9835 N MARCUS AVE 91042
Certificate Information: 9835 N MARCUS AVE 91042
- Application / Permit
- 17014-10000-02066
- Plan Check / Job No.
- B17LA07531
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH DETACHED GARAGE
- Permit Issued
- Issued on 9/13/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2017 | RICARDO RAMIREZ |
| Corrections Issued | 5/20/2017 | RICARDO RAMIREZ |
| Quality Review Completed | 5/24/2017 | STEVEN KIM |
| Building Plans Picked Up | 5/30/2017 | APPLICANT |
| Green Plans Picked Up | 5/31/2017 | APPLICANT |
| Applicant returned to address corrections | 7/14/2017 | RICARDO RAMIREZ |
| Plan Check Approved | 7/17/2017 | RICARDO RAMIREZ |
| Issued | 9/13/2017 | LADBS |
| CofO in Progress | 10/6/2022 | DAVID ANDERSON |
| CofO Issued | 11/17/2022 | MICHAEL SMITH |
| Permit Finaled | 11/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2017 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 6/6/2017 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 6/6/2017 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 7/14/2017 | BRIAN MILLER |
| Green Code | Cleared | 7/14/2017 | KATHRYN BUTTERWORTH |
| Private sewage disp. approval | Cleared | 7/14/2017 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Guzman, Jesus Enrique; Lic. No.: C27906 | 927 AMELUXEN AVE HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/5/2019 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 12/16/2019 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 12/20/2019 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 2/25/2020 | Partial Approval | BEAU COLLINS |
| Gas Test | 3/16/2020 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 11/9/2020 | Corrections Issued | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Not Ready for Inspection | BEAU COLLINS |
| Gas Test | 11/9/2020 | Partial Approval | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Not Ready for Inspection | BEAU COLLINS |
| Rough-Elec/Plmb/HVAC | 11/16/2020 | Not Ready for Inspection | BEAU COLLINS |
| BUILDING-Rough-Frame | 3/25/2021 | Corrections Issued | BEAU COLLINS |
| Green Building Rough | 3/25/2021 | Not Ready for Inspection | BEAU COLLINS |
| BUILDING-Rough-Frame | 2/9/2022 | Partial Inspection | MATTHEW NELSON |
| Green Building Rough | 2/9/2022 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/4/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 4/4/2022 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/4/2022 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 5/4/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 5/4/2022 | Corrections Issued | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/8/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/8/2022 | Approved | MATTHEW NELSON |
| Insulation | 6/13/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/13/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 6/29/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/22/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 9/22/2022 | Corrections Issued | DAVID ANDERSON |
| Final | 9/22/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 9/22/2022 | Approved | DAVID ANDERSON |
| HVAC-Final | 9/22/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 9/22/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 9/22/2022 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/28/2022 | Approved | DAVID ANDERSON |
| Final | 9/28/2022 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 9/28/2022 | Approved | DAVID ANDERSON |
| Final | 10/5/2022 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | DAVID ANDERSON |