4149 1/2 N BRUNSWICK AVE 90039
Certificate Information: 4149 1/2 N BRUNSWICK AVE 90039
- Application / Permit
- 17014-10000-02934
- Plan Check / Job No.
- B17LA10724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ENCLOSE PORTION OF COVERED PATIO (60 SF) TO CREATE ADDITIONAL AREA TO AN EXISTING REC-ROOM AND CONVERT TO ADU PER AB 2299.
- Permit Issued
- Issued on 8/17/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2017 | JAYDON NGUYEN |
| Corrections Issued | 6/20/2017 | JAYDON NGUYEN |
| Plan Check Approved | 8/11/2017 | LOC TRUONG |
| Issued | 8/17/2017 | LADBS |
| CofO in Progress | 7/21/2018 | LUIS ALVAREZ |
| No Progress | 2/11/2023 | MICHAEL PELHAM |
| CofO in Progress | 2/27/2023 | MICHAEL PELHAM |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
| CofO Issued | 3/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/20/2017 | ROCHELLE DUNGCA |
| Sewer availability | Cleared | 6/20/2017 | ROCHELLE DUNGCA |
| ZA Case | Cleared | 6/20/2017 | ARIEL MORENO |
| ZA Case | Cleared | 6/20/2017 | ARIEL MORENO |
| ZI | Cleared | 6/20/2017 | ARIEL MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2017 | ROCHELLE DUNGCA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/6/2017 | Corrections Issued | LUIS ALVAREZ |
| Footing/Foundation/Slab | 12/1/2017 | Approved | LUIS ALVAREZ |
| Wood Frame | 12/15/2017 | Partial Approval | LUIS ALVAREZ |
| ELECTRICAL-Rough | 1/5/2018 | Approved | LUIS ALVAREZ |
| PLUMBING-Rough | 1/5/2018 | Corrections Issued | LUIS ALVAREZ |
| PLUMBING-Rough | 1/19/2018 | Approved | LUIS ALVAREZ |
| Wood Frame | 1/19/2018 | Approved | LUIS ALVAREZ |
| Insulation | 1/26/2018 | Approved | LUIS ALVAREZ |
| Interior/Exterior Lathing | 2/2/2018 | Approved | DOMINIC DANERI |
| Drywall Nailing | 3/2/2018 | Approved | LUIS ALVAREZ |
| Gas Test | 3/2/2018 | Not Ready for Inspection | LUIS ALVAREZ |
| BUILDING-Rough-Frame | 6/29/2018 | Approved | LUIS ALVAREZ |
| Final | 6/29/2018 | Corrections Issued | LUIS ALVAREZ |
| Green Building Final | 6/29/2018 | Approved | LUIS ALVAREZ |
| Green Building Rough | 6/29/2018 | Approved | LUIS ALVAREZ |
| SGSOV-Seismic Gas S/O Valve | 6/29/2018 | SGSOV Approved | LUIS ALVAREZ |
| Smoke Detectors | 6/29/2018 | Approved | LUIS ALVAREZ |
| Final | 7/6/2018 | OK to Issue CofO | LUIS ALVAREZ |