Application / Permit
17014-10000-03319
Plan Check / Job No.
B17LA12063
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition at 2nd floor of ( e ) 2-story single family dwelling to create new master bathroom . Interior remodel on the first floor to create bathroom and new kitchen layout. Change out of (e) windows with same size and same location . ( See comments ).
Permit Issued
Issued on 9/1/2017
Issuing Office
Metro
Current Status
CofO Issued on 10/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2017 APPLICANT
Assigned to Plan Check Engineer 7/10/2017 TU HUA
Corrections Issued 7/10/2017 TU HUA
Plan Check Approved 8/31/2017 GEORGE BANNING
Issued 9/1/2017 LADBS
CofO in Progress 9/3/2022 FREDDIE RIVERA
CofO Issued 10/12/2022 DEROLD HAUFF
Permit Finaled 10/12/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/25/2017 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 7/25/2017 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 7/25/2017 ADRIAN SANCHEZ
Sewer availability Cleared 7/25/2017 ADRIAN SANCHEZ

Contact Information

Architect Noteware, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor New World Remodeling; Lic. No.: 877349-B 7731 ANGELS CT      FONTANA, CA 92336
Engineer Canby, John Christopher; Lic. No.: C21514 2370 MIDLOTHIAN DRIVE      ALTADENA, CA 91001

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/30/2017 Approved MATTHEW NUCKOLLS
METHANE-Barrier 11/30/2017 Approved MATTHEW NUCKOLLS
METHANE-Subgrade 11/30/2017 Approved MATTHEW NUCKOLLS
Floor/Roof Diaphrgm/Shear Wall 2/22/2018 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 3/19/2018 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 3/19/2018 Partial Approval ROBERT MCDOWELL
Green Building Rough 3/19/2018 Approved ROBERT MCDOWELL
METHANE-Rough 3/19/2018 Approved ROBERT MCDOWELL
PLUMBING-Rough 3/19/2018 Partial Approval ROBERT MCDOWELL
ELECTRICAL-Rough 3/21/2018 Approved ROBERT MCDOWELL
Insulation 3/21/2018 Approved ROBERT MCDOWELL
PLUMBING-Rough 3/21/2018 Approved ROBERT MCDOWELL
Drywall Nailing 5/16/2018 Approved ROBERT MCDOWELL
ELECTRICAL-Final 12/26/2018 Not Ready for Inspection ANDEY CHAPARRO
ELECTRICAL-Final 1/21/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 1/21/2022 Not Ready for Inspection THOMAS LOGRASSO
Pre-Inspection 1/21/2022 Corrections Issued THOMAS LOGRASSO
Final 8/4/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 8/4/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/4/2022 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 8/4/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 8/9/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 8/9/2022 Partial Inspection FREDDIE RIVERA
Final 9/3/2022 OK to Issue CofO FREDDIE RIVERA