8446 W KIRKWOOD DR 90046

Certificate Information: 8446 W KIRKWOOD DR 90046

Application / Permit
17014-10000-02366
Plan Check / Job No.
B17LA08626
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING "COMPLY WITH DEPARTMENT ORDER effective date 07/06/2004. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 7/13/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2017 APPLICANT
Assigned to Plan Check Engineer 6/1/2017 LARRY LEE
Corrections Issued 6/6/2017 LARRY LEE
Quality Review Completed 6/7/2017 PETER KIM
Building Plans Picked Up 6/8/2017 APPLICANT
Green Plans Picked Up 6/8/2017 APPLICANT
Applicant returned to address corrections 7/18/2017 LARRY LEE
Plan Check Approved 3/5/2018 LARRY LEE
Issued 7/13/2018 LADBS
CofO in Progress 3/8/2022 RAUL BARAJAS
Permit Finaled 5/4/2022 DEROLD HAUFF
CofO Issued 5/4/2022 DEROLD HAUFF
Permit Finaled 5/4/2022 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 8/24/2017 EDBER MACEDO
ZA Case Cleared 8/24/2017 EDBER MACEDO
Green Code Cleared 9/7/2017 WILLIAM ROSE
Low Impact Development Cleared 9/19/2017 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 9/26/2017 CELINA MORENO
Roof/Waste drainage to street Cleared 9/26/2017 CELINA MORENO

Contact Information

Contractor Ample Construction; Lic. No.: 957060-B 23442 CAMINITO NORTE      LAGUNA HILLS, CA 92653
Engineer Salehipour, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Engineer Yaghi, Shucri Ibrahim; Lic. No.: C43205 112 E CHAPMAN AVE STE D      ORANGE, CA 92866

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/23/2018 Partial Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 2/11/2020 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 2/11/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 2/11/2020 Not Ready for Inspection RAUL BARAJAS
Wood Frame 2/11/2020 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 2/18/2020 Corrections Issued RAUL BARAJAS
Green Building Rough 2/18/2020 Not Ready for Inspection RAUL BARAJAS
Wood Frame 2/18/2020 Not Ready for Inspection RAUL BARAJAS
Special/Order Compliance 4/29/2020 Approved CHRISTOPHER DELLEFIELD
Special/Order Compliance 9/4/2020 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 3/8/2022 Approved RAUL BARAJAS
Final 3/8/2022 OK to Issue CofO RAUL BARAJAS
Footing/Foundation/Slab 3/8/2022 Approved RAUL BARAJAS
Green Building Final 3/8/2022 Approved RAUL BARAJAS
Green Building Rough 3/8/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 3/8/2022 Approved RAUL BARAJAS