5039 N MT ROYAL DR 90041
Certificate Information: 5039 N MT ROYAL DR 90041
- Application / Permit
- 17014-10000-02442
- Plan Check / Job No.
- B17LA08830
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION (536 SQ FT) WITH NEW KITCHEN LOCATION, BATHROOM AND MASTER BEDROOM WITH NEW BALCONY OF 45 SQ FT; INTERIOR REMODEL
- Permit Issued
- Issued on 5/28/2021
- Issuing Office
- Current Status
- Issued on 5/28/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/24/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2017 | WEIWEI BREAKWELL |
| Corrections Issued | 6/28/2017 | WEIWEI BREAKWELL |
| Quality Review Completed | 6/30/2017 | JOHN VASQUEZ |
| Building Plans Picked Up | 7/7/2017 | APPLICANT |
| Green Plans Picked Up | 7/7/2017 | APPLICANT |
| Plan Check Approved | 5/20/2021 | LAMAR DAVIS |
| Issued | 5/28/2021 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/12/2021 | HOK CHI CHIU |
| Low Impact Development | Cleared | 3/29/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/1/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 4/16/2021 | BRIAN MILLER |
| GPI Written Notices | Cleared | 4/29/2021 | ROBERT HUGHES |
| Green Code | Cleared | 5/20/2021 | LAMAR DAVIS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh, Jasbir; Lic. No.: C38767 | 15095 CALLE DEL ORO CHINO HILLS, CA 91709 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/11/2021 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/21/2021 | Corrections Issued | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/28/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/28/2021 | Approved | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 7/1/2021 | Corrections Issued | SCOTT FINNILA |
| Masonry Wall/Backfill | 7/6/2021 | Partial Inspection | COREY HUPP |
| Masonry Wall/Backfill | 7/8/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 7/9/2021 | No Access for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/24/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/24/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 9/24/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 9/24/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/24/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/7/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 10/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| Wood Frame | 10/7/2021 | Partial Approval | CRAIG VAUGHAN |
| Deputy Wood Construction | 10/12/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 10/12/2021 | Not Ready for Inspection | ADAM ESCOTO |
| BUILDING-Rough-Frame | 10/14/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 10/14/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 10/14/2021 | Corrections Issued | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 10/14/2021 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 10/19/2021 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 10/26/2021 | Conditional Approval | ROBERT VORHIS |
| Shower Pan | 3/4/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 3/9/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 7/27/2022 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 8/12/2022 | Approved | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 12/28/2023 | Conditional Approval | LILIANA PORTILLO |
| Wood Frame | 1/10/2024 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 8/30/2024 | Approved | CRAIG VAUGHAN |
| Final | 8/30/2024 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 8/30/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 8/30/2024 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 8/30/2024 | Approved | CRAIG VAUGHAN |