4016 S BEETHOVEN ST 90066
Certificate Information: 4016 S BEETHOVEN ST 90066
- Application / Permit
- 17014-10000-03403
- Plan Check / Job No.
- B17LA12433
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED 18'x20' GARAGE TO ACCESSORY DWELLING UNIT PER AB 2299 AND SB 1069 WITH 3 UNCOVERED PARKING SPACES PROVIDED FOR SITE. See comment.
- Permit Issued
- Issued on 12/28/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2017 | TU HUA |
| Corrections Issued | 7/14/2017 | TU HUA |
| Plan Check Approved | 7/18/2017 | RICARDO SUPAN |
| Issued | 12/28/2017 | LADBS |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
| CofO Issued | 6/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2017 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2017 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/14/2017 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 7/14/2017 | ADRIAN SANCHEZ |
| Specific Plan | Cleared | 7/14/2017 | EDER ROMERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen, Scott; Lic. No.: C37989 | 710 WILSHIRE BLVD_#230 SANTA MONICA, CA 90401 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2018 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/31/2018 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/10/2018 | Corrections Issued | JONATHAN HOM |
| ELECTRICAL-Rough | 9/10/2018 | Corrections Issued | JONATHAN HOM |
| Rough-Elec/Plmb/HVAC | 9/10/2018 | No Access for Inspection | JONATHAN HOM |
| BUILDING-Rough-Frame | 10/1/2018 | Corrections Issued | JONATHAN HOM |
| ELECTRICAL-Rough | 10/1/2018 | Partial Approval | JONATHAN HOM |
| Green Building Rough | 10/1/2018 | Not Ready for Inspection | JONATHAN HOM |
| Rough-Elec/Plmb/HVAC | 10/1/2018 | Not Ready for Inspection | JONATHAN HOM |
| Shower Pan | 10/1/2018 | Approved | JONATHAN HOM |
| BUILDING-Rough-Frame | 10/5/2018 | Partial Inspection | JONATHAN HOM |
| ELECTRICAL-Rough | 10/5/2018 | Approved | JONATHAN HOM |
| Green Building Rough | 10/5/2018 | Not Ready for Inspection | JONATHAN HOM |
| PLUMBING-Rough | 10/5/2018 | Partial Inspection | JONATHAN HOM |
| BUILDING-Rough-Frame | 11/2/2018 | Partial Approval | JONATHAN HOM |
| Insulation | 11/2/2018 | Approved | JONATHAN HOM |
| Interior/Exterior Lathing | 11/2/2018 | Approved | JONATHAN HOM |
| Drywall Nailing | 4/12/2019 | Approved | JUAN VALENZUELA |
| Green Building Rough | 4/12/2019 | Approved | JUAN VALENZUELA |
| Special/Order Compliance | 4/12/2019 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/23/2019 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 12/23/2019 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Final | 12/23/2019 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/23/2019 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 12/23/2019 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/14/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 2/14/2020 | Approved | JOHNNY MIRANDA |
| Final | 2/14/2020 | Approved Pending GreenApproval | JOHNNY MIRANDA |
| Green Building Final | 2/14/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 2/14/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 2/14/2020 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 2/14/2020 | Approved | JOHNNY MIRANDA |