8446 W KIRKWOOD DR 90046
Certificate Information: 8446 W KIRKWOOD DR 90046
- Application / Permit
- 17014-10000-02366
- Plan Check / Job No.
- B17LA08626
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING "COMPLY WITH DEPARTMENT ORDER effective date 07/06/2004. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 7/13/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2017 | LARRY LEE |
| Corrections Issued | 6/6/2017 | LARRY LEE |
| Quality Review Completed | 6/7/2017 | PETER KIM |
| Building Plans Picked Up | 6/8/2017 | APPLICANT |
| Green Plans Picked Up | 6/8/2017 | APPLICANT |
| Applicant returned to address corrections | 7/18/2017 | LARRY LEE |
| Plan Check Approved | 3/5/2018 | LARRY LEE |
| Issued | 7/13/2018 | LADBS |
| CofO in Progress | 3/8/2022 | RAUL BARAJAS |
| Permit Finaled | 5/4/2022 | DEROLD HAUFF |
| CofO Issued | 5/4/2022 | DEROLD HAUFF |
| Permit Finaled | 5/4/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 8/24/2017 | EDBER MACEDO |
| ZA Case | Cleared | 8/24/2017 | EDBER MACEDO |
| Green Code | Cleared | 9/7/2017 | WILLIAM ROSE |
| Low Impact Development | Cleared | 9/19/2017 | ORVAL HERNANDEZ-MARCI |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2017 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 9/26/2017 | CELINA MORENO |
Contact Information
| Contractor | Ample Construction; Lic. No.: 957060-B | 23442 CAMINITO NORTE LAGUNA HILLS, CA 92653 |
| Engineer | Salehipour, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Engineer | Yaghi, Shucri Ibrahim; Lic. No.: C43205 | 112 E CHAPMAN AVE STE D ORANGE, CA 92866 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/23/2018 | Partial Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/11/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 2/11/2020 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 2/11/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 2/11/2020 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/18/2020 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 2/18/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 2/18/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 4/29/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Special/Order Compliance | 9/4/2020 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/8/2022 | Approved | RAUL BARAJAS |
| Final | 3/8/2022 | OK to Issue CofO | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/8/2022 | Approved | RAUL BARAJAS |
| Green Building Final | 3/8/2022 | Approved | RAUL BARAJAS |
| Green Building Rough | 3/8/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 3/8/2022 | Approved | RAUL BARAJAS |