approved EUGENE CASSIDY
Green Building Rough 11/12/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 11/12/2020 Approved EUGENE CASSIDY
Footing/Foundation/Slab 12/15/2020 Corrections Issued EUGENE CASSIDY
Pre-Inspection 12/15/2020 Not Ready for Inspection EUGENE CASSIDY
Final 3/4/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 3/4/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Not Ready EUGENE CASSIDY
ELECTRICAL-Final 3/10/2021 Approved EUGENE CASSIDY
Final 3/10/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 3/10/2021 Approved EUGENE CASSIDY
PLUMBING-Final 3/10/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/10/2021 SGSOV Approved EUGENE CASSIDY