3636 W BOYCE AVE 90039
Certificate Information: 3636 W BOYCE AVE 90039
- Application / Permit
- 17014-10000-03634
- Plan Check / Job No.
- B17LA13265
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION AND INTERIOR RENOVATION TO SINGLE FAMILY DWELLING AT FRONT OF LOT
- Permit Issued
- Issued on 7/31/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2017 | KEVIN STEWART |
| Corrections Issued | 8/9/2017 | KEVIN STEWART |
| Quality Review Completed | 8/23/2017 | SAI KHUM |
| Building Plans Picked Up | 9/15/2017 | APPLICANT |
| Green Plans Picked Up | 9/15/2017 | APPLICANT |
| Applicant returned to address corrections | 3/28/2018 | KEVIN STEWART |
| Applicant returned to address corrections | 6/25/2018 | SAM CHANG |
| Applicant returned to address corrections | 7/11/2018 | SAM CHANG |
| Applicant returned to address corrections | 7/20/2018 | SAM CHANG |
| Plan Check Approved | 7/31/2018 | SAM CHANG |
| Issued | 7/31/2019 | LADBS |
| CofO in Progress | 11/14/2024 | HAMIK HARTOUNIAN |
| No Progress | 11/14/2024 | HAMIK HARTOUNIAN |
| CofO in Progress | 11/14/2024 | HAMIK HARTOUNIAN |
| Permit Finaled | 12/3/2024 | DEROLD HAUFF |
| CofO Issued | 12/3/2024 | DEROLD HAUFF |
| Permit Finaled | 12/3/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 7/6/2018 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2018 | CARLA VALLADARES |
| Sewer availability | Cleared | 7/10/2018 | CARLA VALLADARES |
| Housing rent stabilization | Cleared | 7/31/2018 | STEVEN HOFSTAD |
| Hydrant and Access approval | Cleared | 7/31/2018 | GILBERT URREA |
| Low Impact Development | Cleared | 7/31/2018 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/31/2018 | MICHAEL CASTILLO |
| ZI | Cleared | 7/31/2018 | BRIAN CARR |
Contact Information
| Contractor | Alfa Construction; Lic. No.: 768378-B | 1278 E LOS ANGELES AVE SIMI VALLEY, CA 93065 |
| Engineer | Saljooghi, Sanjar; Lic. No.: C53610 | 23265 PARK ENSENADA CALABASAS, CA 91302 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/23/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/23/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 9/25/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/4/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/4/2019 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 11/6/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 11/12/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 11/12/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 11/15/2019 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/19/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/19/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 11/19/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 11/19/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 11/19/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2019 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/19/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 1/22/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 1/22/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 2/26/2020 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 2/26/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 3/6/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/10/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 9/11/2020 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/3/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 12/3/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/23/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/23/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/23/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/1/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/1/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 3/1/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/3/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 5/3/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/3/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 5/3/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 7/8/2021 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 7/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 10/6/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Gas Test | 10/21/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/21/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Shower Pan | 10/21/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 3/22/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 3/22/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/22/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 8/9/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 8/9/2024 | Approved | THOMAS LOGRASSO |
| Final | 10/15/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 11/12/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |