1232-1234 W LILAC PL 90026

Certificate Information: 1232-1234 W LILAC PL 90026

Application / Permit
17014-10000-02559
Plan Check / Job No.
B17LA09290
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX OVER BASEMENT GARAGE, (4 stalls ). fully sprinkler, NFPA-13D
Permit Issued
Issued on 7/11/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2017 APPLICANT
Assigned to Plan Check Engineer 6/22/2017 SAM CHANG
Corrections Issued 7/6/2017 SAM CHANG
Green Plans Picked Up 7/6/2017 APPLICANT
Quality Review Completed 7/7/2017 SUEN LIEU
Building Plans Picked Up 8/29/2017 APPLICANT
Applicant returned to address corrections 8/10/2018 SAM CHANG
Applicant returned to address corrections 9/27/2018 SAM CHANG
Applicant returned to address corrections 10/10/2018 SAM CHANG
Applicant returned to address corrections 10/30/2018 SAM CHANG
Applicant returned to address corrections 4/3/2019 SAM CHANG
Plan Check Approved 7/9/2019 SAM CHANG
Issued 7/11/2019 LADBS
CofO in Progress 9/18/2024 HAMIK HARTOUNIAN
CofO Issued 9/19/2024 DEROLD HAUFF
Permit Finaled 9/19/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/29/2017 RAVIL MANAPOV
Address approval Cleared 8/29/2017 RAVIL MANAPOV
Green Code Cleared 8/1/2018 SARAH ABOULHOSN
Permit Cleared 10/30/2018 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 4/2/2019 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 4/2/2019 SOPHIE GABEL-SCHEINBAU
Housing rent stabilization Cleared 4/2/2019 STEVEN HOFSTAD
Low Impact Development Cleared 4/2/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/2/2019 CELINA MORENO
Sewer availability Cleared 4/2/2019 CELINA MORENO
GPI Written Notices Cleared 7/9/2019 SAM CHANG
Grading Pre-Inspection Cleared 7/9/2019 SAM CHANG

Contact Information

Contractor Shum Simon T Contractor; Lic. No.: 649012-B 385 S LEMON #E383      WALNUT, CA 91789
Engineer , ; Lic. No.: C19689       ,
Engineer Li, Dacheng David; Lic. No.: C58075 23240 RIDGELINE DR      DIAMOND BAR, CA 91765

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/25/2019 Partial Approval DAVID CHAN
Footing/Foundation/Slab 7/25/2019 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 8/8/2019 Partial Inspection ROBERT VORHIS
METHANE-Barrier 8/8/2019 Not Ready for Inspection ROBERT VORHIS
METHANE-Subgrade 8/8/2019 Not Ready for Inspection ROBERT VORHIS
Footing/Foundation/Slab 8/14/2019 Not Ready for Inspection RUBEN SALAS
METHANE-Barrier 8/14/2019 Not Ready for Inspection RUBEN SALAS
METHANE-Subgrade 8/14/2019 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 8/23/2019 Partial Approval RUBEN SALAS
METHANE-Barrier 8/23/2019 Approved RUBEN SALAS
METHANE-Subgrade 8/23/2019 Approved RUBEN SALAS
Footing/Foundation/Slab 9/19/2019 Partial Approval DAVID CHAN
PLUMBING-Rough 10/8/2019 Corrections Issued DAVID CHAN
PLUMBING-Rough 10/15/2019 Partial Approval DAVID CHAN
Footing/Foundation/Slab 10/31/2019 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 11/7/2019 Partial Approval DAVID CHAN
Masonry Wall/Backfill 11/14/2019 Partial Approval AJA COLLAY
Masonry Wall/Backfill 11/26/2019 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 3/17/2020 Corrections Issued SCOTT FINNILA
Green Building Rough 3/17/2020 Not Ready for Inspection SCOTT FINNILA
METHANE-Rough 3/17/2020 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 3/17/2020 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 Approved ROBERT VORHIS
BUILDING-Rough-Frame 10/7/2020 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 10/7/2020 Approved OSVALDO PARAMO
Green Building Rough 10/7/2020 Approved OSVALDO PARAMO
HVAC-Rough 10/7/2020 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 10/7/2020 Corrections Issued OSVALDO PARAMO
Verify Sprinkler Sign Off 10/7/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/26/2020 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 10/26/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 10/30/2020 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Approved OSVALDO PARAMO
PLUMBING-Rough 11/5/2020 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 11/14/2020 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 11/24/2020 Approved SCOTT FINNILA
Final 12/4/2020 Partial Inspection SCOTT FINNILA
Insulation 12/4/2020 Approved SCOTT FINNILA
Interior/Exterior Lathing 12/4/2020 Conditional Approval SCOTT FINNILA
Drywall Nailing 12/14/2020 Approved RICHARD STEINBACH
Sewer 2/9/2021 Approved KATHRYN BUTTERWORTH
Underground Mechanical 5/17/2021 Partial Approval SCOTT FINNILA
Final 11/2/2021 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 11/2/2021 Approved THOMAS LOGRASSO
Green Building Final 11/2/2021 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/2/2021 SGSOV Not Ready THOMAS LOGRASSO
Service/Power Release 11/2/2021 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 11/2/2021 Approved THOMAS LOGRASSO
Final 6/3/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 6/3/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Not Ready THOMAS LOGRASSO
Service/Power Release 6/3/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 6/23/2022 Corrections Issued STUART CHAPMAN
Green Building Final 6/23/2022 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/23/2022 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 6/23/2022 Not Ready for Inspection STUART CHAPMAN
Final 8/18/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 8/18/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Not Ready THOMAS LOGRASSO
Service/Power Release 8/18/2023 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 8/18/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 4/9/2024 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 4/23/2024 Not Ready for Inspection THOMAS LOGRASSO
Pre-Inspection 4/24/2024 Partial Inspection THOMAS LOGRASSO
Green Building Final 5/30/2024 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 8/7/2024 No Access for Inspection HAMIK HARTOUNIAN
Final 8/7/2024 No Access for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 8/7/2024 No Access for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/14/2024 SGSOV Not Ready HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/19/2024 Not Ready for Inspection WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 8/19/2024 SGSOV Not Ready WILLIAM SIERRA
Service/Power Release 8/19/2024 Not Ready for Inspection WILLIAM SIERRA
Final 8/20/2024 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 8/23/2024 Approved HAMIK HARTOUNIAN
Final 8/23/2024 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Approved HAMIK HARTOUNIAN
Final 9/18/2024 OK to Issue CofO HAMIK HARTOUNIAN