5039 N MT ROYAL DR 90041

Certificate Information: 5039 N MT ROYAL DR 90041

Application / Permit
17014-10000-02442
Plan Check / Job No.
B17LA08830
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION (536 SQ FT) WITH NEW KITCHEN LOCATION, BATHROOM AND MASTER BEDROOM WITH NEW BALCONY OF 45 SQ FT; INTERIOR REMODEL
Permit Issued
Issued on 5/28/2021
Issuing Office
Current Status
Issued on 5/28/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/24/2017 APPLICANT
Assigned to Plan Check Engineer 6/22/2017 WEIWEI BREAKWELL
Corrections Issued 6/28/2017 WEIWEI BREAKWELL
Quality Review Completed 6/30/2017 JOHN VASQUEZ
Building Plans Picked Up 7/7/2017 APPLICANT
Green Plans Picked Up 7/7/2017 APPLICANT
Plan Check Approved 5/20/2021 LAMAR DAVIS
Issued 5/28/2021 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 3/12/2021 HOK CHI CHIU
Low Impact Development Cleared 3/29/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/1/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/5/2021 CELINA MORENO
Grading Pre-Inspection Cleared 4/16/2021 BRIAN MILLER
GPI Written Notices Cleared 4/29/2021 ROBERT HUGHES
Green Code Cleared 5/20/2021 LAMAR DAVIS

Contact Information

Contractor Owner-Builder       ,
Engineer Singh, Jasbir; Lic. No.: C38767 15095 CALLE DEL ORO      CHINO HILLS, CA 91709

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/11/2021 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/21/2021 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/23/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 6/28/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/28/2021 Approved HAMIK HARTOUNIAN
Masonry Wall/Backfill 7/1/2021 Corrections Issued SCOTT FINNILA
Masonry Wall/Backfill 7/6/2021 Partial Inspection COREY HUPP
Masonry Wall/Backfill 7/8/2021 Partial Approval HAMIK HARTOUNIAN
Masonry Wall/Backfill 7/9/2021 No Access for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 9/24/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 9/24/2021 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 9/24/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 9/24/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 9/24/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 10/7/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 10/7/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 10/7/2021 Corrections Issued CRAIG VAUGHAN
Wood Frame 10/7/2021 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 10/12/2021 No Access for Inspection CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 10/12/2021 Not Ready for Inspection ADAM ESCOTO
BUILDING-Rough-Frame 10/14/2021 Approved CRAIG VAUGHAN
Green Building Rough 10/14/2021 Approved CRAIG VAUGHAN
Insulation 10/14/2021 Corrections Issued CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 10/14/2021 Partial Approval CRAIG VAUGHAN
Insulation 10/19/2021 Partial Approval CRAIG VAUGHAN
Drywall Nailing 10/26/2021 Conditional Approval ROBERT VORHIS
Shower Pan 3/4/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/9/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/27/2022 Corrections Issued CRAIG VAUGHAN
Service/Power Release 8/12/2022 Approved ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 12/28/2023 Conditional Approval LILIANA PORTILLO
Wood Frame 1/10/2024 Partial Approval CRAIG VAUGHAN
Drywall Nailing 8/30/2024 Approved CRAIG VAUGHAN
Final 8/30/2024 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/30/2024 Approved CRAIG VAUGHAN
HVAC-Final 8/30/2024 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 8/30/2024 Approved CRAIG VAUGHAN