1920 N LAUGHLIN PARK DR 90027

Certificate Information: 1920 N LAUGHLIN PARK DR 90027

Application / Permit
17014-10000-03083
Plan Check / Job No.
B17LA11314
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Approximately 9'x15' 2-story ground floor addition to inlcude new kitchen and bedroom layouts. Change windows and doors same size and type . See comments.
Permit Issued
Issued on 3/19/2018
Issuing Office
Metro
Current Status
CofO Issued on 4/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2017 APPLICANT
Assigned to Plan Check Engineer 6/27/2017 JESSE JIMENEZ
Corrections Issued 7/7/2017 TU HUA
Applicant returned to address corrections 1/17/2018 JAMES DETCHMENDY
Plan Check Approved 1/25/2018 JAYDON NGUYEN
Issued 3/19/2018 LADBS
CofO in Progress 3/12/2021 BRIAN SULLIVAN
Permit Finaled 4/12/2021 DEROLD HAUFF
CofO Issued 4/12/2021 DEROLD HAUFF
Permit Finaled 4/12/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/11/2017 ADRIAN SANCHEZ
Sewer availability Cleared 12/11/2017 ADRIAN SANCHEZ
ZA Case Cleared 12/11/2017 FIPE LEILUA
Eng Process Fee Ord 176,300 Cleared 12/14/2017 RAVIL MANAPOV
Grading Pre-Inspection Cleared 1/17/2018 TU HUA
Specific Plan Cleared 1/24/2018 NURI CHO

Contact Information

Contractor F M Mercado Construction Inc; Lic. No.: 991282-B 1112 E 22ND STREET      LOS ANGELES, CA 90011
Engineer Banaie, Saeed; Lic. No.: C32792 10869 VIA VERONA      LOS ANGELES, CA 90077

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/10/2018 Approved LUIS BARRALES
Deputy Drilled-In Anchors 6/6/2018 Approved LUIS BARRALES
Footing/Foundation/Slab 6/7/2018 Partial Approval LUIS BARRALES
Footing/Foundation/Slab 6/14/2018 Partial Approval LUIS BARRALES
PLUMBING-Rough 7/9/2018 Partial Approval LUIS BARRALES
Insulation 7/17/2018 Partial Approval LUIS BARRALES
Floor/Roof Diaphrgm/Shear Wall 7/19/2018 No Access for Inspection LUIS BARRALES
Floor/Roof Diaphrgm/Shear Wall 8/2/2018 Partial Approval LUIS BARRALES
Pre-Inspection 4/17/2019 Partial Inspection RAUL BARAJAS
Interior/Exterior Lathing 11/26/2019 Approved ROBERT CORNELL
PLUMBING-Rough 11/26/2019 Approved ROBERT CORNELL
HVAC-Rough 11/27/2019 Approved ROBERT CORNELL
ELECTRICAL-Rough 12/4/2019 Approved ROBERT CORNELL
Insulation 12/18/2019 Approved ROBERT CORNELL
Drywall Nailing 12/31/2019 Approved ARTHUR SARGSYAN
Green Building Rough 12/31/2019 Approved ARTHUR SARGSYAN
Shower Pan 1/10/2020 Approved ROBERT CORNELL
Interior/Exterior Lathing 1/17/2020 Approved ROBERT CORNELL
Pre-Inspection 10/20/2020 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 11/6/2020 Approved BRIAN SULLIVAN
ELECTRICAL-Final 11/6/2020 Not Ready for Inspection BRIAN SULLIVAN
Final 11/6/2020 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 11/6/2020 Approved BRIAN SULLIVAN
Green Building Final 11/6/2020 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 11/6/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 11/6/2020 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 11/6/2020 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 11/6/2020 Not Ready for Inspection BRIAN SULLIVAN
Final 12/24/2020 Corrections Issued JOSEPH MCGARRY
Green Building Final 12/24/2020 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/24/2020 SGSOV Not Ready JOSEPH MCGARRY
Service/Power Release 12/24/2020 Not Ready for Inspection JOSEPH MCGARRY
Smoke Detectors 12/24/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 1/25/2021 Corrections Issued BRIAN SULLIVAN
Service/Power Release 1/25/2021 Approved BRIAN SULLIVAN
Final 2/25/2021 Conditional Approval BRIAN SULLIVAN
Green Building Final 2/25/2021 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/25/2021 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 2/25/2021 Approved BRIAN SULLIVAN
Final 3/8/2021 Corrections Issued BRIAN SULLIVAN
Final 3/12/2021 OK to Issue CofO BRIAN SULLIVAN