4149 1/2 N BRUNSWICK AVE 90039

Certificate Information: 4149 1/2 N BRUNSWICK AVE 90039

Application / Permit
17014-10000-02934
Plan Check / Job No.
B17LA10724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ENCLOSE PORTION OF COVERED PATIO (60 SF) TO CREATE ADDITIONAL AREA TO AN EXISTING REC-ROOM AND CONVERT TO ADU PER AB 2299.
Permit Issued
Issued on 8/17/2017
Issuing Office
Metro
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2017 APPLICANT
Assigned to Plan Check Engineer 6/20/2017 JAYDON NGUYEN
Corrections Issued 6/20/2017 JAYDON NGUYEN
Plan Check Approved 8/11/2017 LOC TRUONG
Issued 8/17/2017 LADBS
CofO in Progress 7/21/2018 LUIS ALVAREZ
No Progress 2/11/2023 MICHAEL PELHAM
CofO in Progress 2/27/2023 MICHAEL PELHAM
Permit Finaled 3/7/2023 DANIEL ORRANTE
CofO Issued 3/7/2023 DANIEL ORRANTE
Permit Finaled 3/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/20/2017 ROCHELLE DUNGCA
Sewer availability Cleared 6/20/2017 ROCHELLE DUNGCA
ZA Case Cleared 6/20/2017 ARIEL MORENO
ZA Case Cleared 6/20/2017 ARIEL MORENO
ZI Cleared 6/20/2017 ARIEL MORENO
Eng Process Fee Ord 176,300 Cleared 6/21/2017 ROCHELLE DUNGCA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/6/2017 Corrections Issued LUIS ALVAREZ
Footing/Foundation/Slab 12/1/2017 Approved LUIS ALVAREZ
Wood Frame 12/15/2017 Partial Approval LUIS ALVAREZ
ELECTRICAL-Rough 1/5/2018 Approved LUIS ALVAREZ
PLUMBING-Rough 1/5/2018 Corrections Issued LUIS ALVAREZ
PLUMBING-Rough 1/19/2018 Approved LUIS ALVAREZ
Wood Frame 1/19/2018 Approved LUIS ALVAREZ
Insulation 1/26/2018 Approved LUIS ALVAREZ
Interior/Exterior Lathing 2/2/2018 Approved DOMINIC DANERI
Drywall Nailing 3/2/2018 Approved LUIS ALVAREZ
Gas Test 3/2/2018 Not Ready for Inspection LUIS ALVAREZ
BUILDING-Rough-Frame 6/29/2018 Approved LUIS ALVAREZ
Final 6/29/2018 Corrections Issued LUIS ALVAREZ
Green Building Final 6/29/2018 Approved LUIS ALVAREZ
Green Building Rough 6/29/2018 Approved LUIS ALVAREZ
SGSOV-Seismic Gas S/O Valve 6/29/2018 SGSOV Approved LUIS ALVAREZ
Smoke Detectors 6/29/2018 Approved LUIS ALVAREZ
Final 7/6/2018 OK to Issue CofO LUIS ALVAREZ