1232-1234 W LILAC PL 90026
Certificate Information: 1232-1234 W LILAC PL 90026
- Application / Permit
- 17014-10000-02559
- Plan Check / Job No.
- B17LA09290
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX OVER BASEMENT GARAGE, (4 stalls ). fully sprinkler, NFPA-13D
- Permit Issued
- Issued on 7/11/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2017 | SAM CHANG |
| Corrections Issued | 7/6/2017 | SAM CHANG |
| Green Plans Picked Up | 7/6/2017 | APPLICANT |
| Quality Review Completed | 7/7/2017 | SUEN LIEU |
| Building Plans Picked Up | 8/29/2017 | APPLICANT |
| Applicant returned to address corrections | 8/10/2018 | SAM CHANG |
| Applicant returned to address corrections | 9/27/2018 | SAM CHANG |
| Applicant returned to address corrections | 10/10/2018 | SAM CHANG |
| Applicant returned to address corrections | 10/30/2018 | SAM CHANG |
| Applicant returned to address corrections | 4/3/2019 | SAM CHANG |
| Plan Check Approved | 7/9/2019 | SAM CHANG |
| Issued | 7/11/2019 | LADBS |
| CofO in Progress | 9/18/2024 | HAMIK HARTOUNIAN |
| CofO Issued | 9/19/2024 | DEROLD HAUFF |
| Permit Finaled | 9/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2017 | RAVIL MANAPOV |
| Address approval | Cleared | 8/29/2017 | RAVIL MANAPOV |
| Green Code | Cleared | 8/1/2018 | SARAH ABOULHOSN |
| Permit | Cleared | 10/30/2018 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2019 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 4/2/2019 | SOPHIE GABEL-SCHEINBAU |
| Housing rent stabilization | Cleared | 4/2/2019 | STEVEN HOFSTAD |
| Low Impact Development | Cleared | 4/2/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/2/2019 | CELINA MORENO |
| Sewer availability | Cleared | 4/2/2019 | CELINA MORENO |
| GPI Written Notices | Cleared | 7/9/2019 | SAM CHANG |
| Grading Pre-Inspection | Cleared | 7/9/2019 | SAM CHANG |
Contact Information
| Contractor | Shum Simon T Contractor; Lic. No.: 649012-B | 385 S LEMON #E383 WALNUT, CA 91789 |
| Engineer | , ; Lic. No.: C19689 | , |
| Engineer | Li, Dacheng David; Lic. No.: C58075 | 23240 RIDGELINE DR DIAMOND BAR, CA 91765 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/25/2019 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 7/25/2019 | Corrections Issued | DAVID CHAN |
| Footing/Foundation/Slab | 8/8/2019 | Partial Inspection | ROBERT VORHIS |
| METHANE-Barrier | 8/8/2019 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Subgrade | 8/8/2019 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 8/14/2019 | Not Ready for Inspection | RUBEN SALAS |
| METHANE-Barrier | 8/14/2019 | Not Ready for Inspection | RUBEN SALAS |
| METHANE-Subgrade | 8/14/2019 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 8/23/2019 | Partial Approval | RUBEN SALAS |
| METHANE-Barrier | 8/23/2019 | Approved | RUBEN SALAS |
| METHANE-Subgrade | 8/23/2019 | Approved | RUBEN SALAS |
| Footing/Foundation/Slab | 9/19/2019 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 10/8/2019 | Corrections Issued | DAVID CHAN |
| PLUMBING-Rough | 10/15/2019 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 10/31/2019 | Corrections Issued | DAVID CHAN |
| Footing/Foundation/Slab | 11/7/2019 | Partial Approval | DAVID CHAN |
| Masonry Wall/Backfill | 11/14/2019 | Partial Approval | AJA COLLAY |
| Masonry Wall/Backfill | 11/26/2019 | Partial Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 3/17/2020 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 3/17/2020 | Not Ready for Inspection | SCOTT FINNILA |
| METHANE-Rough | 3/17/2020 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 3/17/2020 | Not Ready for Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 10/7/2020 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/7/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/7/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 10/7/2020 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 10/7/2020 | Corrections Issued | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 10/7/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/26/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/26/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/30/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 11/5/2020 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 11/14/2020 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 11/24/2020 | Approved | SCOTT FINNILA |
| Final | 12/4/2020 | Partial Inspection | SCOTT FINNILA |
| Insulation | 12/4/2020 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 12/4/2020 | Conditional Approval | SCOTT FINNILA |
| Drywall Nailing | 12/14/2020 | Approved | RICHARD STEINBACH |
| Sewer | 2/9/2021 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 5/17/2021 | Partial Approval | SCOTT FINNILA |
| Final | 11/2/2021 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/2/2021 | Approved | THOMAS LOGRASSO |
| Green Building Final | 11/2/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 11/2/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 11/2/2021 | Approved | THOMAS LOGRASSO |
| Final | 6/3/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 6/3/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 6/3/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 6/23/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 6/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 6/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 8/18/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 8/18/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 8/18/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 8/18/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/9/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 4/23/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 4/24/2024 | Partial Inspection | THOMAS LOGRASSO |
| Green Building Final | 5/30/2024 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 8/7/2024 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 8/7/2024 | No Access for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 8/7/2024 | No Access for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/19/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Not Ready | WILLIAM SIERRA |
| Service/Power Release | 8/19/2024 | Not Ready for Inspection | WILLIAM SIERRA |
| Final | 8/20/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 8/23/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 9/18/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |